Building Resilient Infrastructure and Communities FY 2021 Subapplication and Selection Status

Subapplication Summary

Selected Subapplications

Highlights

Status by State

The Building Resilient Infrastructure and Communities (BRIC) grant program provides proactive investment in resilience for communities are better prepared and remain resilient prior to a hurricane, flood or wildfire. BRIC provides funds annually for hazard mitigation planning and projects to reduce risk of damage before a disaster.

On August 1, FEMA announced the 53 projects selected from the national competition applications received. In addition, on May 19, FEMA announced the BRIC Round 1 selections for the tribal set-aside and the state and territory allocations.  

alert - info


In addition to project selections, the BRIC Program offers help to communities in the form non-financial Direct Technical Assistance (DTA). For this fiscal year, 20 eligible communities from more than 100 applications have been selected to receive subject matter expertise and partnership collaboration to bolster a community’s success with project development.

Visit the BRIC Direct Technical Assistance webpage for more information.

This announcement is not an award. The information below summarizes the status of all subapplications submitted, including a table showing Subapplications by State, submitted for this grant cycle.

Summary of Total Fiscal Year 2021 Subapplications

FEMA made $1.16 billion available for the Building Resilient Infrastructure and Communities (BRIC) and Flood Mitigation Assistance (FMA) grant programs in fiscal year 2021.

  • For BRIC, every state and territory, including 36 tribes, submitted 788 subapplications requesting $4.16 billion in federal cost share funding.
  • For Flood Mitigation Assistance, 25 states submitted 194 subapplications requesting $534 million in federal cost share funding.

The breakdown of available funding for fiscal year 2021 includes $1 billion for BRIC and $160 million for Flood Mitigation Assistance.

For the BRIC program, this includes an increase in set-aside grants for tribes—from $20 million to $25 million. The state and territory allocation also increased from $600,000 per applicant to $1 million per applicant for a total of $56 million in available funds.

Summary of the First Round of Subapplication Selections Announced on May 19

  • For BRIC, FEMA selected 316 subapplications totaling $65.7 million across 53 states and territories, including 27 tribes.
  • For Flood Mitigation Assistance, FEMA selected 22 subapplications totaling $25.5 million across 19 different communities in five states.

Subapplication Selections for the BRIC National Competition

In Fiscal Year 2021,FEMA selected projects from 19 states, including the District of Columbia, across all 10 FEMA Regions. The selected  projects have met the basic eligibility requirements and will enter the next phase of the awards review process. FEMA will provide funding through these selections for states, local communities, and District of Columbia for larger more complex infrastructure projects.

View full summaries of all competitive BRIC selections.

These selection announcements are not awards. FEMA will work with applicants “Identified for Further Review” to conduct programmatic reviews of the selected subapplications before making a final decision for funding. 

Reminder: As in previous years, funding requests exceeded the amounts available for Hazard Mitigation Assistance grant programs. This trend shows the need for more funding to reduce hazards in the United States.

The data shown below represents a summary of the subapplications. The table below lists additional information about subapplications by state.

For the subapplications identified for further review for the BRIC National Competition, 49% ($455.8 million) of the funding will be delivered to communities that meet one or more Justice40 interim criteria. Overall, for the Fiscal Year 2021 BRIC selections, FEMA achieved delivering nearly 50% of grant funding to disadvantaged communities.

As in previous years, BRIC and Flood Mitigation Assistance funding requests exceeded the amounts available for Hazard Mitigation Assistance grant programs. This trend shows the need for more funding to reduce hazards in the United States.

alert - info

For additional information or to ask questions, grant applicants should contact their FEMA regional offices.

BRIC Selected Subapplications in the Total Grant Cycle

FEMA received 788 subapplications for BRIC funding of which 369 have been selected for further review as part of the state and tribal set-aside.

Through the National Competition, FEMA selected 53 large competitive projects based on the highest composite score until the funding amount available had been reached.

For fiscal year 2021, FEMA received applications for $4.16 billion in federal cost share. The total proposed project costs exceeded $6.44 billion.

Geography Summary

In this grant cycle, 56 states and territories applied for BRIC. Of these, 12 states submitted projects that totaled more than $50 million or more in federal cost share funding.

Four states submitted projects with over $200 million federal cost share funding: California, Louisiana, Texas and Virginia.

FEMA received 72 subapplications from tribes requesting an estimated $27.95 million in federal cost share funding.

Subapplications Summary for BRIC

States, territories and tribes submitted applications in the following categories: Capability and Capacity Building Activities and Mitigation Projects.

The 20 communities selected to receive non-financial Direct Technical Assistance through BRIC represent five tribal governments, one territory and 15 states. Of the communities selected 17 out of 20 are disadvantaged communities, six of which are Economically Disadvantaged Rural Communities (EDRC).

From the previous year, subapplication requests for federal funding for Capability and Capacity Building Activities increased by 49%. These investments build a basis for future successful grant applications and projects.

The technical assistance that FEMA provides through BRIC grants can also help communities build applications to other funding sources. Over time, this can help diversify their funding options.

Building capacity takes time. The growth in requests in this funding area shows that communities value this support from FEMA.

Tribes who submitted subapplications in fiscal year 2021 requested significantly more funds in this grant cycle. Tribal applicants requested a total of $3.18 million to support applying building codes and standards, included modern building codes, and developing new plans. Compared to fiscal year 2020, tribal requests increased by 124%.

Types of Subapplications for the Fiscal Year 2021 Grant Cycle

This includes data from state and territory allocations and set-aside for tribes.

Uses of BRIC AssistanceNumber of Subapplications SelectedTotal Amount of Federal Cost Share
Mitigation Projects87$814.96 million
Capability and Capacity Building Activities220$40.37 million
Management Costs62$138.14 million
Direct Technical Assistance20N/A
Totals389$993.47 million

Project Activity Types Summary

There are various types of projects eligible for BRIC funding. The lists below reflect the top five project types by federal cost share requested and the number of subapplications requested and the number of subapplications (not including Management Costs).

alert - info

Definitions for these project types are available here.

TOP FIVE PROJECT TYPES BY FEDERAL SHARE REQUESTED

  1. Flood Control = $1.39 billion
  2. Utility/Infrastructure Protection = $1.26 billion
  3. Stabilization and Restoration = $219 million
  4. Mitigation Reconstruction = $101 million
  5. Retrofits = $100 million

TOP FIVE PROJECT TYPES BY NUMBER OF SUBAPPLICATIONS

  1. Flood Control = 144 subapplications
  2. Project Scoping (Engineering, Environmental, Feasibility and/or Benefit-Cost Analysis) = 125 subapplications
  3. Utility/Infrastructure Protection = 109 subapplications
  4. Plan Update = 61 subapplications
  5. Safe Room/Shelters = 32 subapplications

Highlights of the Fiscal Year 2021 BRIC Subapplications

Justice40

The BRIC program is one of several federal agency programs participating in Justice40, a Biden-Harris Administration initiative to prioritize federal investments benefitting disadvantaged communities. The Fiscal Year 2021 grant cycle focused on advancing support and access for underserved communities.

FEMA set a baseline to achieving the Justice40 Initiative goals which prioritize delivering at least 40% of the overall benefits to disadvantaged communities. This year FEMA established a baseline within the BRIC and Flood Mitigation Assistance grant programs to achieve that goal and will continue to build on the work we have done to ensure equitable outcomes.

FEMA anticipates continued coordination with the Biden Administration and other federal agencies with Justice40 covered programs. Examples of FEMA's commitment to prioritize equity include:

  • Building Resilient Infrastructure and Communities (BRIC): City of Gastonia, North Carolina: Duharts Creek is located along the east side of the city. Frequent, increasingly severe, rain events have left the area vulnerable to flooding and has caused significant erosion along the banks. This federal grant funding will restore the stream, stabilize the creek bank and realign critical water and power infrastructure. This design approach emphasizes nature-based solutions and materials with several recommendations including bank regrading, natural-fiber erosion control matting and native plantings. The goal is to reduce the severity of erosion and encroachment from future flood events. These efforts will be completed in two phases. Phase one includes notice of grant award, preliminary design, permitting, and final design. Phase two will include bidding and construction.

Expanded Selections from Fiscal Year 2020 Cycle

In comparing data and statistics to the fiscal year 2020 grant cycle, the BRIC program expanded selections and made improvements.

  • FEMA made more selections across all 10 FEMA regions, including 53 states and territories, the District of Columbia and 27 tribes.
    • Twelve states, or 63% of all states, will be first time recipients for competitive BRIC selections
    • Competitive project subapplication success rate increased from 4% to 14% in FY21
    • Nineteen states received BRIC Competitive Grant Funds in FY21 versus 10 states in FY20 (90% increase)
    • Most states that received BRIC Competitive funds in both years saw an annual increase in their competitive funds as well
  • Non-coastal states will receive more than 20% of funding in the competitive selection.
    • The states of Wisconsin and Wyoming were competitive this year even without state-level building code points. This demonstrates that applications can be competitive without state-level building codes points in years with high amounts of available funding.
    • The projects selected for this BRIC grant cycle will invest in mitigation in a variety of ways and demonstrate FEMA’s commitment to equity and the equitable distribution of project selections around the nation.

FY 2021 Building Resilient Infrastructure and Communities Subapplicant Status

The below table shows each subapplication status by state.  For this grant cycle, FEMA made two announcements.  In May, the status of subapplication selections for the Non-Financial Direct Technical Assistance communities, tribal set-aside and the state and territory allocations were announced.  In August, FEMA announced the national competition selections for BRIC.

Learn about the definition of each status description:

State Subgrant ID Subapplication Type Subapplication Title Eligible Federal Cost Share Final Selection Status
Alabama EMA-2021-BR-002-0002 Project Baldwin County Emergency Diesel Generator Acquisition and Installation $883,840.80 Identified for Further Review - Round 1
Alabama EMA-2021-BR-002-0003 Management cost Management Cost $116,004.11 Identified for Further Review - Round 1
Alabama EMA-2021-BR-002-0001 Project City of Mobile - Severe Weather Attenuation Tanks & Lift Station Program Not Selected Not Selected for Further Review
Alaska EMS-2021-BR-026-0001 Management cost Management Costs Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-026-0002 Plan Hazard Mitigation Plan Grant Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-085-0004 Plan Prince of Wales Island, Alaska Multi-Jurisdictional Hazard Mitigation Plan Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-085-0006 Project scoping Tsunami early warning research: Noyes Canyon Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-085-0007 Project Klawock Hazard Education Program Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-090-0001 Plan ICAS New Hazard Mitigation Plan Development Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-091-0003 Plan Qawalangin Tribe of Unalaska Tribal Hazard Mitigation Plan Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-097-0001 Management cost Management Costs Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-097-0002 Plan Native Village of Larsen Bay Tribal Hazard Mitigation Plan Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-098-0001 Management cost Management Costs Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-098-0002 Plan Native Village of Hooper Bay Tribal Hazard Mitigation Plan Not Selected Did not meet HMA Requirements
Alaska EMS-2021-BR-040-0001 Project scoping Chester Lake Reservoir Project $774,900.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-071-0001 Project scoping Goldenview Middle School Drainage - Design Study Report $225,000.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-071-0002 Project scoping Bettye Davis East Anchorage High School Benson Building Seismic Safety Improvements - Planning $135,000.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-071-0004 Plan Alaska Hazard Mitigation Plan Grant $411,210.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-071-0005 Management cost State of Alaska Management Costs $102,828.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-072-0001 Project scoping Chistochina River Flood Mitigation Scoping $999,781.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-072-0002 Management cost Chistochina River Flood Mitigation Management Costs $113,612.60 Identified for Further Review - Round 1
Alaska EMS-2021-BR-073-0001 Project Napakiak Managed Retreat Phase One: 10 Home Relocations $2,239,044.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-075-0001 Plan Chenega Hazard Mitigation Plan $55,853.10 Identified for Further Review - Round 1
Alaska EMS-2021-BR-075-0002 Management cost Chenega Hazard Mitigation Plan Management Costs $6,205.90 Identified for Further Review - Round 1
Alaska EMS-2021-BR-085-0001 Project scoping Klawock Drinking Water Storage/Reverse Osmosis Plant $68,638.50 Identified for Further Review - Round 1
Alaska EMS-2021-BR-085-0002 Project scoping Klawock Emergency Shelter Design Scoping $153,796.50 Identified for Further Review - Round 1
Alaska EMS-2021-BR-085-0003 Project scoping Backup Generator for Water Treatment Plant Scoping $92,358.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-085-0005 Management cost KCA Management Costs Subapplication $34,977.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-086-0001 Project scoping Rocky River Basin Project Scoping $697,250.60 Identified for Further Review - Round 1
Alaska EMS-2021-BR-086-0002 Management cost Rocky River Basin Management Cost $79,232.90 Identified for Further Review - Round 1
Alaska EMS-2021-BR-091-0001 Management cost Qawalangin Management Costs $50,000.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-091-0002 Plan Feasibility and Framework for Establishing Mutual Aid for Disaster Support $180,000.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-091-0004 Plan Resilient Building Code Adoption Support $270,000.00 Identified for Further Review - Round 1
Alaska EMS-2021-BR-101-0001 Plan NTC Emergency Operations Plan Update $144,564.37 Identified for Further Review - Round 1
Alaska EMS-2021-BR-071-0003 Project University of Alaska Butrovich building seismic retrofit Not Selected Not Selected for Further Review
Alaska EMS-2021-BR-071-0006 Project Salmon Creek MP4.8 - MP5.95 Not Selected Not Selected for Further Review
American Samoa EMF-2021-BR-069-0004 Plan Territorial Integrated Geospatial Framework Not Selected Did not meet HMA Requirements
American Samoa EMF-2021-BR-069-0009 Project American Samoa Tsunami Siren System Not Selected Did not meet HMA Requirements
American Samoa EMF-2021-BR-069-0006 Project scoping ASCC Drainage $270,000.00 Identified for Further Review - Round 1
American Samoa EMF-2021-BR-069-0007 Plan Hazard Mitigation Plan Update $374,588.33 Identified for Further Review - Round 1
American Samoa EMF-2021-BR-069-0008 Management cost State Management Cost $71,620.93 Identified for Further Review - Round 1
American Samoa EMF-2021-BR-069-0001 Project Route 014 Drainage Mitigation Not Selected Not Selected for Further Review
American Samoa EMF-2021-BR-069-0002 Project Aunu'u Wharf Reconstruction Not Selected Not Selected for Further Review
American Samoa EMF-2021-BR-069-0003 Project Feeder-6 Power Line Conversion from Overhead to Underground Not Selected Not Selected for Further Review
American Samoa EMF-2021-BR-069-0005 Project Feeder 9 Overhead to Underground Primary Line Conversion Not Selected Not Selected for Further Review
Arizona EMF-2021-BR-018-0002 Project City of St. Johns Police Department Emergency Backup Generator Not Selected Did not meet HMA Requirements
Arizona EMF-2021-BR-018-0003 Project City of Bisbee Bridge Mitigation Project Not Selected Did not meet HMA Requirements
Arizona EMF-2021-BR-018-0010 Project Museum Flood Area, Channel Improvement Project Not Selected Did not meet HMA Requirements
Arizona EMF-2021-BR-018-0001 Management cost Arizona Management Costs $36,026.51 Identified for Further Review - Round 1
Arizona EMF-2021-BR-018-0006 Project scoping Landslide mapping along the US Route 60 corridor, Florence Junction to Show Low $75,199.60 Identified for Further Review - Round 1
Arizona EMF-2021-BR-018-0011 Project scoping Assessing post-wildfire flow hazards for mitigation in Gila County $196,174.21 Identified for Further Review - Round 1
Arizona EMF-2021-BR-018-0004 Project Lower Highland Wash Flood Control Project Not Selected Not Selected for Further Review
Arizona EMF-2021-BR-018-0005 Project ACD2 C-328 Fort Defiance Flood Mitigation Not Selected Not Selected for Further Review
Arizona EMF-2021-BR-018-0007 Project City of Bisbee/ Arizona Water Co. Fire Suppression System Mitigation Not Selected Not Selected for Further Review
Arizona EMF-2021-BR-018-0008 Project South Mt. Elden Flood Mitigation Project Not Selected Not Selected for Further Review
Arizona EMF-2021-BR-018-0009 Project Millet Swale Dam, Hazard Mitigation Project Not Selected Not Selected for Further Review
Arizona EMF-2021-BR-018-0012 Project Linda Vista culvert upsizing - post-wildfire flood mitigation Not Selected Not Selected for Further Review
Arizona EMF-2021-BR-018-0013 Project RWRD Tres Rios WRF Microgrid Generator & Solar Power Resiliency Project Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0004 Project Clarendon Drainage Project Not Selected Did not meet HMA Requirements
Arkansas EMT-2021-BR-133-0027 Project Clarendon Infrastructure (WW) Project Not Selected Did not meet HMA Requirements
Arkansas EMT-2021-BR-133-0001 Management cost Arkansas State Management Costs $131,063.78 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0003 Project scoping Humnoke Drainage Study Project Scoping $38,593.75 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0005 Plan Chicot County MultiJurisdiction Hazard Mitigation Plan $26,250.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0006 Project Mountain View School District Safe Room $490,147.50 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0007 Plan Pike County MultiJurisdiction Hazard Mitigation Plan $26,250.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0008 Project scoping Centennial Creek Drainage Study & Centennial Creek from Tyler Street to College Avenue $115,520.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0011 Plan Johnson County Hazard Mitigation Plan Update $30,000.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0013 Plan Montgomery County Hazard Mitigation Plan Update $30,000.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0014 Plan Hot Spring County Hazard Mitigation Plan Update $30,000.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0017 Project scoping 2021 Windchime Bridge Mitigation Project in Sherwood $74,000.25 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0018 Plan Clark County Hazard Mitigation Plan Update $30,000.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0021 Plan Jefferson County Hazard Mitigation Plan Update $52,520.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0025 Plan Ashley County MultiJurisdiction Hazard Mitigation Plan Update $26,250.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0030 Plan Perry County Hazard Mitigation Plan Update $30,000.00 Identified for Further Review - Round 1
Arkansas EMT-2021-BR-133-0002 Project Saline County Drainage Lower Ark/Maumelle Watershed Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0009 Project Jacksonville Rocky Branch Drainage Improvements Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0010 Project Mt. Vernon-Enola Elementary School Safe Room Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0012 Project Monroe County Knights and Dials Creeks Drainage Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0015 Project Saline County Drainage - Upper Saline Watershed Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0016 Project Danville School Safe Room Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0019 Project Des Arc Public School Safe Room Projects Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0020 Project Heber Springs Drainage Improvement Project Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0022 Project North Little Rock Dixie Addition Stormwater Lift Station Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0023 Project Cabot Railroad Drainage Improvement and Drainage Study Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0024 Project Dardanelle Middle School Safe Room Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0026 Project Jacksonville Bayou Meto Bridge Improvements Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0028 Project North Little Rock East Bethany Road Drainage Improvement Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0029 Project Dardanelle Intermediate School Safe Room Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0031 Project North Little Rock Magnolia/Olive Streets Drainage Improvement Not Selected Not Selected for Further Review
Arkansas EMT-2021-BR-133-0032 Project Northlake Road Drainage Improvements Not Selected Not Selected for Further Review
California EMF-2021-BR-058-0002 Plan Robinson Rancheria Tribal Community Emergency Management Plan Not Selected Did not meet HMA Requirements
California EMF-2021-BR-085-0002 Project Planet Pala Information Campaign Not Selected Did not meet HMA Requirements
California EMF-2021-BR-089-0005 Project Tulare County Drought Resiliency and Flood Mitigation Project at McKay Point Not Selected Did not meet HMA Requirements
California EMF-2021-BR-089-0014 Project City of Pacifica Beach Blvd. Infrastructure Resiliency Project Not Selected Did not meet HMA Requirements
California EMF-2021-BR-017-0001 Project Coyote Valley Band of Pomo Indians Russian Riverbank Stabilization Project $5,315,264.32 Identified for Further Review - Round 1
California EMF-2021-BR-058-0001 Project scoping Robinson Rancheria Microgrid Feasibility Study $166,797.00 Identified for Further Review - Round 1
California EMF-2021-BR-079-0001 Project Dry Creek Rancheria Wildfire Resilience Project $247,354.50 Identified for Further Review - Round 1
California EMF-2021-BR-085-0001 Project Pala Building Codes Project $286,125.00 Identified for Further Review - Round 1
California EMF-2021-BR-089-0003 Management cost California State Management Costs $25,452,553.49 Identified for Further Review - Round 1
California EMF-2021-BR-089-0004 Project scoping State Coastal Conservancy Sonoma Creek Flood Mitigation and Restoration Project Scoping $540,096.60 Identified for Further Review - Round 1
California EMF-2021-BR-089-0007 Project scoping Project Scoping: Santa Cruz County - Flood Hazard Mitigation Project $300,000.00 Identified for Further Review - Round 1
California EMF-2021-BR-089-0012 Project scoping Port of SF Project Scoping Innovative Nature-Based Mitigations for Seawall Multi-Hazards $159,900.00 Identified for Further Review - Round 1
California EMF-2021-BR-092-0001 Project Archer Road Repair $377,556.15 Identified for Further Review - Round 1
California EMF-2021-BR-096-0001 Plan New Hazard Mitigation Plan for the Jamul Indian Village of California $92,010.00 Identified for Further Review - Round 1
California EMF-2021-BR-099-0001 Plan Resilient Augustine Information Campaign $392,850.00 Identified for Further Review - Round 1
California EMF-2021-BR-099-0002 Plan Augustine Building Codes Adoption and Land Use Plan $217,500.00 Identified for Further Review - Round 1
California EMF-2021-BR-089-0001 Project Multi-Family Soft-Story Retrofit Program $20,200,000.00 Identified for Further Review - Round 2
California EMF-2021-BR-089-0002 Project City of Healdsburg Water Resiliency Integrating Groundwater in Healdsburg Through ASR $6,066,080.88 Identified for Further Review - Round 2
California EMF-2021-BR-089-0006 Project Imperial Irrigation District K-Line Transmission Hardening Project $23,888,095.86 Identified for Further Review - Round 2
California EMF-2021-BR-089-0008 Project Grimes Floodplain Restoration & Levee Resiliency Project $18,923,625.16 Identified for Further Review - Round 2
California EMF-2021-BR-089-0009 Project City of Imperial Beach Bayside Community Resiliency: The Living Levee Project $15,160,988.50 Identified for Further Review - Round 2
California EMF-2021-BR-089-0010 Project Orange County – Nature-Based Shoreline Adaptation Project $9,799,793.00 Identified for Further Review - Round 2
California EMF-2021-BR-089-0011 Project Nature-based Mitigation & Wildfire Retrofitting for Climate Resiliency in Nevada County $31,034,243.00 Identified for Further Review - Round 2
California EMF-2021-BR-089-0013 Project Belvedere Lagoon Coastal Levee System Resiliency Project $15,610,602.04 Identified for Further Review - Round 2
California EMF-2021-BR-089-0015 Project Kern County Willow Springs Water Bank Drought Mitigation Project $39,496,828.00 Identified for Further Review - Round 2
Colorado EMD-2021-BR-060-0001 Project Skeel Reservoir Hazard Mitigation Not Selected Did not meet HMA Requirements
Colorado EMD-2021-BR-060-0008 Project Colorado Front Range Wildfire Mitigation Not Selected Did not meet HMA Requirements
Colorado EMD-2021-BR-060-0009 Project Project 7 Regional Water Supply and Drought Mitigation Program Not Selected Did not meet HMA Requirements
Colorado EMD-2021-BR-060-0003 Management cost State Management Costs $160,000.00 Identified for Further Review - Round 1
Colorado EMD-2021-BR-060-0007 Project scoping Scoping/Design for 12th Street Outfall $1,000,000.00 Identified for Further Review - Round 1
Colorado EMD-2021-BR-060-0002 Project Monument Creek at Mark Dabling Not Selected Not Selected for Further Review
Colorado EMD-2021-BR-060-0004 Project Cottonwood Creek at Powers Not Selected Not Selected for Further Review
Colorado EMD-2021-BR-060-0005 Project South Englewood Flood Reduction Project Not Selected Not Selected for Further Review
Colorado EMD-2021-BR-060-0006 Project Crystal Lakes Fuels Mitigation Not Selected Not Selected for Further Review
Colorado EMD-2021-BR-060-0010 Project Sand Creek, Galley to Palmer Park Not Selected Not Selected for Further Review
Colorado EMD-2021-BR-060-0011 Project Eisenhower Johnson Memorial Tunnel Generator Replacement Not Selected Not Selected for Further Review
Colorado EMD-2021-BR-060-0012 Project Town of Red Cliff Rockfall Mitigation Not Selected Not Selected for Further Review
Colorado EMD-2021-BR-060-0013 Project Coal Creek - County Line Road Flood Mitigation Not Selected Not Selected for Further Review
Connecticut EMB-2021-BR-002-0006 Project scoping Project Scoping - Langer Pond Dam Not Selected Did not meet HMA Requirements
Connecticut EMB-2021-BR-002-0007 Plan Regional Natural Hazard Mitigation Plan Update Not Selected Did not meet HMA Requirements
Connecticut EMB-2021-BR-002-0003 Management cost DESPP/DEMHS Management Cost $5,201,343.60 Identified for Further Review - Round 1
Connecticut EMB-2021-BR-002-0004 Project scoping Windham Water Works Reservoir Infrastructure Project Scoping, Concept Design, and Hazard Mitigation $100,800.00 Identified for Further Review - Round 1
Connecticut EMB-2021-BR-002-0013 Project scoping Bridgeport Flood Mitigation - Project Scoping $675,000.00 Identified for Further Review - Round 1
Connecticut EMB-2021-BR-002-0002 Project Harbor Brook Flood Control/100 Hanover Street Demolition Project in Meriden $303,187.50 Identified for Further Review - Round 2
Connecticut EMB-2021-BR-002-0005 Project City of New Haven Inland and Coastal Flood Resiliency Project $25,094,886.00 Identified for Further Review - Round 2
Connecticut EMB-2021-BR-002-0008 Project Meriden Harbor Brook Flood Resilience $11,165,250.00 Identified for Further Review - Round 2
Connecticut EMB-2021-BR-002-0001 Project East Lyme Sewer Pump Station Flood Mitigation Not Selected Not Selected for Further Review
Connecticut EMB-2021-BR-002-0009 Project COWH Sewer Outfall Resilience Subgrant Not Selected Not Selected for Further Review
Connecticut EMB-2021-BR-002-0010 Project Department of Transportation Utility & Route 1 Drainage Improvement Not Selected Not Selected for Further Review
Connecticut EMB-2021-BR-002-0011 Project East Branch Trout Brook Culvert Replacements Not Selected Not Selected for Further Review
Connecticut EMB-2021-BR-002-0012 Project City of Stamford Pump Station Improvements Not Selected Not Selected for Further Review
Delaware EMP-2021-BR-050-0001 Project scoping Lower Brandywine River Flooding Study and Mitigation Strategy $500,000.00 Identified for Further Review - Round 1
Delaware EMP-2021-BR-050-0002 Management cost Delaware Management Costs $66,667.50 Identified for Further Review - Round 1
District Of Columbia EMP-2021-BR-057-0001 Project scoping Project Scoping for FloodSmart Homes Retrofit $244,053.00 Identified for Further Review - Round 1
District Of Columbia EMP-2021-BR-057-0002 Management cost DC Management Costs $3,080,207.97 Identified for Further Review - Round 1
District Of Columbia EMP-2021-BR-057-0005 Project scoping Project Scoping for Living Shoreline in Buzzard Point neighborhood in Southwest $242,987.00 Identified for Further Review - Round 1
District Of Columbia EMP-2021-BR-057-0006 Project scoping Project Scoping For Recreation Center Resilience Hubs $212,960.00 Identified for Further Review - Round 1
District Of Columbia EMP-2021-BR-057-0007 Project scoping Project Scoping for DC Kenilworth Park/Watts Branch Environmental Study $300,000.00 Identified for Further Review - Round 1
District Of Columbia EMP-2021-BR-057-0004 Project Blue Plains Advanced Wastewater Treatment Plant Floodwall Segments A, B, and D $20,319,075.00 Identified for Further Review - Round 2
District Of Columbia EMP-2021-BR-057-0003 Project DC Water Backwater Valve Rebate Program Not Selected Not Selected for Further Review
Florida EMA-2021-BR-152-0011 Project Pasco County - Green Key Drainage Not Selected Did not meet HMA Requirements
Florida EMA-2021-BR-152-0015 Project Charlotte County Leachate Plant Generator Project - LPGP Not Selected Did not meet HMA Requirements
Florida EMA-2021-BR-152-0016 Project Flagler County Emergency Operations Center Hardening Not Selected Did not meet HMA Requirements
Florida EMA-2021-BR-152-0017 Project Toho Water Authority Drought Mitigation Project Not Selected Did not meet HMA Requirements
Florida EMA-2021-BR-133-0001 Project scoping Hollywood Reservation C-10 Spur Canal Drainage Study Identified for Further Review - Round 1
Florida EMA-2021-BR-152-0001 Project City of Tampa Fire Station #13 Wind Mitigation $497,887.37 Identified for Further Review - Round 1
Florida EMA-2021-BR-152-0006 Project City of Tampa Fire Station #3 Wind Mitigation $423,806.12 Identified for Further Review - Round 1
Florida EMA-2021-BR-152-0007 Management cost Florida Management Costs $10,526,614.02 Identified for Further Review - Round 1
Florida EMA-2021-BR-152-0012 Project Standby Generators for Jefferson County Volunteer Fire Department Stations $26,404.00 Identified for Further Review - Round 1
Florida EMA-2021-BR-152-0003 Project COJ / JEA Buckman WRF Outfall, Flood Mitigation and WW Reliability Enhancement Project $23,177,551.25 Identified for Further Review - Round 2
Florida EMA-2021-BR-152-0005 Project SFWMD Building Resiliency with Gray and Green Infrastructure, C-8 Basin of Miami-Dade $49,999,463.00 Identified for Further Review - Round 2
Florida EMA-2021-BR-152-0002 Project City of Tampa Fire Station #16 Wind Mitigation Not Selected Not Selected for Further Review
Florida EMA-2021-BR-152-0004 Project Glen Springs Run Creek Restoration Not Selected Not Selected for Further Review
Florida EMA-2021-BR-152-0008 Project City of Tampa Fire Station #18 Wind Mitigation Not Selected Not Selected for Further Review
Florida EMA-2021-BR-152-0009 Project City of Tampa Fire Station #12 Wind Mitigation Not Selected Not Selected for Further Review
Florida EMA-2021-BR-152-0010 Project City of Atlantic Beach, Stanley Road Flood Mitigation Not Selected Not Selected for Further Review
Florida EMA-2021-BR-152-0013 Project City of Atlantic Beach, Cutlass Drive Box Culvert Replacement Not Selected Not Selected for Further Review
Florida EMA-2021-BR-152-0014 Project City of Port St. Lucie Water Control Structure Improvements Not Selected Not Selected for Further Review
Georgia EMA-2021-BR-116-0005 Project Smart Grid for the City of Acworth Not Selected Did not meet HMA Requirements
Georgia EMA-2021-BR-116-0006 Project Stream Restoration and Flood Control in the Headwaters of the Flint Watershed Not Selected Did not meet HMA Requirements
Georgia EMA-2021-BR-116-0010 Project Emory University Microgrid Not Selected Did not meet HMA Requirements
Georgia EMA-2021-BR-116-0001 Project BRIC Application $41,785.44 Identified for Further Review - Round 1
Georgia EMA-2021-BR-116-0003 Plan Enhancing Future Flood Resiliency with Green Infrastructure in Glynn County $190,348.11 Identified for Further Review - Round 1
Georgia EMA-2021-BR-116-0004 Management cost Management Grant $4,394,634.68 Identified for Further Review - Round 1
Georgia EMA-2021-BR-116-0007 Project scoping Smart Sea Level Sensors $219,375.00 Identified for Further Review - Round 1
Georgia EMA-2021-BR-116-0008 Project Wind Retrofit - Facilities Maintenance & Human Resources Buildings $33,948.45 Identified for Further Review - Round 1
Georgia EMA-2021-BR-116-0011 Project 1247 Rowland Road Property Acquisition $287,364.30 Identified for Further Review - Round 1
Georgia EMA-2021-BR-116-0002 Project Springfield Canal Improvement/Historic Carver Village and Cloverdale Flood Reduction Project $30,147,160.00 Identified for Further Review - Round 2
Georgia EMA-2021-BR-116-0009 Project Marietta Power and Water Smart Grid Not Selected Not Selected for Further Review
Guam EMF-2021-BR-086-0003 Project scoping GIAA Ground Support Equipment Inclement Weather Facility Not Selected Did not meet HMA Requirements
Guam EMF-2021-BR-086-0008 Project scoping GIAA Fire Alarm/Fire Suppression Infrastructure Upgrade Not Selected Did not meet HMA Requirements
Guam EMF-2021-BR-086-0010 Project Namo Flood Control and Bank Stabilization Not Selected Did not meet HMA Requirements
Guam EMF-2021-BR-086-0004 Project scoping Manell: Restoring the Manell River's Natural Flowpath $667,360.00 Identified for Further Review - Round 1
Guam EMF-2021-BR-086-0006 Project scoping GIAA Underground Utility Infrastructure Relocation and Power Generation $332,640.00 Identified for Further Review - Round 1
Guam EMF-2021-BR-086-0009 Management cost Guam 2021 Technical Assistance $177,975.00 Identified for Further Review - Round 1
Guam EMF-2021-BR-086-0001 Project GCC Building 600 Retrofit Project Not Selected Not Selected for Further Review
Guam EMF-2021-BR-086-0002 Project Umatac Pre-Storm River Maintenance and Bank Stabilization Not Selected Not Selected for Further Review
Guam EMF-2021-BR-086-0005 Project Yona - Tier 2 Shelter Hardening Not Selected Not Selected for Further Review
Guam EMF-2021-BR-086-0007 Project Manell Reforestation Not Selected Not Selected for Further Review
Guam EMF-2021-BR-086-0011 Project GIAA Information Technology Fiber Optic Infrastructure Not Selected Not Selected for Further Review
Hawaii EMF-2021-BR-006-0002 Project scoping Department of Transportation Scoping Activity - Airport Microgrids and Transportation Resilience $375,000.00 Identified for Further Review - Round 1
Hawaii EMF-2021-BR-006-0004 Project scoping Kapalama Canal Flood Control Project Scoping $300,000.00 Identified for Further Review - Round 1
Hawaii EMF-2021-BR-006-0006 Management cost Hawaii Management Costs $114,843.75 Identified for Further Review - Round 1
Hawaii EMF-2021-BR-006-0007 Plan City and County of Honolulu Hazard Mitigation Plan Update $200,000.00 Identified for Further Review - Round 1
Hawaii EMF-2021-BR-006-0001 Project Hawaii Convention Center Structural Hardening Not Selected Not Selected for Further Review
Hawaii EMF-2021-BR-006-0003 Project Critical Customer Hubs - Ko?olaupoko Not Selected Not Selected for Further Review
Hawaii EMF-2021-BR-006-0005 Project Coco Palms Resort Acquisition and Demolition Not Selected Not Selected for Further Review
Idaho EMS-2021-BR-078-0002 Management cost IOEM Management Costs $64,500.00 Identified for Further Review - Round 1
Idaho EMS-2021-BR-078-0004 Project scoping Little Wood River Flood Control $232,500.00 Identified for Further Review - Round 1
Idaho EMS-2021-BR-078-0006 Project scoping Cascade Stormwater Scoping Project $225,000.00 Identified for Further Review - Round 1
Idaho EMS-2021-BR-078-0007 Plan Fremont County AHMP $26,250.00 Identified for Further Review - Round 1
Idaho EMS-2021-BR-078-0001 Project Custer County Mackay Dam Not Selected Not Selected for Further Review
Idaho EMS-2021-BR-078-0003 Project Power line Conversion to Underground - Hayden Lake Not Selected Not Selected for Further Review
Idaho EMS-2021-BR-078-0005 Project Powerline Conversion to Underground - Farragut State Park / US Naval Warfare Center Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0002 Project Aquisistions Not Selected Did not meet HMA Requirements
Illinois EMC-2021-BR-062-0009 Project Village of Crestwood Storm Sewer Upgrades Not Selected Did not meet HMA Requirements
Illinois EMC-2021-BR-062-0012 Project Downers Grove - Curtiss and Glenview Drainage Improvement Not Selected Did not meet HMA Requirements
Illinois EMC-2021-BR-062-0015 Project St. Joseph Creek Watershed Flood Control and Restoration Project Not Selected Did not meet HMA Requirements
Illinois EMC-2021-BR-062-0017 Project City of Eureka – WWTP Flood Mitigation Not Selected Did not meet HMA Requirements
Illinois EMC-2021-BR-062-0022 Project City of Mattoon WWTP Flood Mitigation Project Not Selected Did not meet HMA Requirements
Illinois EMC-2021-BR-062-0026 Plan State Plan of Flood Control Report Not Selected Did not meet HMA Requirements
Illinois EMC-2021-BR-062-0003 Project scoping Project Scoping for Lake Mistake Drain Culvert $38,880.66 Identified for Further Review - Round 1
Illinois EMC-2021-BR-062-0006 Project Village of Inverness $29,925.00 Identified for Further Review - Round 1
Illinois EMC-2021-BR-062-0010 Project Freeport Subapplication $271,901.25 Identified for Further Review - Round 1
Illinois EMC-2021-BR-062-0011 Management cost Illinois Management Costs $120,920.49 Identified for Further Review - Round 1
Illinois EMC-2021-BR-062-0013 Project Generators $27,722.25 Identified for Further Review - Round 1
Illinois EMC-2021-BR-062-0021 Project Lee County - Court Services Building Generator Project $88,569.00 Identified for Further Review - Round 1
Illinois EMC-2021-BR-062-0025 Project Village of Coal City Water Treatment Plant $245,101.00 Identified for Further Review - Round 1
Illinois EMC-2021-BR-062-0001 Project La Grange 50th Street Relief Storm Sewer Flood Mitigation Project Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0004 Project MWRD Village of Ford Heights Buyout and Riparian Restoration Project Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0005 Project Turf, Countryside, and Ranch Drainage Improvement Project Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0007 Project GPSD Levee Improvement & Certification Project Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0008 Project MWRD City of Harvey Stormwater Management Project Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0014 Project DuPage County Flood Prone Property Acquisition Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0016 Project MWRD Addison Creek Channel Improvements Project Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0018 Project City of Wood Dale Flood Mitigation Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0019 Project City of Peru Water Street Electric Substation Relocation Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0020 Project Machesney Park Acquisition Demolition Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0023 Project Capri-Emerson Flood Mitigation improvements Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0024 Project City of Peoria - Phase I Study - Flood Wall Application Not Selected Not Selected for Further Review
Illinois EMC-2021-BR-062-0027 Project City of Rock Island Not Selected Not Selected for Further Review
Indiana EMC-2021-BR-065-0002 Plan Indiana County MHMP Updates $121,827.36 Identified for Further Review - Round 1
Indiana EMC-2021-BR-065-0004 Project Sugar Creek Acquisition Project $460,248.75 Identified for Further Review - Round 1
Indiana EMC-2021-BR-065-0006 Project Residential Safe Room Program 2022 $115,000.00 Identified for Further Review - Round 1
Indiana EMC-2021-BR-065-0007 Management cost Indiana Management Costs $132,943.74 Identified for Further Review - Round 1
Indiana EMC-2021-BR-065-0008 Plan Indiana MHMP Update $300,000.00 Identified for Further Review - Round 1
Indiana EMC-2021-BR-065-0001 Project Fort Wayne Thieme Drive Floodwall Not Selected Not Selected for Further Review
Indiana EMC-2021-BR-065-0003 Project Fort Wayne Foster Park Pump Station Not Selected Not Selected for Further Review
Indiana EMC-2021-BR-065-0005 Project Rocky Ripple Flood Damage Risk Reduction Project Not Selected Not Selected for Further Review
Iowa EMK-2021-BR-041-0001 Project Scott County EMA Potable Water Resiliency Project Not Selected Did not meet HMA Requirements
Iowa EMK-2021-BR-041-0003 Project scoping Cedar Falls - Stormwater Resilience Project Scoping $208,000.00 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0004 Project scoping City of Hartley Project Scoping $90,000.00 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0005 Project scoping City of Vinton Detention Scoping Project $49,603.50 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0006 Project scoping Code Enforcement Enhancement $56,250.00 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0007 Project scoping Downtown Flood Mitigation $74,775.00 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0008 Management cost Iowa Management Cost $125,884.70 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0009 Project scoping Flexible Energy Sources for Greater Iowa Community Resilience $300,921.00 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0010 Project scoping City of Dyersville Project Scoping $187,500.00 Identified for Further Review - Round 1
Iowa EMK-2021-BR-041-0002 Project Storm Lake Water Infrastructure Mitigation Project Not Selected Not Selected for Further Review
Kansas EMK-2021-BR-042-0004 Project Line Hardening Not Selected Did not meet HMA Requirements
Kansas EMK-2021-BR-001-0001 Project scoping Hydraulic and Hydrologic Study $562,500.00 Identified for Further Review - Round 1
Kansas EMK-2021-BR-001-0002 Management cost Tribal Management Costs $37,500.00 Identified for Further Review - Round 1
Kansas EMK-2021-BR-042-0003 Project City of El Dorado Repetitive Loss Mitigation Project $375,000.00 Identified for Further Review - Round 1
Kansas EMK-2021-BR-042-0006 Project Ozawkie Powered Up Project $133,680.00 Identified for Further Review - Round 1
Kansas EMK-2021-BR-042-0007 Project Ozawkie Sensible Sewer Program $389,958.00 Identified for Further Review - Round 1
Kansas EMK-2021-BR-044-0001 Plan ITKN Multi-Hazard Mitigation Planning Grant $276,120.00 Identified for Further Review - Round 1
Kansas EMK-2021-BR-044-0002 Management cost ITKN Hazard Mitigation Planning Grant $21,000.00 Identified for Further Review - Round 1
Kansas EMK-2021-BR-042-0001 Project Ozawkie Vista View Drainage Project Not Selected Not Selected for Further Review
Kansas EMK-2021-BR-042-0002 Project Calfskin Creek Watershed Mitigation Not Selected Not Selected for Further Review
Kansas EMK-2021-BR-042-0005 Project USD 426 Pike Valley Elementary School Safe Room Addition Not Selected Not Selected for Further Review
Kansas EMK-2021-BR-042-0008 Project Sedgwick County Mulvane KS Styx Creek Flood Mitigation Not Selected Not Selected for Further Review
Kentucky EMA-2021-BR-038-0001 Project Paddy's Run Resilient Infrastructure Project Not Selected Did not meet HMA Requirements
Kentucky EMA-2021-BR-038-0002 Project Owensboro Grain Bank Stabilization Project Not Selected Did not meet HMA Requirements
Kentucky EMA-2021-BR-038-0003 Management cost Kentucky Management Costs Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0004 Project scoping Lafourche Parish Pump Station Upgrade and Hardening Scoping Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0007 Project scoping Project Scoping for Terrebonne Parish Hospitals Resilience Measures Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0010 Project scoping Project Scoping for Houma Navigation Canal Pump Station Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0013 Plan JP Multi Jurisdictional Hazard Mitigation Plan 2025 Update Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0019 Project Entergy Louisiana Happy Jack Substation Feeder Resilience Project Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0023 Plan Lafourche Parish Stormwater Management Framework Plan Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0028 Plan City of Scott Emergency Monitoring Services Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0032 Plan City of New Orleans Small Business Resilience Planning Assistance Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0033 Project scoping City of New Orleans Public Park Resilience Project Scoping Not Selected Did not meet HMA Requirements
Louisiana EMT-2021-BR-091-0006 Project scoping Tangipahoa Parish Government Project Scoping $359,238.00 Identified for Further Review - Round 1
Louisiana EMT-2021-BR-091-0009 Project scoping White's Bayou to Cypress Bayou Subwatershed $344,250.00 Identified for Further Review - Round 1
Louisiana EMT-2021-BR-091-0018 Management cost GOHSEP State Management Costs $135,423.40 Identified for Further Review - Round 1
Louisiana EMT-2021-BR-091-0021 Project scoping Lake Charles - Project Scoping - Flood Mitigation, Public Safety & Citywide Resilience $75,000.00 Identified for Further Review - Round 1
Louisiana EMT-2021-BR-091-0027 Project scoping City of New Orleans Lower 9th Ward Energy Resilience Project Scoping $221,375.00 Identified for Further Review - Round 1
Louisiana EMT-2021-BR-091-0001 Project SELFPA-E Safe Room Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0002 Project DPS06 Audubon Golf Course Community Flood Mitigation Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0003 Project JP Retrofit for Subsidence/Erosion Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0005 Project Entergy New Orleans - Derbigny Substation Feeder Resilience Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0008 Project SWBNO Power Reliability Program Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0011 Project LSU Lakes - McKinley Diversion and Corporation Canal Retrofit Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0012 Project Sibley Lake Lift Station Emergency Power System Replacement Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0014 Project Entergy Louisiana Alliance Substation Feeder Resilience Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0015 Project Entergy Louisiana Buras Substation Feeder Resilience Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0016 Project JP Elevation Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0017 Project Entergy Louisiana Terrebonne Parish Transmission Resiliency Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0020 Project Washington Parish Safe Room Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0022 Project Town of Vidalia Wastewater Improvements Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0024 Project Entergy Louisiana Mossville Substation Flood Protection Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0025 Project Taylor Bayou Regional Improvements Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0026 Project Entergy Louisiana Toomey Substation Flood Protection Project Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0029 Project Terrebonne Parish Safe Room - TLCD Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0030 Project City of Central - Shoe Creek Channel Improvements Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0031 Project JP Mitigation Reconstruction Not Selected Not Selected for Further Review
Louisiana EMT-2021-BR-091-0034 Project Entergy Louisiana Laplace Substation Flood Protection Project Not Selected Not Selected for Further Review
Maine EMB-2021-BR-006-0006 Project Saco Water Resource Recovery Project Not Selected Did not meet HMA Requirements
Maine EMB-2021-BR-006-0001 Project scoping Hunt Street Pump Station and Force Main Mitigation- Preliminary and Final Design, Bath ME $328,000.00 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0002 Project scoping Project Scoping for Jepson Brook Culvert Mitigation $70,000.00 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0003 Management cost Maine Management Costs $117,062.67 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0004 Project scoping Drift Inn Road Project Scoping $15,750.00 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0005 Plan Hancock County Hazard Mitigation Plan Update 2023 $17,513.77 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0007 Project Town of Union Clarry Hill Culvert Mitigation Strategy $206,250.00 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0008 Plan Piscataquis Hazard Mitigation Plan Update $4,725.00 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0009 Project scoping Harward Street Drainage Area Sewer Interceptor- Sanitary Sewer Overflow Mitigation $228,400.00 Identified for Further Review - Round 1
Maine EMB-2021-BR-006-0010 Plan Franklin County Hazard Mitigation Plan Update 2022 $11,025.00 Identified for Further Review - Round 1
Maryland EMP-2021-BR-053-0002 Project Port Deposit Flood Control Structures. Not Selected Did not meet HMA Requirements
Maryland EMP-2021-BR-053-0004 Project Sawmill Creek Tributaries Restoration - Ferndale, Irving, & Muddy Bridge Branch Not Selected Did not meet HMA Requirements
Maryland EMP-2021-BR-053-0005 Project Make Cambridge Resilient Flood Mitigation Project Not Selected Did not meet HMA Requirements
Maryland EMP-2021-BR-053-0008 Project scoping Using IOT and Sensor Technology to Improve Stormwater Management along the Route One Corridor Not Selected Did not meet HMA Requirements
Maryland EMP-2021-BR-053-0009 Project scoping Critical Infrastructure and Community Lifelines Mapping, Prince George's County Not Selected Did not meet HMA Requirements
Maryland EMP-2021-BR-053-0001 Project scoping Department of Transportation MPA Marine Terminals Coastal Resiliency Assessment and Adaptation Planning $150,000.00 Identified for Further Review - Round 1
Maryland EMP-2021-BR-053-0003 Project scoping Mill Swamp Flood Mitigation Project- Implementing the County Nuisance and Urban Flood Plan $49,500.00 Identified for Further Review - Round 1
Maryland EMP-2021-BR-053-0006 Management cost Maryland Management Cost $105,265.00 Identified for Further Review - Round 1
Maryland EMP-2021-BR-053-0007 Project scoping Cloverfields Neighborhood Flood Mitigation Project Scoping $116,200.00 Identified for Further Review - Round 1
Maryland EMP-2021-BR-053-0010 Project scoping Snow Hill Manor Park Stream Restoration Project $208,837.50 Identified for Further Review - Round 1
Maryland EMP-2021-BR-053-0011 Project scoping Shady Side Peninsula Climate Adaptation Study $240,000.00 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0012 Project Somerville - Poplar Street Pump Station Not Selected Did not meet HMA Requirements
Massachusetts EMB-2021-BR-072-0017 Project Chicopee - Abbey Brook Dam Removal, Culvert Replacement, and Stream Restoration Not Selected Did not meet HMA Requirements
Massachusetts EMB-2021-BR-074-0001 Management cost MWT FY21 BRIC 2 Not Selected Did not meet HMA Requirements
Massachusetts EMB-2021-BR-074-0002 Plan MWT FY21 BRIC 3 Not Selected Did not meet HMA Requirements
Massachusetts EMB-2021-BR-074-0003 Project MWT FY21 BRIC 1 Not Selected Did not meet HMA Requirements
Massachusetts EMB-2021-BR-072-0001 Project scoping Woburn - Washington Street Flood Mitigation $58,650.00 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0007 Project scoping Tisbury Beach Road Resiliency Improvements Project Scoping $78,750.00 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0009 Project scoping Weymouth Fort Point Road Seawall Project Scoping $112,590.00 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0010 Project scoping Resilient Town Line Brook Project Scoping– DCR $252,750.00 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0011 Project scoping Royalston Watershed Based Assessment $90,000.00 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0013 Project scoping West Springfield - Block Brook Watershed Study and Flood Mitigation Plan $38,709.75 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0014 Project scoping Attleboro Downtown Flood Mitigation and Resiliency Planning Assessment $187,125.00 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0018 Management cost Massachusetts Management Costs $3,546,943.30 Identified for Further Review - Round 1
Massachusetts EMB-2021-BR-072-0006 Project Resilient Moakley Park - Equitable Climate Resilience at Boston’s Moakley Park - Boston, MA $24,064,600.00 Identified for Further Review - Round 2
Massachusetts EMB-2021-BR-072-0002 Project Wayland - Snake Brook Dam Resiliency Not Selected Not Selected for Further Review
Massachusetts EMB-2021-BR-072-0003 Project Cities of Chelsea and Everett Island End Flood Resilience Project Not Selected Not Selected for Further Review
Massachusetts EMB-2021-BR-072-0004 Project Ipswich Town Wharf Sewer Pump Station Relocation Flood Mitigation Project Not Selected Not Selected for Further Review
Massachusetts EMB-2021-BR-072-0005 Project Salem, MA Sewer Pipe Relocation Project Not Selected Not Selected for Further Review
Massachusetts EMB-2021-BR-072-0008 Project Cohasset Microgrid 2022 Not Selected Not Selected for Further Review
Massachusetts EMB-2021-BR-072-0015 Project Marion - Creek Road Pump Station Resiliency Improvements Not Selected Not Selected for Further Review
Massachusetts EMB-2021-BR-072-0016 Project Gloucester - Haskell pond Dam Design Storm and Seismic Improvements Not Selected Not Selected for Further Review
Michigan EMC-2021-BR-063-0001 Project Clinton River Water Resources Recovery Facility Switchgear Resiliency Project Not Selected Did not meet HMA Requirements
Michigan EMC-2021-BR-063-0004 Project GLWA: Northwest Interceptor Diversion Tunnel Not Selected Did not meet HMA Requirements
Michigan EMC-2021-BR-063-0005 Project Building Resilient Infrastructure and Communities Not Selected Did not meet HMA Requirements
Michigan EMC-2021-BR-063-0010 Project Salem Township Southshore Tornado Safe room Not Selected Did not meet HMA Requirements
Michigan EMC-2021-BR-063-0011 Project Grosse Pointe Park Sanitary Sewer Project Not Selected Did not meet HMA Requirements
Michigan EMC-2021-BR-063-0008 Project scoping City of Hamtramck Phase 2 Sewer Relief $243,765.00 Identified for Further Review - Round 1
Michigan EMC-2021-BR-063-0009 Project scoping Project Scoping for An Oakland County Community safe room Construction $435,000.00 Identified for Further Review - Round 1
Michigan EMC-2021-BR-063-0014 Management cost Michigan Management Costs $90,502.00 Identified for Further Review - Round 1
Michigan EMC-2021-BR-063-0002 Project Plainfield Charter Township Property Acquisitions Not Selected Not Selected for Further Review
Michigan EMC-2021-BR-063-0003 Project Wayne County Design and Install Permanent Standby Generators Pump Stations Not Selected Not Selected for Further Review
Michigan EMC-2021-BR-063-0006 Project Grosse Pointe Sewer Separation Not Selected Not Selected for Further Review
Michigan EMC-2021-BR-063-0007 Project Commercial District Storm Sewer Improvements Not Selected Not Selected for Further Review
Michigan EMC-2021-BR-063-0012 Project City of Hamtramck Phase 18 Sewer Relief Not Selected Not Selected for Further Review
Michigan EMC-2021-BR-063-0013 Project City of Southgate Combined Sewer Relief Not Selected Not Selected for Further Review
Minnesota EMC-2021-BR-010-0001 Project Mankato Area Public Schools Community Safe Room Not Selected Did not meet HMA Requirements
Minnesota EMC-2021-BR-010-0003 Project Red Rock Central School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Minnesota EMC-2021-BR-010-0005 Project DuluthPhase 4 Shoreline Mitigation Not Selected Did not meet HMA Requirements
Minnesota EMC-2021-BR-010-0002 Project City of Saint Paul Virtual Inspections Project $278,565.00 Identified for Further Review - Round 1
Minnesota EMC-2021-BR-010-0004 Plan 14 County Hazard Mitigation Plan Updates $492,000.00 Identified for Further Review - Round 1
Minnesota EMC-2021-BR-010-0006 Project scoping Department of Natural Resources Project Scoping Lower Zumbro $43,736.25 Identified for Further Review - Round 1
Minnesota EMC-2021-BR-010-0007 Management cost Minnesota Management Costs $108,573.50 Identified for Further Review - Round 1
Mississippi EMA-2021-BR-156-0005 Project Pump Station 20 Improvement Project Not Selected Did not meet HMA Requirements
Mississippi EMA-2021-BR-156-0007 Project City of Nettleton Drainage Not Selected Did not meet HMA Requirements
Mississippi EMA-2021-BR-156-0003 Project scoping City of Biloxi Project Scoping for a New Cedar Lake Bridge $531,538.99 Identified for Further Review - Round 1
Mississippi EMA-2021-BR-156-0004 Project Quitman County Capability-and Capacity Building $94,543.20 Identified for Further Review - Round 1
Mississippi EMA-2021-BR-156-0006 Project Bolivar County Flood Mitigation Study $187,500.00 Identified for Further Review - Round 1
Mississippi EMA-2021-BR-156-0008 Management cost Mississippi Management Cost $106,376.67 Identified for Further Review - Round 1
Mississippi EMA-2021-BR-156-0001 Project City of Canton MLK South Flood Mitigation Project Not Selected Not Selected for Further Review
Mississippi EMA-2021-BR-156-0002 Project Mill Creek Watershed Mitigation & Restoration Not Selected Not Selected for Further Review
Missouri EMK-2021-BR-037-0003 Project scoping State Allocation City of St. James Resilient Safe Room Shelter Project Scoping $119,350.00 Identified for Further Review - Round 1
Missouri EMK-2021-BR-037-0004 Management cost Missouri Management Cost $117,867.76 Identified for Further Review - Round 1
Missouri EMK-2021-BR-037-0006 Project scoping Project State Allocation – Project Scoping Jefferson County Warning Siren Acoustic Survey $22,500.00 Identified for Further Review - Round 1
Missouri EMK-2021-BR-037-0007 Project State Allocation-Gasconade C-4 School District Safe Room $768,150.00 Identified for Further Review - Round 1
Missouri EMK-2021-BR-037-0008 Project scoping State Allocation-Project Scoping for City of Seymour - Flood Mitigation $90,000.00 Identified for Further Review - Round 1
Missouri EMK-2021-BR-037-0001 Project Fredericktown Seismic Retrofit Competitive Project Not Selected Not Selected for Further Review
Missouri EMK-2021-BR-037-0002 Project Competitive-City Utilities of Springfield-Blackman WTP Back-Up Power with Enclosure Not Selected Not Selected for Further Review
Missouri EMK-2021-BR-037-0005 Project City St Louis Backup Power Generators-Chain of Rocks/Howard Bend WTPs Not Selected Not Selected for Further Review
Missouri EMK-2021-BR-037-0009 Project City of Clarksville Floodwall Not Selected Not Selected for Further Review
Missouri EMK-2021-BR-037-0010 Project Excelsior Springs City Hospital Microgrid Not Selected Not Selected for Further Review
Montana EMD-2021-BR-001-0001 Project Lincoln County Resilient Infrastructure for Energy and Transportation Project Not Selected Did not meet HMA Requirements
Montana EMD-2021-BR-001-0002 Project University Of Montana Microgrid Not Selected Did not meet HMA Requirements
Montana EMD-2021-BR-001-0005 Project City of Billings: Adapting to Future Climate and Water Needs through Flood, and Drought Resilience Not Selected Did not meet HMA Requirements
Montana EMD-2021-BR-001-0003 Project Missoula County Rock Creek Fire Mitigation Project $919,950.00 Identified for Further Review - Round 1
Montana EMD-2021-BR-001-0006 Management cost Montana Management Costs $122,660.00 Identified for Further Review - Round 1
Montana EMD-2021-BR-001-0004 Project Three Forks Confluence Project: Mitigation for Affordability, Climate Resiliency & Economic Vitality Not Selected Not Selected for Further Review
Nebraska EMK-2021-BR-002-0001 Project scoping Salt Creek Flood Reduction Feasibility Study $249,937.50 Identified for Further Review - Round 1
Nebraska EMK-2021-BR-002-0002 Project scoping Grant OPPD's Service Territory $150,000.00 Identified for Further Review - Round 1
Nebraska EMK-2021-BR-002-0004 Plan Lower Elkhorn NRD/Cedar-Dixon Counties Multi-Jurisdictional Hazard Mitigation Plan Update $199,984.37 Identified for Further Review - Round 1
Nebraska EMK-2021-BR-002-0006 Project scoping City of Hastings Flood Mitigation Project Scoping $262,500.00 Identified for Further Review - Round 1
Nebraska EMK-2021-BR-002-0007 Management cost Nebraska Management Cost $1,432,902.58 Identified for Further Review - Round 1
Nebraska EMK-2021-BR-002-0009 Plan Hazard Mitigation Plan Update $75,000.00 Identified for Further Review - Round 1
Nebraska EMK-2021-BR-002-0005 Project Papio WP-4 Project $5,335,650.00 Identified for Further Review - Round 2
Nebraska EMK-2021-BR-002-0003 Project St. Edward Beaver Creek Stabilization Not Selected Not Selected for Further Review
Nebraska EMK-2021-BR-002-0008 Project Falls City Electrical Distribution System Improvements Not Selected Not Selected for Further Review
Nevada EMF-2021-BR-016-0001 Management cost Nevada Management Costs $66,666.67 Identified for Further Review - Round 1
Nevada EMF-2021-BR-016-0002 Plan Truckee Meadows Water Reclamation Facility Seismic Evaluation $300,000.00 Identified for Further Review - Round 1
Nevada EMF-2021-BR-016-0003 Plan Disadvantaged Community Inventory - Planning-related Activity $132,500.00 Identified for Further Review - Round 1
Nevada EMF-2021-BR-016-0004 Plan Washoe County Hazard Mitigation Plan Update $67,500.00 Identified for Further Review - Round 1
Nevada EMF-2021-BR-016-0005 Project Hobart Creek Reservoir Dam Resilient Infrastructure Project Not Selected Not Selected for Further Review
New Hampshire EMB-2021-BR-075-0001 Plan Local Hazard Mitigation Plan Updates $498,497.25 Identified for Further Review - Round 1
New Hampshire EMB-2021-BR-075-0002 Management cost New Hampshire Management Costs $66,466.30 Identified for Further Review - Round 1
New Jersey EMN-2021-BR-058-0001 Project Wildwood Crest Boro: Bayside Resiliency Project Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0003 Project Neptune Township South Riverside Flood Pumps Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0005 Project Wildwood Bayside Resiliency Project Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0007 Project BCUA Flood Mitigation of Pink Street Pump Station Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0008 Project Woodbridge Township: Sanitary Pump Station Floodproofing Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0010 Project Stone Harbor Bayside Resiliency Project Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0014 Project Pacific Avenue Flood Mitigation Project Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0016 Project Jefferson Township: Three Rivers Bridge Stabilization and Restoration Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0018 Plan Bergen County Multi-jurisdictional Hazard Mitigation Plan Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0022 Project North Wildwood Bayside Resiliency Project Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0023 Project Reconstruction of Rochelle Park Sanitary Sewer Pump Station Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0027 Project Sea Isle City: 46th Street Pump Station Mitigation Project Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0028 Project Township of Stafford and OCUA - Erosion Control Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0031 Project Secaucus Huber Street Floodwall Project Not Selected Did not meet HMA Requirements
New Jersey EMN-2021-BR-058-0011 Project New Jersey Statewide Floodplain Administrator Training $304,716.16 Identified for Further Review - Round 1
New Jersey EMN-2021-BR-058-0013 Plan Burlington County Hazard Mitigation Plan Update 2025 $168,750.00 Identified for Further Review - Round 1
New Jersey EMN-2021-BR-058-0015 Management cost New Jersey Management Costs $3,353,373.49 Identified for Further Review - Round 1
New Jersey EMN-2021-BR-058-0030 Project scoping Hoboken Project Scoping: Southwest Park Expansion $100,000.00 Identified for Further Review - Round 1
New Jersey EMN-2021-BR-058-0032 Plan Morris County Hazard Mitigation Plan Update $172,500.00 Identified for Further Review - Round 1
New Jersey EMN-2021-BR-058-0002 Project 63rd Street Pumping Station Power and Flood Resilience Project $2,207,087.83 Identified for Further Review - Round 2
New Jersey EMN-2021-BR-058-0012 Project Newark Ironbound Resilience Hub $10,576,121.83 Identified for Further Review - Round 2
New Jersey EMN-2021-BR-058-0019 Project BCUA Flood Mitigation of Joint Meeting Pump Station $4,558,868.27 Identified for Further Review - Round 2
New Jersey EMN-2021-BR-058-0021 Project Cottage Street Park Flood Mitigation Project $4,642,474.00 Identified for Further Review - Round 2
New Jersey EMN-2021-BR-058-0024 Project PANYNJ Elevation-Floodproofing of Building 111 Infrastructure Mitigation $1,999,022.20 Identified for Further Review - Round 2
New Jersey EMN-2021-BR-058-0004 Project Atlantic City Baltic Canal Resiliency Project Not Selected Not Selected for Further Review
New Jersey EMN-2021-BR-058-0006 Project Margate Amherst Avenue Resiliency Project Not Selected Not Selected for Further Review
New Jersey EMN-2021-BR-058-0009 Project Jersey City McGovern Park Resilience Project Not Selected Not Selected for Further Review
New Jersey EMN-2021-BR-058-0017 Project Freehold Township Water Treatment Plant Generator Project Not Selected Not Selected for Further Review
New Jersey EMN-2021-BR-058-0020 Project ELSA Flood Mitigation of Fackler Road and Lower Ferry Pump Stations Not Selected Not Selected for Further Review
New Jersey EMN-2021-BR-058-0025 Project Atlantic City Fire Station Emergency Generators Not Selected Not Selected for Further Review
New Jersey EMN-2021-BR-058-0026 Project Township of Brick Roadway Elevation Project Not Selected Not Selected for Further Review
New Jersey EMN-2021-BR-058-0029 Project Snug Harbor and North Street Stormwater Pump Stations Not Selected Not Selected for Further Review
New Mexico EMT-2021-BR-134-0004 Project Initial Early Warning System for Arroyo Flash Floods Not Selected Did not meet HMA Requirements
New Mexico EMT-2021-BR-132-0001 Plan Santa Clara Pueblo Hazard Mitigation Plan $44,727.19 Identified for Further Review - Round 1
New Mexico EMT-2021-BR-134-0001 Project scoping Nightglow Avenue Area Flood Mitigation $215,750.02 Identified for Further Review - Round 1
New Mexico EMT-2021-BR-134-0002 Management cost New Mexico Management Costs $74,005.90 Identified for Further Review - Round 1
New Mexico EMT-2021-BR-134-0003 Project scoping Los Ranchos Levee Failure – Flood Mitigation Project Scoping $348,104.45 Identified for Further Review - Round 1
New Mexico EMT-2021-BR-138-0001 Project Pueblo of Laguna Uniform Residential Building Code Development 2022 $225,000.00 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0001 Project scoping NYS-OPRHP Dinsmore GC Communitywide Flood Protection Not Selected Did not meet HMA Requirements
New York EMN-2021-BR-069-0002 Project Nyack, Village - (Project) Nyack Creek Drainage Improvements Not Selected Did not meet HMA Requirements
New York EMN-2021-BR-069-0006 Project scoping NYS-OPRHP Dunham Reservoir Scoping for Decommissioning Not Selected Did not meet HMA Requirements
New York EMN-2021-BR-069-0010 Project scoping Asharoken (V) Seawall Structure Upgrade Not Selected Did not meet HMA Requirements
New York EMN-2021-BR-069-0011 Project NYCHA - (Project) St. Nicholas Houses Not Selected Did not meet HMA Requirements
New York EMN-2021-BR-060-0001 Plan BRIC Subapplication $184,476.08 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0003 Plan Tree Mitigation Plan $97,640.80 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0005 Project Port Dickinson (V) Sewage Pump Station Resiliency Project $24,750.00 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0007 Project scoping NYCHA - (Scoping) Resilience Hubs $256,000.00 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0013 Project scoping Village of Saltaire Scoping Project $187,368.75 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0016 Project scoping NYCHA - (Scoping) Flood Protections for Highly Vulnerable Properties $271,840.00 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0017 Project scoping Tompkins County - Scoping Human Services Building Energy Resilience $23,650.45 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0018 Plan Planning for Resiliency: Keeping Piermont Viable in the Era of Climate Change $75,000.00 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0019 Management cost New York Management Cost $28,634,116.47 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0020 Project scoping Sea Cliff Village (Scoping) Waterfront Slope & Shoreline $63,750.00 Identified for Further Review - Round 1
New York EMN-2021-BR-069-0008 Project NYCDEP - (Project) Clinton Houses/East Harlem Community Stormwater Resiliency $8,358,867.35 Identified for Further Review - Round 2
New York EMN-2021-BR-069-0009 Project NYCHA - (Project) Breukelen Houses Stormwater Protection $19,843,141.15 Identified for Further Review - Round 2
New York EMN-2021-BR-069-0012 Project NYCEDC - (Project) Seaport Coastal Resilience Project $50,000,000.00 Identified for Further Review - Round 2
New York EMN-2021-BR-069-0021 Project NYCEDC - (Project) Hunts Point Food Security Mitigation Project $14,682,301.72 Identified for Further Review - Round 2
New York EMN-2021-BR-060-0002 Management cost Saint Regis Mohawk Tribe Management Costs $21,238.00 Identified for Further Review
New York EMN-2021-BR-069-0004 Project Orange County - Cromline Creek Pump Station Flood Resilience Improvement Project Not Selected Not Selected for Further Review
New York EMN-2021-BR-069-0014 Project Greene County - (Project) Catskill Point Shoreline Stabilization Not Selected Not Selected for Further Review
New York EMN-2021-BR-069-0015 Project Monroe (T) Generator Project Not Selected Not Selected for Further Review
North Carolina EMA-2021-BR-005-0003 Project City of Rocky Mount: Downtown Drainage Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0005 Project Cumberland County Flood Warning System Development Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0006 Project Upper Yadkin River Floodplain Resiliency Initiative for Jonesville Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0007 Project Wilson Mall Acquisition Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0009 Project Duffyfield Community Stormwater Enhancements - Infrastructure Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0011 Project Lenoir - Arrowood Street Bridge Replacement Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0013 Project Sewer system floodproofing and stream restoration Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0014 Project Selma Storm Water Resiliency Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0015 Project Oak-Island-Ocean Drive Drainage Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0016 Project Town of Kure Beach Stormwater Infiltration for 7 Sites Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0017 Project Surry County Flood Hazard Mitigation Project in the Yadkin Valley Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0018 Project Emergency Access Road Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0019 Project Sewer Force Main, Raw Water Intake, & Stream Bank Stabilization Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0025 Project Chadbourn Stormwater System Improvements for Flood Mitigation Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0026 Project Town of Benson Driving Branch Stream Restoration Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0028 Project Central Business-District Nature-Based Flood Mitigation Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0029 Project Wilkesboro Cub Creek Phase III Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0031 Project Resilient Utilities Infrastructure - Electric Substation Project - Infrastructure Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0033 Project Greenbriar Flood Mitigation and Stream Restoration Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0034 Project Town of Cape Carteret Flood Mitigation and Stormwater Resiliency Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0036 Project Town of Beech Mountain Water Supply Drought Mitigation Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0037 Project Taylorsville Flood Mitigation Improvements Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0039 Project Dare County - Roanoke Island Stormwater Infrastructure Improvements Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0040 Project Lenoir Resilient Wastewater Infrastructure Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0043 Project Rhodhiss - Floodplain Resilience Project Final Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0045 Project DEFD Sea Level Fire Station Relocation Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0049 Project Davie County/Yadkinville Waterline Interconnection Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0050 Project Newton Reservoir Retaining Wall Replacement Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0053 Project Town of Biscoe Wastewater Treatment Plant Gravity Sewer Outfall Replacement Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0055 Project Lansing Wastewater Treatment Plant Elevation Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0056 Project Pump Station Relocation Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0057 Project Town of Emerald Isle - Western Stormwater Mitigation Project Not Selected Did not meet HMA Requirements
North Carolina EMA-2021-BR-005-0001 Plan Town of Hertford Climate Risk Assessment $130,000.00 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0010 Project scoping Watershed-based V/R assessment to scale up resilience building actions across jurisdictions $202,800.00 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0020 Management cost North Carolina Management Costs $7,108,616.70 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0035 Project scoping Spindale Aerial Crossing Repair $199,999.80 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0038 Plan Rowland Stormwater Asset Inventory and Assessment Study $200,000.00 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0047 Project scoping Town of Pembroke Stormwater Mitigation Project $90,200.00 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0048 Plan City of Oxford Flood Vulnerbility & Risk Assessment Study $105,000.00 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0042 Plan Conover - Community Resilience Plan $70,000.00 Identified for Further Review - Round 1
North Carolina EMA-2021-BR-005-0004 Project Blood Run Pump Station Relocation and Sewer Line Replacement $5,001,399.00 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0012 Project City of Gastonia Duharts Creek - Critical Infrastructure Protection and Stream Restoration $5,979,200.00 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0022 Project Sawmills South Caldwell Sewer Pump Station Elevation Project $189,000.00 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0024 Project City of Greenville St. Andrews Drive- Critical Infrastructure Protection and Stream Restoration $3,445,106.00 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0027 Project Pollocksville Floodprint: Building Elevations to Restore the Town's Commercial Corridor $1,083,811.36 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0032 Project Fair Bluff Park Phase 2 $2,441,298.00 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0041 Project Town of Hillsborough NC - Resilient Regional Water Supply Project $1,015,469.23 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0044 Project Water Supply Resiliency Project for SRU Pump Station Along Yadkin River $22,496,850.00 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0046 Project Fayetteville, NC - Wayland Drive Drainage Improvements $2,612,602.78 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0054 Project Town of Hillsborough River Pumping Station Relocation from Floodway $5,805,546.35 Identified for Further Review - Round 2
North Carolina EMA-2021-BR-005-0002 Project Bay River Metropolitan Sewer District- Facultative Lagoon System Renovation and Capacity Upgrades Not Selected Not Selected for Further Review
North Carolina EMA-2021-BR-005-0008 Project Wrightsville Goddard Interceptor Not Selected Not Selected for Further Review
North Carolina EMA-2021-BR-005-0021 Project Black River Culvert Improvement Project Not Selected Not Selected for Further Review
North Carolina EMA-2021-BR-005-0023 Project Elizabethtown Regional Sewer Not Selected Not Selected for Further Review
North Carolina EMA-2021-BR-005-0030 Project Bledsoe Creek Interceptor Relocation Project Not Selected Not Selected for Further Review
North Carolina EMA-2021-BR-005-0051 Project Jack’s Creek Pump Station Automated Screen Project Not Selected Not Selected for Further Review
North Carolina EMA-2021-BR-005-0052 Project Jack’s Creek Drainage Improvement (Brown and 12th Streets) Project Not Selected Not Selected for Further Review
North Dakota EMD-2021-BR-059-0006 Project City of Fargo Sewer System Mitigation Project - West Side Interceptor Not Selected Did not meet HMA Requirements
North Dakota EMD-2021-BR-059-0010 Project City of Lincoln Wastewater Pond System Regionalization Not Selected Did not meet HMA Requirements
North Dakota EMD-2021-BR-059-0001 Management cost North Dakota Management Costs $94,742.08 Identified for Further Review - Round 1
North Dakota EMD-2021-BR-059-0002 Plan Stark County Comprehensive Plan Update $105,525.00 Identified for Further Review - Round 1
North Dakota EMD-2021-BR-059-0004 Project scoping West Fargo Bank Stabilization Scoping $75,000.00 Identified for Further Review - Round 1
North Dakota EMD-2021-BR-059-0008 Project scoping Grand Forks Sanitary Forcemain North End Reliever Scoping $243,966.00 Identified for Further Review - Round 1
North Dakota EMD-2021-BR-059-0012 Plan North Dakota Enhanced Multi-Hazard Mitigation Plan Update $286,074.60 Identified for Further Review - Round 1
North Dakota EMD-2021-BR-059-0003 Project City of Minot Puppy Dog Coulee Flood Resiliency Project Not Selected Not Selected for Further Review
North Dakota EMD-2021-BR-059-0005 Project Lower Heart River Flood Risk Reduction Project - City of Mandan Not Selected Not Selected for Further Review
North Dakota EMD-2021-BR-059-0007 Project Grand Forks County Emergency Access Mitigation Project - 62nd Avenue Bridge Not Selected Not Selected for Further Review
North Dakota EMD-2021-BR-059-0009 Project City of Fessenden Wastewater Lagoon System Mitigation Project Not Selected Not Selected for Further Review
North Dakota EMD-2021-BR-059-0011 Project Emmons County - Schwahn Lake High Water Outlet Not Selected Not Selected for Further Review
North Dakota EMD-2021-BR-059-0013 Project Hay Creek Sewer System Mitigation Project - Building A Resilient Bismarck Not Selected Not Selected for Further Review
North Dakota EMD-2021-BR-059-0014 Project Northwood Citywide Severe Storm Resiliency Project Not Selected Not Selected for Further Review
Northern Mariana Islands EMF-2021-BR-103-0001 Project Gapgap Road Resilience Project Not Selected Not Selected for Further Review
Ohio EMC-2021-BR-019-0002 Project City of Columbus Winter Weather Plow Driver Capability Improvement Project Not Selected Did not meet HMA Requirements
Ohio EMC-2021-BR-019-0001 Plan State of Ohio Hazard Mitigation Plan Update $218,875.00 Identified for Further Review - Round 1
Ohio EMC-2021-BR-019-0003 Management cost Ohio Management Costs $98,588.33 Identified for Further Review - Round 1
Ohio EMC-2021-BR-019-0004 Project Ohio Safe Room Rebate Program $528,800.00 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-034-0001 Management cost Cheyenne & Arapaho Management Costs Not Selected Did not meet HMA Requirements
Oklahoma EMT-2021-BR-034-0002 Project Public Safety Project Not Selected Did not meet HMA Requirements
Oklahoma EMT-2021-BR-071-0005 Project City of Lawton – Lake Ellsworth Spillway Drought Resilience Project Not Selected Did not meet HMA Requirements
Oklahoma EMT-2021-BR-071-0007 Project Broadband Infrastructure Not Selected Did not meet HMA Requirements
Oklahoma EMT-2021-BR-135-0002 Project Choctaw Nation LIDAR Mapping Project Not Selected Did not meet HMA Requirements
Oklahoma EMT-2021-BR-139-0001 Management cost BRIC Project Management Costs Not Selected Did not meet HMA Requirements
Oklahoma EMT-2021-BR-139-0002 Project BRIC Project Not Selected Did not meet HMA Requirements
Oklahoma EMT-2021-BR-032-0001 Project Muscogee (Creek) Nation Residential Safe Room Program $1,066,666.67 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-032-0002 Management cost Oklahoma Management Costs $100,000.00 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-071-0001 Project SoonerSafe Phase 27 $533,166.00 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-071-0002 Project scoping Oklahoma County Wilshire Rd. Resilient Infrastructure Scoping $311,465.72 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-071-0003 Management cost State Management Costs $2,742,015.85 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-071-0004 Plan City of Tulsa 2023 Hazard Mitigation Plan Update $149,958.00 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-135-0001 Project Choctaw Nation Mitigation Voucher Project $750,000.00 Identified for Further Review - Round 1
Oklahoma EMT-2021-BR-071-0006 Project Fulton Creek Drainage Basin Urban Flood and Heat Reduction Project $19,578,851.87 Identified for Further Review - Round 2
Oregon EMS-2021-BR-028-0001 Project City of Hood River Elevated Sewer Upgrade Not Selected Did not meet HMA Requirements
Oregon EMS-2021-BR-028-0003 Project Mount Hood Corridor Resiliency Project Not Selected Did not meet HMA Requirements
Oregon EMS-2021-BR-028-0006 Project City of Grants Pass Water Treatment Plant Relocation and Water Intake Retrofit Not Selected Did not meet HMA Requirements
Oregon EMS-2021-BR-028-0002 Management cost Oregon Management Costs $488,256.73 Identified for Further Review - Round 1
Oregon EMS-2021-BR-028-0004 Project Regner Reservoir Seismic Retrofit $707,217.75 Identified for Further Review - Round 1
Oregon EMS-2021-BR-028-0007 Plan Oregon Hazard Mitigation Plan Update 2025 $292,782.25 Identified for Further Review - Round 1
Oregon EMS-2021-BR-028-0005 Project Lane County - Alderwood Looped Power Transmission to Increase Reliability and Community Resilience $2,704,178.25 Identified for Further Review - Round 2
Pennsylvania EMP-2021-BR-042-0001 Project scoping Project Scoping Penn State, Dauphin County, Floodplain Insurance Research Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0002 Project scoping Scoping Lancaster Lancaster Localized Flood Mitigation Planning Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0006 Project scoping Scoping Philadelphia Climate Change Adaptation – Facility Flood Risk and Resiliency Assessment Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0009 Project scoping Scoping Harrisburg Dauphin Paxton Creek Flood Mitigation Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0011 Project Thornbury Chester Gate System Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0012 Project scoping Scoping Pocono Farms Monroe Mitigation Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0013 Project Bethlehem Northampton Infrastructure Project - Easton Avenue Flood Mitigation Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0014 Project scoping Scoping West Newton Westmoreland Allison Street Storm / Drainage System Analysis Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0016 Project West Pittston Luzerne Levee System Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0018 Project Pine Grove Schuylkill 2021 Stormwater Project Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0019 Project scoping City of Lancaster, Lancaster County: AWWTP Outfall Expansion/Relocation Scoping Project Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0028 Plan Scoping Williamsport LYCOMING Levee Evaluation Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0030 Project Township of Upper Darby Stormwater Flood Mitigation Not Selected Did not meet HMA Requirements
Pennsylvania EMP-2021-BR-042-0005 Project scoping Scoping Jersey Shore, Lycoming Lawshee Run Engineering and Design $258,129.00 Identified for Further Review - Round 1
Pennsylvania EMP-2021-BR-042-0008 Project scoping Project Scoping Middle Delaware River Basin Mitigation $199,999.50 Identified for Further Review - Round 1
Pennsylvania EMP-2021-BR-042-0010 Project scoping 2021 Penn Lake Park/Dennison Luzerne Project Scoping Final Design $307,500.00 Identified for Further Review - Round 1
Pennsylvania EMP-2021-BR-042-0015 Project scoping Scoping Phila Germantown Wingohocking Creek Flood Risk Reduction $103,950.00 Identified for Further Review - Round 1
Pennsylvania EMP-2021-BR-042-0022 Project scoping Scoping Orwigsburg Schuylkill Flood Mitigation $99,186.86 Identified for Further Review - Round 1
Pennsylvania EMP-2021-BR-042-0027 Management cost Pennsylvania Management Cost $3,757,479.02 Identified for Further Review - Round 1
Pennsylvania EMP-2021-BR-042-0023 Project City of Philadelphia Cohocksink Flood Mitigation Project $25,010,092.10 Identified for Further Review - Round 2
Pennsylvania EMP-2021-BR-042-0003 Project Shamokin Coal Northumberland Sewer Treatment Plant Mitigation Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0004 Project Manheim Lancaster Chiques Creek Flood Resiliency Project Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0007 Project Danville, Montour Mahoning Creek Restoration Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0017 Project Bridgeville Allegheny Flood Control Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0020 Project Hampton Township Allegheny County Water Pollution Control Facility Mitigation Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0021 Project Mayfield Lackawanna Levee Mitigation Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0024 Project Royalton Dauphin Water Street Pump Station Mitigation Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0025 Project RADNOR Delaware South Wayne Avenue Stormwater Management and Flood Reduction Project Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0026 Project Penn Lake Park/Dennison Luzerne Dam Mitigation Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0029 Project City of Lancaster, Lancaster Standby Generator for Wastewater Treatmennt Plant Not Selected Not Selected for Further Review
Pennsylvania EMP-2021-BR-042-0031 Project Borough of Coraopolis, Allegheny County, Ohio River Levee Improvements Project Not Selected Not Selected for Further Review
Puerto Rico EMN-2021-BR-067-0001 Project scoping COR3 Capability and Capacity Building Activities Not Selected Did not meet HMA Requirements
Puerto Rico EMN-2021-BR-067-0002 Management cost COR3 Management Cost Subapplication Not Selected Not Selected for Further Review
Rhode Island EMB-2021-BR-014-0003 Project City of Warwick Critical Infrastructure Generators Not Selected Did not meet HMA Requirements
Rhode Island EMB-2021-BR-014-0005 Plan Foddering Farm Causeway Scoping Study Not Selected Did not meet HMA Requirements
Rhode Island EMB-2021-BR-014-0009 Project Building Resiliency in the Westerly Building Permit System Not Selected Did not meet HMA Requirements
Rhode Island EMB-2021-BR-014-0001 Management cost Rhode Island Management Costs $26,698.00 Identified for Further Review - Round 1
Rhode Island EMB-2021-BR-014-0002 Plan 2023 Town of Westerly Hazard Mitigation Plan $56,250.00 Identified for Further Review - Round 1
Rhode Island EMB-2021-BR-014-0004 Plan Hopkinton Hazard Mitigation Plan Update $31,125.00 Identified for Further Review - Round 1
Rhode Island EMB-2021-BR-014-0006 Plan Providence Multi-Hazard Mitigation Plan Update $46,485.00 Identified for Further Review - Round 1
Rhode Island EMB-2021-BR-014-0007 Plan Multi-Jurisdictional Pawtucket/Central Falls Hazard Mitigation Plan Update $28,875.00 Identified for Further Review - Round 1
Rhode Island EMB-2021-BR-014-0008 Plan City of Warwick Hazard Mitigation Plan Update Active $37,500.00 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0001 Project City of Charleston King Street Flood Pump Station Project Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0003 Project Peachtree Ground Storage and High Service Pump Station Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0007 Project Town of Hilton Head Island Wexford Stormwater Pump Station Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0009 Project scoping ReWa South Carolina, Critical Wastewater Lifeline, Energy Resilience Project Scoping Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0011 Project S. 1st Ave. at W. Hampton St. to N. 1st Ave. at W. Madison St. Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0012 Project Charleston Medical District Elevated Walkway Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0015 Project Conway WWTP Earthen Berm Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0016 Project Town of Hilton Head Island Jarvis Creek System Outfall Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0018 Project scoping ReWa South Carolina, Critical Wastewater Infrastructure, Resilience Project Scoping Not Selected Did not meet HMA Requirements
South Carolina EMA-2021-BR-158-0002 Project scoping Edisto Beach-Interior Lagoon Study $80,000.00 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0005 Plan Town of Hilton Head Island Climate Adaptation Plan $56,250.00 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0006 Project scoping Mauldin/Fountain Inn Multi-Jurisdictional Stormwater Master Plan $375,000.00 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0008 Project scoping Analysis for the Upper Enoree River, Greenville County $230,130.50 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0013 Project Mitigation Partnership Building Project $104,119.50 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0014 Plan Sullivan's Island Coastal Community Resiliency Plan $112,500.00 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0017 Project scoping Chattooga Lake Dam D1637 Project Scoping Mountain Rest NID ID SC00519 $42,000.00 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0019 Management cost South Carolina Management Costs $1,284,819.27 Identified for Further Review - Round 1
South Carolina EMA-2021-BR-158-0004 Project Chestnut Bay Resilience Project $2,168,320.00 Identified for Further Review - Round 2
South Carolina EMA-2021-BR-158-0010 Project Old Village Drainage Improvement $5,677,915.50 Identified for Further Review - Round 2
South Dakota EMD-2021-BR-061-0005 Project OAHE Electric Line - Grey Goose Rd Not Selected Did not meet HMA Requirements
South Dakota EMD-2021-BR-061-0016 Project Douglas Electric Line G Not Selected Did not meet HMA Requirements
South Dakota EMD-2021-BR-057-0001 Plan TERO Building Code Development & Enforcement Project: $509,765.60 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0001 Plan Roberts County Pre-Disaster Mitigation Plan Update $14,310.00 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0002 Project Douglas Electric Line I $18,847.24 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0003 Project Central Electric Line 10 $178,739.42 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0004 Project scoping Kimball Stormwater Drainage Study $43,874.75 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0006 Plan Minnehaha-Lincoln Counties Joint Pre-Disaster Mitigation Plan Update $22,500.00 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0007 Plan Miner County Pre-Disaster Mitigation Plan Update $13,068.75 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0008 Project Central Electric Line 12/Aurora County $138,472.87 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0009 Plan Pennington County Pre-Disaster Mitigation Plan Update $52,500.00 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0011 Project Douglas Electric Line H $98,475.48 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0012 Plan Harding County Pre-Disaster Mitigation Plan Update $7,500.00 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0013 Management cost South Dakota Management Costs $83,488.50 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0014 Plan Clark County Pre-Disaster Mitigation Plan Update $14,625.00 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0015 Plan Clay County Pre-Disaster Mitigation Plan Update $11,250.00 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0017 Plan Custer County Pre-Disaster Mitigation Plan Update $12,000.00 Identified for Further Review - Round 1
South Dakota EMD-2021-BR-061-0010 Project Walworth County Resilient Systems Project Not Selected Not Selected for Further Review
Tennessee EMA-2021-BR-146-0001 Plan East Tennessee State University Hazard Mitigation Plan Update $120,519.00 Identified for Further Review - Round 1
Tennessee EMA-2021-BR-146-0002 Management cost Tennessee Management Cost $22,069.20 Identified for Further Review - Round 1
Tennessee EMA-2021-BR-146-0003 Project scoping Rutherford County Flood Mitigation Scoping Project $45,000.00 Identified for Further Review - Round 1
Tennessee EMA-2021-BR-146-0004 Project EPB Chattanooga Community Network Conversion for Critical Infrastructure Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0001 Project Bayou Din Detention Not Selected Did not meet HMA Requirements
Texas EMT-2021-BR-005-0005 Project scoping Austin Energy Distribution System Load Shed Resiliency $569,500.00 Identified for Further Review - Round 1
Texas EMT-2021-BR-005-0019 Plan Kenedy County's Sarita Drainage Master Plan $228,000.00 Identified for Further Review - Round 1
Texas EMT-2021-BR-005-0020 Project scoping Tarrant Regional Water District Kennedale Balancing Reservoir Water Resilience Project Scoping $202,500.00 Identified for Further Review - Round 1
Texas EMT-2021-BR-005-0028 Management cost Texas Management Costs $148,157.00 Identified for Further Review - Round 1
Texas EMT-2021-BR-005-0002 Project City of Harlingen 5th and 7th Storm Sewer Improvement Project Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0003 Project DD6 Delaware Street Detention Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0004 Project Jefferson County DD6 Channel 100A Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0006 Project Chimneystone Drainage Improvements Phase 2 Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0007 Project City of Richardson BRIC Generator Project Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0008 Project CCDD5 N. Main Drain Improvements at BUS 77 Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0009 Project City of Rowlett Sewer Lift Station Backup Generators Project Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0010 Project DD6 Borley Heights Relief Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0011 Project City of Victoria Aquifer Storage and Recovery (ASR) Injection Well Project Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0012 Project Weatherford Water/Wastewater Portable Pump Station Generator Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0013 Project Oyster Creek Diversion Channel Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0014 Project Galveston National Laboratory and Keiller/Robert E. Shope Laboratory Flood Mitigation Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0015 Project DD6 Fannin Street Diversion Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0016 Project DD6 Virginia Street Detention Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0017 Project Sawdust Bridge Road and Elevation Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0018 Project Roman Forest Blvd Bridge and Elevation Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0021 Project City of Southside Place Auden Street Drainage Improvement Project Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0022 Project City of Graham Water Plant Generator Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0023 Project Basic Science Building & Medical Research Building Flood Mitigation Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0024 Project Town of Combes-Nixon Rd Drainage Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0025 Project Brazos Landing/Avalon Drainage Improvements Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0026 Project Hopkins County Dual Use Tornado Safe room Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0027 Project Repetitive Loss Property Acquisition Projects in Dallas, Texas (Various Locations) Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0029 Project City of Port Arthur - Generators to Critical Facilities Not Selected Not Selected for Further Review
Texas EMT-2021-BR-005-0030 Project South Post Oak Detention Basin C547-00-00 & Channel Improvement C147-00-00 Harris County Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0019 Project Logan Service Center Seismic Retrofit Not Selected Did not meet HMA Requirements
Utah EMD-2021-BR-063-0021 Project Neffs Canyon Debris Basin Project Not Selected Did not meet HMA Requirements
Utah EMD-2021-BR-063-0005 Project scoping Beaver City Storm Water Drainage Study Project Scoping $110,467.90 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0007 Project scoping Beaver County Beaver River Project Scoping $40,500.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0009 Plan Region 5 Mitigation Plan Update $56,250.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0012 Project scoping Sevier County Gooseberry Landslide Project Scoping Study $152,250.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0013 Project scoping Jordan River Canal Project Scoping $333,600.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0014 Project scoping Grantsville City Project Scoping $41,100.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0017 Project scoping Escalante City Flood Project Scoping $41,715.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0018 Project scoping Richfield City Storm Water Drainage Study Project Scoping $108,750.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0023 Project scoping Salt Lake Community College Project Scoping South City Campus $92,867.10 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0024 Project scoping Grand County Pack Creek Project Scoping $22,500.00 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0025 Management cost Utah Management Costs $18,869,529.21 Identified for Further Review - Round 1
Utah EMD-2021-BR-063-0001 Project Long Term Sustainability for Provo’s Water Supply $50,000,000.00 Identified for Further Review - Round 2
Utah EMD-2021-BR-063-0004 Project Avoiding Faults: Geohazards and Water Resilience through Parallel Pipeline in Northern Utah $21,586,182.00 Identified for Further Review - Round 2
Utah EMD-2021-BR-063-0016 Project Salt Lake City Creek Water Treatment Plant Resilient Water Quality & Supply $36,680,000.00 Identified for Further Review - Round 2
Utah EMD-2021-BR-063-0002 Project Springdale Virgin River Streambank Protection Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0003 Project Salt Lake City Schools Community Microgrid Resiliency Project Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0006 Project Granite Schools Seismic Retrofit Project Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0008 Project Perry City Well #3 and Well #4 Generators Project Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0010 Project WBWCD Emergency Generators for Culinary Water Wells Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0011 Project Morgan City Hall / Well Generators Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0015 Project JVWTP Sedimentation Basins Earthquake, Drought, and Wildfire Resilience Upgrades Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0020 Project Kane County Joe Creek Culvert Replacement Project Not Selected Not Selected for Further Review
Utah EMD-2021-BR-063-0022 Project Ensuring Water Delivery from Treatment Plant in South Ogden for WBWCD Not Selected Not Selected for Further Review
Vermont EMB-2021-BR-007-0001 Project scoping Calais Kent Hill Road Culvert Scoping Study $31,936.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0002 Project scoping Stowe Electric System Resiliency Scoping Project $30,000.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0003 Project scoping Brandon North Street Bridge Project Scoping $80,000.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0004 Plan Local Hazard Mitigation Plan Development 2021 $299,325.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0005 Project scoping Lyndon Flood Reduction Scoping $60,000.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0006 Project scoping Bethel Gilead Brook Road Project Scoping $73,625.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0007 Project scoping Moscow Road Flood Resiliency Project Scoping $27,648.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0008 Project scoping Boulder Wood Stabilization Project Scoping in Bolton $19,680.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0009 Project scoping Roxbury Project Scoping Crossings over Sunny Brook $98,176.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0010 Project scoping Brookfield Halfway Brook Culvert Project Scoping $81,746.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0011 Project scoping Roxbury Project Scoping - Premo Road Bridge over Dog River $48,888.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0012 Project scoping Town of Poultney Rail Trail Bridge $48,000.00 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0013 Management cost Vermont Management Costs $126,491.71 Identified for Further Review - Round 1
Vermont EMB-2021-BR-007-0014 Project scoping Scoping Study - North Hollow Rd and Bryant Rd over Gold Brook $71,592.80 Identified for Further Review - Round 1
Virgin Islands EMN-2021-BR-070-0002 Plan Capacity and Stakeholder Assessment for USVI Resilience Hubs Not Selected Did not meet HMA Requirements
Virgin Islands EMN-2021-BR-070-0001 Management cost Virgin Islands Management Cost $50,000.00 Identified for Further Review - Round 1
Virgin Islands EMN-2021-BR-070-0003 Plan Federally Funded Generators Management Plan $450,000.00 Identified for Further Review - Round 1
Virginia EMP-2021-BR-051-0001 Project SWCD Dam Rehabilitation G2 - Leatherwood Creek #2A, Leatherwood Creek #3, Leatherwood Creek #5 Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0002 Project Critical Public Structure Generators Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0004 Project SWCD Dam Rehabilitation G1 - Johns Creek 1 and 2, South River 19 Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0005 Project SWCD Dam Rehabilitation G3 - Buffalo Creek #4, Bush River #4B, Roanoke Creek #68 Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0008 Project Waterfront Implementation Project Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0009 Project Greene/Stanardsville - Water Supply Protection Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0012 Project Communication Infrastructure Upgrades Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0014 Project Brooke Road Flood Mitigation and Resiliency Project Not Selected Did not meet HMA Requirements
Virginia EMP-2021-BR-051-0003 Project scoping Private Sector Engagement and Partnership $41,250.00 Identified for Further Review - Round 1
Virginia EMP-2021-BR-051-0007 Project scoping All Hazards Consortium - Energy Project Scoping $578,748.00 Identified for Further Review - Round 1
Virginia EMP-2021-BR-051-0015 Project scoping Henrico County - Water Reclamation Facility Flow Equalization Study $380,000.00 Identified for Further Review - Round 1
Virginia EMP-2021-BR-051-0016 Management cost Virginia Management Costs $3,774,418.40 Identified for Further Review - Round 1
Virginia EMP-2021-BR-051-0010 Project Eastern Shore Drive Drainage Improvement Project $25,144,014.00 Identified for Further Review - Round 2
Virginia EMP-2021-BR-051-0006 Project Henrico County Gambles Mill Pump Station Water and Sewer Protective Measures Not Selected Not Selected for Further Review
Virginia EMP-2021-BR-051-0011 Project Craig County Emergency Communication System Upgrade Not Selected Not Selected for Further Review
Virginia EMP-2021-BR-051-0013 Project Franklin County Emergency Communications System Not Selected Not Selected for Further Review
Washington EMS-2021-BR-044-0001 Project Building Climate Resilience in Clallam County, WA: the Dungeness Off-Channel Reservoir Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-044-0002 Plan Clallam County Energy Resilience Planning Scoping Project Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-083-0001 Management cost Shoalwater Bay Indian Tribe Management Costs Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-083-0002 Project scoping Shoalwater Bay Indian Tribe's Building Inventory Analysis Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-083-0003 Project Shoalwater Bay Indian Tribe's Communications Project Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-083-0004 Project scoping Shoalwater Bay Indian Tribe's Water Resiliency Analysis Project Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-084-0001 Plan Queets Relocation Phase 1 Engineering Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-093-0001 Plan Planning Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-093-0002 Project scoping Project Scoping Wildfire Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-093-0005 Project scoping Project Scoping Multiple Natural Hazards Not Selected Did not meet HMA Requirements
Washington EMS-2021-BR-044-0006 Project scoping Walla Walla Municipal Watershed Resiliency Plan $375,000.00 Identified for Further Review - Round 1
Washington EMS-2021-BR-044-0010 Project scoping Seattle Lower Duwamish Valley Sea Level Rise Mitigation Project Scoping $400,000.00 Identified for Further Review - Round 1
Washington EMS-2021-BR-044-0012 Management cost Washington State Management Costs Sub-Application $9,443,153.45 Identified for Further Review - Round 1
Washington EMS-2021-BR-048-0001 Management cost Management Costs $66,500.00 Identified for Further Review - Round 1
Washington EMS-2021-BR-048-0002 Plan Natural Hazards Mitigation Plan Update $243,000.00 Identified for Further Review - Round 1
Washington EMS-2021-BR-048-0003 Project scoping Stormwater Flooding Study $238,500.00 Identified for Further Review - Round 1
Washington EMS-2021-BR-048-0004 Project scoping Sanitary Sewer Seismic Retrofit Scoping $117,000.00 Identified for Further Review - Round 1
Washington EMS-2021-BR-089-0001 Project scoping Development of a Project Scoping Framework for Hazard Mitigation Plans $977,014.00 Identified for Further Review - Round 1
Washington EMS-2021-BR-093-0003 Project scoping Code Update $112,586.40 Identified for Further Review - Round 1
Washington EMS-2021-BR-093-0004 Management cost Management Cost $12,509.60 Identified for Further Review - Round 1
Washington EMS-2021-BR-044-0003 Project North 175th Street Soil Stabilization Project $8,869,500.00 Identified for Further Review - Round 2
Washington EMS-2021-BR-044-0004 Project 2021 Relocate Wells & WTP, Complete intertie for Emergency Water $2,166,295.50 Identified for Further Review - Round 2
Washington EMS-2021-BR-044-0008 Project North Shore Levee $50,000,000.00 Identified for Further Review - Round 2
Washington EMS-2021-BR-044-0009 Project City of Auburn Reservoir 2 Seismic Control Valve project $1,087,500.00 Identified for Further Review - Round 2
Washington EMS-2021-BR-044-0011 Project City of Seattle Good Shepherd Center South Annex Seismic Retrofit $380,517.58 Identified for Further Review - Round 2
Washington EMS-2021-BR-044-0005 Project Ocean Shores Seismic Retrofit Water Storage Not Selected Not Selected for Further Review
Washington EMS-2021-BR-044-0007 Project Covington Water District Tank 4 Replacement Project in Auburn Not Selected Not Selected for Further Review
West Virginia EMP-2021-BR-056-0002 Management cost Management Costs $34,337.66 Identified for Further Review - Round 1
West Virginia EMP-2021-BR-056-0003 Project scoping US Route 11 & CR 12 Flood Mitigation Study $202,500.00 Identified for Further Review - Round 1
West Virginia EMP-2021-BR-056-0001 Plan Building Resilient Infrastructures and Communities and Flood Mitigation Assistance $90,190.35 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0001 Project Hayward Community School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0003 Project Hillsboro School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0004 Project Grantsburg School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0005 Project Cuba City School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0006 Project Royall School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0008 Project Potosi School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0010 Project 2022 1st Avenue Revetment Reconstruction Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0015 Project Barron Area School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0016 Project Ladysmith School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0017 Project Medford School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0021 Project Platteville School District Community Safe Room Project Not Selected Did not meet HMA Requirements
Wisconsin EMC-2021-BR-064-0007 Project Radisson Community Safe Room $571,937.57 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0009 Plan Vilas County All Hazards Mitigation Plan Update $31,500.00 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0011 Plan Vernon County Mitigation Plan Update $44,811.90 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0012 Plan Ashland County Hazard Mitigation Plan Update $29,295.00 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0013 Plan Crawford County Mitigation Plan Update $44,990.70 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0014 Management cost Wisconsin Management Costs $956,642.29 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0018 Plan WEM State Planning/Outreach Grant $92,788.21 Identified for Further Review - Round 1
Wisconsin EMC-2021-BR-064-0019 Project Pheasant Branch Tributary Greenway Enhancement Project: City of Madison $6,028,190.00 Identified for Further Review - Round 2
Wisconsin EMC-2021-BR-064-0002 Project Lake Halle BRIC Safe Room Project Not Selected Not Selected for Further Review
Wisconsin EMC-2021-BR-064-0020 Project Kemper Center Shoreline Mitigation Project Not Selected Not Selected for Further Review
Wyoming EMD-2021-BR-047-0003 Project Generator Not Selected Did not meet HMA Requirements
Wyoming EMD-2021-BR-047-0001 Project scoping Scoping/Design for Crow Creek 19th Street Crossing Improvement $180,000.00 Identified for Further Review - Round 1
Wyoming EMD-2021-BR-047-0002 Project scoping Scoping/Design for Clear Creek Detention Storage $262,500.00 Identified for Further Review - Round 1
Wyoming EMD-2021-BR-047-0004 Project scoping Green River Diversion Dam & Killdeer Wetland Improvements/Project Scoping $75,000.00 Identified for Further Review - Round 1
Wyoming EMD-2021-BR-047-0006 Project scoping Donkey Creek Master Drainage Plan $187,500.00 Identified for Further Review - Round 1
Wyoming EMD-2021-BR-047-0007 Management cost Wyoming Office of Homeland Security - Management Costs $392,698.50 Identified for Further Review - Round 1
Wyoming EMD-2021-BR-047-0005 Project 2021 Lander Flooding: Structure Relocation and Property Acquisition $2,090,889.00 Identified for Further Review - Round 2