Ocean City MD
Maryland Emergency Management Agency
Ocean City MD
1st Appeal
Project Number: 19
Related Disaster Declarations:
Appeal Keywords: Flood Hazard Areas, Scope of Work, Structure Elevation
04/26/2017
Ocean City MD
1st Appeal
Project Number: 19
Related Disaster Declarations:
Appeal Keywords: Flood Hazard Areas, Scope of Work, Structure Elevation
04/26/2017
Appeal Summary | Back to Search
Appeal Summary
- Issue
- Scope of Work (SOW) was changed without prior approval; In accordance with 2 CFR Section 200.308, pass-through entities (MEMA) must obtain FEMA’s prior approval prior to any SOW change.
- Cost effectiveness needed re-evaluation.
- Reason for appeal approval
- The Applicant/Recipient submitted a revised Benefit Cost Analysis (BCA) resulting in a favorable benefit/cost ratio.
- Reference
- 2 CFR Section 200.308