Project Management and Design Services
Appeal Brief
Disaster | 4614 |
Applicant | Borough of Jamesburg |
Appeal Type | Second |
PA ID# | 023-34890-00 |
PW ID# | GMP 548926/PW 2030 |
Date Signed | 2024-10-17T16:00:00 |
Summary Paragraph
From September 1-3, 2021, flooding from Hurricane Ida damaged a police station (Facility) owned by the Borough of Jamesburg (Applicant). The Applicant requested Public Assistance funding to replace destroyed contents, make repairs, and implement hazard mitigation measures at the Facility. FEMA created Grants Manager Project 548926 to document the Applicant’s claim. The Applicant hired Clarke Caton Hintz (CCH), an architectural firm, to design renovations and an addition to the Facility. Estimated costs for CCH’s services totaled $336,500.00. In a Determination Memorandum, FEMA found that the work proposed by CCH included upgrades unrelated to disaster-caused damage to the Facility. FEMA denied $336,500.00 for CCH’s services. The Applicant submitted a first appeal revising the amount in dispute to $34,100.00 for costs paid to CCH. The Applicant asserted that it engaged CCH at FEMA’s direction, and thus FEMA was liable for the costs at issue. The Applicant stated that the Facility’s holding cells required upgrades per New Jersey codes and standards. The FEMA Region 2 Regional Administrator denied the appeal. FEMA found that the codes provided by the Applicant did not apply to the requested repairs, and there was no relationship between the holding cell upgrades and disaster related damage to the Facility. Therefore, both the upgrades and the costs for CCH’s services were ineligible. The Applicant submitted a second appeal requesting FEMA approve $34,100.00. The Applicant does not dispute FEMA’s denial of costs for upgrades to the Facility. However, it again states that it sought CCH’s services at FEMA’s direction, and thus FEMA should reimburse the costs at issue.
Authorities
- Stafford Act §§ 406(a)(1)(A), (e), 42 U.S.C. §§ 5172(a)(1)(A), (e).
- 44 C.F.R. §§ 206.223(a)(1), 206.226.
- PAPPG, at 51, 92, 140, and 145.
- Sumter (Cnty.), FEMA-4241-DR-SC, at 3.
Headnotes
- Costs for project management and design services associated with improvements or other ineligible work are not eligible.
- On second appeal, the Applicant acknowledges that the improvements to the Facility proposed by CCH are ineligible expenses.
- FEMA’s policy states explicitly that costs for project management and design services associated with improvements and other ineligible work are not eligible.
- Therefore, because the project design costs at issue are associated with ineligible improvements, the costs are ineligible.
Conclusion
The costs for the project design services at issue are associated with ineligible improvements. Consequently, the design services costs are ineligible. Therefore, this appeal is denied.
Appeal Letter
SENT VIA EMAIL
Lieutenant Colonel Christopher DeMaise
Governor’s Authorized Representative
Division of State Police, Recovery Bureau
1034 River Road
West Trenton, NJ 08628
Michael Capabianco
Business Administrator
Borough of Jamesburg
131 Perrineville Road
Jamesburg, NJ 08831-1672
Re: Second Appeal – Borough of Jamesburg, PA ID: 023-34890-00, FEMA-4614-DR-NJ, Grants Manager Project (GMP) 548926/Project Worksheet (PW) 2030, Project Management and Design Services
Dear Lieutenant Colonel Christopher DeMaise and Michael Capabianco:
This is in response to the New Jersey Division of State Police (Recipient) letter dated August 12, 2024, which transmitted the referenced second appeal on behalf of Borough of Jamesburg (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of funding in the amount of $34,100.00 for project design services.
As explained in the enclosed analysis, I have determined that the costs for the project design services at issue are associated with ineligible improvements. Consequently, the design services costs are ineligible. Therefore, this appeal is denied.
This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.
Sincerely,
/S/
Robert M. Pesapane
Director, Public Assistance
Enclosure
cc: David Warrington
Regional Administrator
FEMA Region 2
Appeal Analysis
Background
From September 1 through 3, 2021, the remnants of Hurricane Ida impacted areas throughout New Jersey.[1] Flooding from the disaster damaged a police station (Facility) located in the lower level of a municipal building owned by the Borough of Jamesburg (Applicant). The Applicant requested Public Assistance (PA) funding to replace destroyed contents, make repairs, and implement hazard mitigation (HM) measures at the Facility, with total costs of $355,621.00.[2] FEMA created Grants Manager Project 548926 to document the Applicant’s claim as category E (buildings and equipment) work.
The Applicant hired Clarke Caton Hintz (CCH), an architectural firm, to prepare project design plans for the Facility. CCH submitted fee proposals for its services, including renovations to the Facility and construction of a one-story, 3,826 square foot addition to the municipal building.[3] CCH estimated costs of $336,500.00 for the project design services.
On March 23, 2023, FEMA conducted a “tabletop” site inspection of the Facility using information and photographs provided by the Applicant to complete the damage description and dimensions (DDD) section of the site inspection report.[4] The DDD included damage to interior features, including drywall, base molding, and chair rail; and damaged or destroyed contents, including conference tables, desks, chairs, filing cabinets, bookshelves, appliances, and a gun locker. On June 8, 2023, the Applicant approved the DDD in Grants Portal/Grants Manager (GM).[5]
In a Determination Memorandum (DM) uploaded to GM on August 2, 2023, FEMA found that the work proposed by CCH included “design renovations and upgrades,” which “deviate[d] from the disaster-related damage originally captured for the Facility.”[6] Thus, FEMA determined that the work was not necessary as a result of the disaster, and denied $336,500.00 for CCH’s project design services.[7]
First Appeal
The Applicant submitted a first appeal dated September 11, 2023. The Applicant revised the amount in dispute, requesting $34,100.00 in costs paid to date to CCH. It described the history of the project development process, asserting that it engaged CCH and incurred the costs at issue following a verbal conversation with FEMA’s representatives. The Applicant stated that FEMA subsequently opined that the work recommended by CCH would not be found eligible, at which point it “immediately ceased any FEMA approved work with [CCH].”[8] It asserted that FEMA’s representatives did not have the discretion under federal law, regulation, or policy to direct the expenditure of public funding or “to verify [the] eligibility of a project before the project has been through the various management reviews.”[9] Moreover, it asserted that “FEMA’s insistence and directive to perform new construction [was] unreasonable,” and thus the construction proposed by CCH was unnecessary; however, FEMA had prevented it from exploring more reasonable cost options such as “reconfiguring internal items and the code compliance sally port.”[10] Therefore, the Applicant argued that because FEMA’s representatives acted outside of their authorized discretion, “FEMA [wa]s liable for all costs associated with the [CCH] work.”[11]
The Applicant also stated that the Facility’s holding cells required upgrades in order to comply with current codes and standards. It attached copies of the New Jersey specifications for holding cell construction, which it asserted met the criteria for eligible codes and standards under federal regulation.[12] The Applicant stated that it understood it would be responsible for any ineligible Facility upgrades. Finally, the Applicant noted that the disaster caused damage to the Facility, which was not disputed. Therefore, it asserted that work to reconstruct the holding cells was required as a result of the disaster. In a transmittal letter dated September 22, 2023, the New Jersey Division of State Police (Recipient) expressed support for the appeal. The Recipient stated that FEMA denied costs to reconstruct the Facility, and that the Applicant was requesting reasonable costs for “internally moving the holding cells, creation of the code required sally port and any [Americans with Disabilities Act (ADA)] compliance issues.”[13]
On June 6, 2024, the FEMA Region 2 Regional Administrator denied the appeal. FEMA found that the New Jersey Department of Corrections and Juvenile Justice Commission specifications for holding cell construction did not apply to the requested repairs, as the former applied “only to new facility construction and renovation, not repairs,” and the latter code did not contain specifications requiring the reconstruction of holding cells.[14] Additionally, FEMA stated that the Applicant had not identified any provision of the ADA that required holding cell upgrades. Further, FEMA noted that, for construction design services to be eligible, “the required facility alterations must have a reasonable and technically supportable relationship to the damaged elements of the facility.”[15] However, FEMA determined that no such relationship existed between the upgrades the Applicant requested and the disaster related damage to the Facility. Therefore, FEMA found that the upgrades were ineligible and, consequently, the costs for CCH’s services were also ineligible. Finally, FEMA stated that “it is not bound by statements of rank-and-file employees prior to management review regarding the eligibility of the claimed work.”[16]
Second Appeal
The Applicant submitted a second appeal dated July 31, 2024, requesting FEMA approve $34,100.00 for the CCH project design services. The Applicant does not dispute FEMA’s denial of costs for upgrades to the Facility. However, it again argues that it sought CCH’s services at the direction of FEMA’s representatives and asserts that FEMA’s position in the first appeal decision regarding the “statements of rank-and-file employees … is against FEMA’s own policy.”[17] It quotes the Public Assistance Program and Policy Guide (PAPPG), which states that “PA staff at the [Joint Field Office] are responsible for providing customer service to each Applicant, conducting site inspections, obtaining project information and documentation, determining eligibility, and awarding projects.”[18] Thus, the Applicant asserts that FEMA policy “demonstrates that the PA staff is responsible for determining eligibility, not management,” and the Applicant “should be reimbursed as per FEMA guidelines.”[19] In a transmittal letter dated August 12, 2024, the Recipient expresses support for the appeal.
Discussion
FEMA may provide funding to a local government for the repair of public facilities damaged by a major disaster based on the predisaster design and function of the facilities and in conformity with applicable codes and standards.[20] To be eligible for PA funding, work must be required as a result of the disaster.[21] FEMA may provide PA funding for costs related to project management and design activities as part of the project.[22] Architectural, engineering, and design services for the approved scope of work, including HM, are eligible provided the services are reasonable.[23] When evaluating the eligibility of project management and design services, FEMA considers whether the project includes improvements that are ineligible for funding.[24] Costs for project management and design services associated with improvements or other ineligible work are not eligible.[25] No approval given by field personnel outside of the obligation process can be considered legally binding.[26]
Here, the Applicant requests reimbursement for a partial payment for CCH’s services in designing the Facility improvement project. However, on second appeal, the Applicant acknowledges that “the proposed improvements to the [Facility] are ineligible expenses.”[27] As stated above, FEMA’s policy explicitly states that costs for project management and design services associated with improvements and other ineligible work are not eligible.[28] Therefore, regardless of the Applicant’s contention that it obtained CCH’s services at the direction of FEMA’s field personnel (without FEMA approving any costs for architectural, engineering, or design services through the obligation process), because the project design costs at issue are associated with ineligible improvements, the costs are ineligible.
Conclusion
The costs for the project design services at issue are associated with ineligible improvements. Consequently, the design services costs are ineligible. Therefore, this appeal is denied.
[1] The President issued a major disaster declaration on September 5, 2021.
[2] Grants Manager Project (GMP) 548926, Project Report.
[3] See Clarke Caton Hintz, Jamesburg Police Department Addition and Renovation, Architectural & Engineering Fee Proposal, at 1 (Oct. 10, 2022). CCH stated that the one-story addition to the municipal building would include “dispatch, [a] meeting room, armory, offices, unisex restrooms, processing with jail cells, elevator and sally port.”
[4] GMP 548926, Project Report (“[t]his report is a tabletop inspection for the [Applicant] … [a]ll information and photo[graphs] were furnished by the [A]pplicant”).
[5] GMP 548926, Action Log.
[6] Determination Memorandum, Borough of Jamesburg, FEMA-4614-DR-NJ, at 3 (Aug. 2, 2023).
[7] In January 2024, FEMA obligated $355,621.00 for GMP 548926, for work to replace destroyed contents, make repairs, and implement hazard mitigation measures at the Facility. See Project Worksheet 2030, Borough of Jamesburg, Version 0 (Jan. 18, 2024).
[8] First Appeal Letter from Administrator, Borough of Jamesburg, to Pub. Assistance Appeals, FEMA Region 2, at 2 (Sept. 11, 2023).
[9] Id. at 3.
[10] Id. at 4. A sally port is defined as “a secure entryway (as at a prison) that consists of a series of doors or gate.” Merriam-Webster Dictionary, https://www.merriam-webster.com/dictionary/sally%20port (last visited Aug. 21, 2024).
[11] Id. at 3. In support, the Applicant cites the Robert T. Stafford Disaster Relief and Emergency Assistance (Stafford) Act provision regarding non-liability, i.e., “[t]he Federal Government shall not be liable for any claim based upon the exercise or performance of or the failure to exercise or perform a discretionary function or duty on the part of a Federal agency or an employee of the Federal Government in carrying out the provisions of this Act.” Stafford Act § 305, Title 42, United States Code (U.S.C.) § 5148 (2018). It argues that FEMA’s representatives were not exercising such a discretionary function in the matters specified above and, therefore, the non-liability provision of the Stafford Act does not apply.
[12] Upgrades required by federal or state, local, territorial, or tribal (SLTT) repair or replacement codes or standards are eligible only if the code or standard: (1) applies to the type of restoration required; (2) is appropriate to the predisaster use of the facility; (3) is found reasonable, in writing, formally adopted by the SLTT government, and implemented by the applicant on or before the declaration date, or is a legal federal requirement; (4) applies uniformly; and (5) was enforced during the time it was in effect. See Title 44 of the Code of Federal Regulations (C.F.R.) § 206.226(d) (2020); Public Assistance Program and Policy Guide, FP 104-009-2, at 145 (June 1, 2020) [hereinafter PAPPG].
[13] Letter from Unit Head, Pub. Assistance, N.J. Div. of State Police, to Reg’l Adm’r, FEMA Region 2, at 1 (Sept. 22, 2023).
[14] FEMA First Appeal Analysis, Borough of Jamesburg, FEMA-4614-DR-NJ, at 3 (June 6, 2024).
[15] Id. (quoting and citing the “Accessibility for Individuals with Disabilities” section of the PAPPG). See PAPPG, at 152.
[16] Id. at 4.
[17] Second Appeal Letter from Adm’r, Borough of Jamesburg, to Pub. Assistance Supervisor, N.J. Office of Emergency Mgmt., at 1-2 (July 31, 2024) [hereinafter Second Appeal Letter].
[18] Id. at 2 (citing and quoting PAPPG, at 33).
[19] Second Appeal Letter, at 2.
[20] Stafford Act §§ 406(a)(1)(A), (e), 42 U.S.C. §§ 5172(a)(1)(A), (e); 44 C.F.R. § 206.226; PAPPG, at 140, 145.
[21] 44 C.F.R. § 206.223(a)(1); PAPPG, at 51.
[22] PAPPG, at 92.
[23] Id. (“[s]ome projects do not need these services or require only basic services, while others require specialized engineering and design”).
[24] Id.
[25] Id.
[26] FEMA Second Appeal Analysis, Sumter (Cnty.), FEMA-4241-DR-SC, at 3 (Nov. 20, 2020). See Columbus Reg’l Hosp. v. FEMA, 708 F.3d 893, 899 (7th Cir. 2013) (“That promise, if made, lacks legal significance. No field employee can commit the agency to pay more than the statute and regulations require.”). See generally 44 C.F.R. § 206.201(l) (stating that “[p]roject approval means the process in which the Regional Administrator, or designee, reviews and signs an approval of work and costs on a Project Worksheet or on a batch of Project Worksheets. Such approval is also an obligation of funds to the recipient.”).
[27] Second Appeal Letter, at 1.
[28] PAPPG, at 92.