Procurement and Contracting Requirements/Allowable Costs & Reasonable Costs

Appeal Brief Appeal Letter Appeal Analysis

Appeal Brief

Disaster1791
ApplicantStafford Municipal School District
Appeal TypeSecond
PA ID#157-UWQRE-00
PW ID#3942
Date Signed2023-08-18T16:00:00

Summary Paragraph

From September 7 through October 2, 2008, Hurricane Ike struck Texas with high winds, heavy rains, and storm surge. The disaster tore nine skylights off the flat roof of the Applicant’s Facility, causing water to enter the Facility. The water infiltration resulted in additional Facility damage. The Applicant requested Public Assistance (PA) funding for costs associated with the Facility repairs. FEMA prepared and obligated multiple versions of project worksheet (PW) 3942 to capture the scope of work (SOW) of $318,447.87 for wind damage repairs and $7,202.79 in direct administrative costs (DAC). FEMA also reduced costs according to actual insurance proceeds of $209,750.96, for a total claim of $115,899.70. On February 8, 2022, the Texas Division of Emergency Management (Recipient) submitted a Large Project Closeout Request to FEMA. A Financial Compliance Review, prepared by the Recipient’s auditor, recommended that FEMA deobligate all the funds associated with repairs because the Applicant had not substantiated any of the contract costs and had not provided documentation to show it followed competitive procurement procedures. FEMA prepared an amendment to PW 3942, deobligating the entire $115,899.70. FEMA stated that, in the absence of supporting documentation, it could not determine whether the costs were reasonable or whether the Applicant had accomplished the purpose of the grant. FEMA also explained that because the Applicant could not substantiate repair costs or verify project completion, all DAC tied to those repairs was similarly ineligible. The Applicant appealed, stating the deobligation is inconsistent with federal law, regulations, and FEMA policy. The Recipient supported the appeal. FEMA denied the appeal, finding the Applicant did not provide adequate documentation to support the claimed costs. The Applicant submits a second appeal, reiterating first appeal arguments and arguing that FEMA incorrectly stated the Recipient’s position. The Recipient supports the appeal.

Authorities and Second Appeals

  • Stafford Act §705(c).
  • 44 C.F.R. §§ 13.36, 13.43.
  • PA Guide, at 53.
  • FP 205-081-2, at 4.
  • Vidor Indep. School Dist., FEMA-1791-DR-TXat 4; Port of Galveston, FEMA-1791-DR-TX, at 4, 6; St. Thomas by the Sea Parish, FEMA-4563-DR-AL, at 6-7.

Headnotes

FEMA provides PA funding for contract costs based on the terms of the contract if an applicant meets federal procurement and contracting requirements. FEMA has discretionary authority that it exercises on a case-by-case basis to resolve issues of noncompliance, including procurement noncompliance. For costs to be allowable and therefore reimbursable, under a PA award, the costs must be, among other requirements, reasonable and adequately documented.

  • The Applicant has not provided information documenting the procurement history for the contracted work. However, the Applicant has shown that the completed repair costs were reasonable and adequately documented; thus, FEMA determines that funding totaling $105,740.85 represents reasonable costs a prudent person would incur for the completed work at issue.

Conclusion

FEMA finds the Applicant did not demonstrate that it procured its contracts in accordance with federal regulations. However, the Applicant has substantiated through documentation that $105,740.85 of the requested costs for completed work are reasonable and directly tied to the performance of eligible work. FEMA awards reasonable costs of $105,740.85 for the completed work. Therefore, this appeal is partially granted. 


 

Appeal Letter

SENT VIA EMAIL                                             

 

W. Nim Kidd, MPA, CEM

Chief, Texas Division of Emergency Management

Vice Chancellor-The Texas A&M University System

2883 Highway 71 E.

P.O. Box 285

Del Valle, TX   78617-9998

Robert Bostic

Superintendent

Stafford Municipal School District

1633 Staffordshire Road

Staffordshire, TX 77477

 

 

Re: Second Appeal – Stafford Municipal School District, PA ID: 157-UWQRE-00, FEMA-1791-DR-TX, Project Worksheet (PW) 3942, Procurement and Contracting Requirements/Allowable Costs & Reasonable Costs

 

Dear Chief Kidd and Robert Bostic:

This is in response to the Texas Division of Emergency Management’s (Recipient) letter dated May 23, 2023, which transmitted the referenced second appeal on behalf of Stafford Municipal School District (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) deobligation of funding in the amount of $115,899.70 for contract costs and direct administrative costs associated with work to repair the Applicant’s middle school/high school building and annex. 

As explained in the enclosed analysis, I have determined that the Applicant did not demonstrate that it procured its contracts in accordance with federal regulations. However, the Applicant has substantiated through documentation that $105,740.85 of the requested costs for completed work are allowable and reasonable and directly tied to the performance of eligible work. As such, FEMA awards reasonable costs of $105,740.85 for the completed work. Therefore, this appeal is partially granted.

This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.

 

                                                                                           Sincerely, 

                                                                                              /S/

                                                                                           Tod Wells

                                                                                           Deputy Director for Policy

                                                                                           Public Assistance Division

 

Enclosure

cc:  George A. Robinson

Regional Administrator

FEMA Region 6

 

Appeal Analysis

Background

From September 7 through October 2, 2008, Hurricane Ike struck Texas with high winds, heavy rains, and storm surge. The disaster tore nine skylights off the flat roof of the Stafford Municipal School District’s (Applicant) middle school/high school building and annex (Facility), causing water to enter the Facility. The water infiltration resulted in additional damage to the Facility. The Applicant requested Public Assistance (PA) funding for costs associated with the Facility repairs. FEMA prepared and obligated multiple versions of project worksheet (PW) 3942 to capture the scope of work (SOW) of $318,447.87 for wind damage repairs and $7,202.79 in direct administrative costs (DAC). FEMA also reduced costs according to actual insurance proceeds of $209,750.96, for a total claim of $115,899.70. The repair costs included actual contract costs for completed work, as well as $10,158.85 in estimated costs for work yet to be completed to enclose a skylight.[1]

On February 8, 2022, the Texas Division of Emergency Management (Recipient) submitted a Large Project Closeout Request to FEMA. A Financial Compliance Review, prepared by the Recipient’s auditor, recommended that FEMA deobligate all the funds associated with repairs because the Applicant had not substantiated any of the contract costs and had not provided documentation to show it had followed competitive procurement procedures. On June 29, 2022, FEMA prepared an amendment to PW 3942, deobligating the entire $115,899.70 for the Facility repairs and DAC. FEMA stated that, in the absence of supporting documentation such as cancelled checks, payrolls, and time/attendance records, it could not determine whether the costs were reasonable or whether the Applicant had accomplished the purpose of the grant. FEMA also explained that because the Applicant could not substantiate repair costs or verify project completion, all DAC tied to those repairs was similarly ineligible.

First Appeal 

The Applicant appealed, stating the FEMA deobligation was inconsistent with federal law, regulations, and FEMA policy. The Applicant stated that it complied with the record retention schedules mandated by the Texas State Library and Archives Commission and Title 2 Code of Federal Regulations § 200.334[2], and that FEMA never notified it of the need to retain records past the three year-period following the disbursement of funds based on any exception to 2 C.F.R. § 200.334 requirements. The Applicant also stated that requiring it to pay back the funds would cause it financial hardship. The Recipient supported the appeal. In a March 16, 2023 decision, the FEMA Region 6 Regional Administrator denied the appeal, finding the Applicant did not provide adequate documentation to support the claimed costs. 

Second Appeal

The Applicant submitted a second appeal on May 15, 2023, reiterating its first appeal arguments, and also arguing that FEMA was untimely in issuing its first appeal decision and that it misrepresented the Recipient’s position as supporting the deobligation. The Applicant disputes the deobligation of $115,899.70. The Recipient transmitted the appeal on May 23, 2023, along with a letter of support.

 

Discussion

Procurement and Contracting Requirements

Title 44 of the Code of Federal Regulations (44 C.F.R.) Part 13, Uniform Administrative Requirements for Grants and Cooperative Agreements to State and Local Governments, codifies the requirements for local governments seeking, receiving, or administering PA grants.[3] Section 13.36 requires an applicant to procure services in a manner that allows full and open competition.[4] Among other requirements, applicants must also perform and document a cost or price analysis in connection with every procurement action, and take necessary affirmative steps to assure that minority-owned firms, women’s business enterprises, and labor surplus area firms are used when possible.[5] The Applicant also must maintain records sufficient to detail the significant history of its procurement.[6] 

As a local government entity, the Applicant was required to comply with federal procurement standards found in 44 C.F.R. § 13.36 at the time of the disaster declaration. Here, the Applicant did not maintain records sufficient to detail the history of its procurement, and thus it did not demonstrate that it: (1) procured services in a manner that allowed full and open competition; (2) performed and documented a cost or price analysis in connection with the procurement of the service contracts; and (3) took necessary affirmative steps to assure that minority-owned firms, women’s business enterprises, and labor surplus area firms were used when possible. Therefore, the Applicant did not demonstrate that it properly procured the repair work contracts.

 

Allowable Costs & Reasonable Costs

FEMA has discretionary authority that it exercises on a case-by-case basis to resolve issues of noncompliance with procurement requirements.[7] The range of authorized actions include disallowing all or part of the cost of the activity or action not in compliance.[8] While enforcement action taken by FEMA is discretionary, the action selected must be appropriate given the circumstances.[9] To the extent FEMA agrees to allow funding, FEMA first determines whether costs are reasonable.[10] For costs to be allowable and therefore reimbursable, under a PA award, the costs must be, among other requirements, reasonable and adequately documented.[11] A cost is reasonable if, in its nature or amount, it does not exceed that which would be incurred by a prudent person under the circumstances prevailing at the time the decision was made to incur the costs.[12]

Given the Applicant’s procurement noncompliance, FEMA previously disallowed the contract costs at issue because it was unable to determine reasonable costs without documentation such as cancelled checks, payrolls, and time/attendance records, which the Applicant states it did not maintain. However, FEMA can also use other information, including paid invoices, to help determine reasonableness.[13] Here, the invoices contained within the Administrative Record provide sufficient detail to directly tie the claimed costs of $308,289.02 to associated work in PW 3942 and show that those costs are reasonable. The descriptions in the invoices are specific enough for FEMA to evaluate the eligibility of the work and costs, and the multiple invoices from multiple companies are date-stamped and contain contemporaneous notations confirming that work was complete and detailing the costs.[14] The SOW included in the PW was 97 percent complete and the PW itself was written based on actual contract costs.[15] Although FEMA did not make a reasonable cost determination in the project at that time, FEMA has now performed a reasonable cost analysis as part of its second appeal review and determines that PA funding totaling $308,289.02 represents reasonable costs a prudent person would incur for the work at issue. For example, on second appeal, FEMA reviewed an invoice for labor for journeyman electrical work to install, repair and rewire lights, billed at $65.00 per hour, and finds the costs to be fair and equitable for the type of work being performed. Thus, FEMA finds that the Applicant has provided documentation to reinstate $308,289.02 in deobligated funding for the completed repairs.[16] Additionally, FEMA previously deobligated DAC tied to unsubstantiated costs for completed repairs. Because FEMA is reinstating all completed repair costs after substantiating reasonable and eligible costs, the agency is also reinstating $7,202.79 in deobligated DAC.

However, FEMA upholds its deobligation of $10,158.85 in estimated costs for enclosing a skylight because the Applicant did not substantiate through documentation that the repair was completed, and if so, the actual costs of those repairs.[17]

 

Conclusion

FEMA finds the Applicant did not demonstrate that it procured its contracts in accordance with federal regulations. However, the Applicant has substantiated through documentation that $105,740.85 of the requested costs for completed work are reasonable and directly tied to the performance of eligible work. FEMA awards reasonable costs of $105,740.85 for the completed work. Therefore, this appeal is partially granted.

 


 

[1] See Project Worksheet 3942, Stafford Mun. Sch. Dist., Version 1 (Dec. 8, 2008).

[2] Section 200.334 of Title 2 of the Code of Federal Regulation provides that financial records, supporting documents, statistical records, and all other non-federal entity records pertinent to a federal award must be retained for a period of three years from the date of submission of the final expenditure report or, for Federal awards that are renewed quarterly or annually, from the date of the submission of the quarterly or annual financial report, respectively, as reported to the Federal awarding agency or pass-through entity in the case of a subrecipient. It further provides that federal awarding agencies and pass-through entities must not impose any other record retention requirements upon non-federal entities. 

[3] Title 44 of the Code of Federal Regulations (44 C.F.R.) Part 13 sets forth requirements for grants to state, local, 

and Indian tribal governments and was applicable to all major disasters declared before December 26, 2014. 

[4] 44 C.F.R. § 13.36(c)(1) (2007). Noncompetitive procurement may be allowed when the award of a contract is 

infeasible under small purchase procedures, sealed bids, or competitive proposals and one of the following 

circumstances applies: (1) the item or service is only available from a single source; (2) a public exigency or 

emergency does not allow for delay; (3) the awarding agency allows for noncompetitive bids; or (4) after solicitation 

from a number of sources, competition is deemed inadequate; 44 C.F.R. § 13.36(d)(4).

[5] 44 C.F.R.§ 13.36(e)(1), 13.36(f)(1).

[6] 44 C.F.R. § 13.36(b)(9).

[7] 44 C.F.R. § 13.43; FEMA Second Appeal Analysis, Port of Galveston, (PW) 14996, FEMA-1791-DR-TX, at 4 (May 11, 2023).

[8] 44 C.F.R. § 13.43(a); Port of Galveston, (PW) 14996, FEMA-1791-DR-TX, at 6.

[9] Id.

[10] Public Assistance Guide, FEMA 322, at 53 (June 2007); Port of Galveston, (PW) 14996, FEMA-1791-DR-TX, 

at 4.

[11] Office Of Mgmt. & Budget, Exec. Office Of The President, OMB Circular A-87, Cost Principles For State, Local, And Indian Tribal Governments, Att. A § (C)(1)(A) AND (J) (2004). Per 44 C.F.R. § 13.22(b), for local government costs, the applicable cost principles are found in OMB Circular A-87; see also FEMA Second Appeal Analysis, Vidor Indep. School Dist., FEMA-1791-DR-TX (Mar. 3, 2023) [hereinafter Vidor]. In Vidor, FEMA was unable to award reasonable costs because the applicant no longer had any documentation to support costs as its invoices had to be shredded due to a 2019 flood that water-logged its files and its bank no longer retained the banking records. In contrast, in this appeal, the Applicant has source documentation in the form of invoices in EMMIE. The invoices are not estimates but actual costs and indicate that the work was actually performed.

[12] OMB Circular A-87, ATT. A § (C)(2).

[13] See FEMA Second Appeal Analysis, St. Thomas by the Sea Parish (Orange Beach), FEMA-4563-DR-AL, at 6-7 (Feb. 15, 2023) (FEMA exercised its discretionary authority to award reasonable costs for project where FEMA determined that Public Assistance funding totaling $262,929.59 represented reasonable costs a prudent person would incur for the emergency protective measures at issue. On second appeal, FEMA examined the available information pertaining to the Facility and the work the contractor performed and used RS Means data to adjust for the locale to determine reasonable costs).

[14] For example, in the documentation the Applicant submitted, an invoice marked Exhibit 15 for Kimball Construction Services Inc., dated October 2, 2008, contains the following specific descriptions of the work: (1) dust barriers and masonite carpet protection; (2) demolition of the furr downs and walls; (3) new drywall where damaged drywall was removed in classrooms; (4) new metal stud framing and drywall in corridors for furr downs; (5) new acoustical lay in ceilings where skylights were removed; (6) paintings. The invoice contains an amount due of $79,876.00 and states “the work was performed during days, evenings and weekends as requested.” The invoice contains a handwritten note “Ike repairs, okay to pay.” The Applicant also separated out costs for individual projects and highlighted them in the invoices.

[15] The Project Completion and Certification report (P4), which the Applicant certified on October 17, 2008, also stated that the project costs were $115,899.70.

[16] Invoices for PW 3942 support that contract costs total $308,289.02. FEMA applied insurance reductions to that amount prior to awarding funding, and the Applicant has not challenged those insurance adjustments on second appeal.

[17] Neither the Applicant nor the Recipient raise Section 705(c) of the Stafford Act as an argument against the deobligation in their appeal letters; however, FEMA is not barred from deobligating this amount under Section 705(c). As occurred in this instance, FEMA’s Section 705 policy allows FEMA to adjust and correct project funding based on properly supported actual costs for the approved and completed scope of work as appropriate. See The Robert T. Stafford Disaster Relief and Emergency Assistance (Stafford) Act, § 705(c), Title 42, United 

States Code (42 U.S.C.) § 5205(c) (2006); FEMA Policy (FP) 205-081-2, Stafford Act Section 705, Disaster Grant Closeout Procedures, at 4 (June 2, 2021). 

Last updated