Allowable Costs and Reasonable Costs, Financial Accounting and Reconciliation

Appeal Brief Appeal Letter Appeal Analysis

Appeal Brief

Disaster4399
ApplicantSchool Board of Bay County
Appeal TypeSecond
PA ID#005-U5PCR-00
PW ID#GMP 113459/ PW 2156
Date Signed2023-07-21T16:00:00

Summary Paragraph

On October 10, 2018, Hurricane Michael struck Florida, damaging to the Applicant’s the Lynn Haven Elementary School Gymnasium (Facility). The Applicant requested Public Assistance (PA) funding for the Facility’s replacement. FEMA prepared Grants Manager Project 113459 based on the Applicant’s building inspections and representation of damage. FEMA issued requests for Information (RFI) requesting confirmation of Facility dimensions and adjustment to various inconsistent quantities, unsupported percentage factors and soft costs in the Applicant’s estimates. The Applicant responded with a revised cost estimate. FEMA issued a Determination Memorandum (DM) denying $269,026.83 and capping reimbursement at approved cost estimates. The Applicant appealed, seeking the denied DM costs, and contending that it was not required to provide invoices supporting completed work until project closeout and that FEMA policy allowed for funding completed work using estimated costs. FEMA issued another RFI, noting the DM did not adequately communicate all applicable eligibility issues. The Applicant responded, confirming it repaired the Facility and providing additional completed and contracted work documentation. The FEMA Region 4 Regional Administrator denied the appeal, performed a reasonable cost analysis, and found an underrun of $647,079.88. FEMA also determined that federal law did not bar the recovery of funds and deobligated funding for the underrun amount. The Applicant submitted its second appeal seeking $121,338.19. reiterating its first appeal arguments and providing an additional pay application.

Authorities and Second Appeals

  • Stafford Act §§ 406(a),705 (c).
  • 2 C.F.R. § 200.403; 44 C.F.R. §§ 206.205(b), 206.206.
  • PAPPG, at 21-22, 144.
  • Sch. Bd. Of Bay Cnty., FEMA-4339-DR-FL, at 2, Campbell Cty. Fire Dist. #1, FEMA-4497-DR-KY, at 3.

Headnotes

  • To be eligible, costs must be directly tied to the performance of eligible work and be adequately documented.
    • The Applicant provided adequate documentation to demonstrate that the repairs to its Facility and associated costs were directly tied to the performance of eligible work.

Conclusion

The Applicant has demonstrated that the costs claimed are directly tied to the performance of completed eligible work. Accordingly, this appeal is granted in the amount of $121,338.19 and  the Regional Administrator is requested to take appropriate action to implement this determination.


 

Appeal Letter

SENT VIA EMAIL

Kevin Guthrie                                                                    Lee Walters

Director                                                                              Executive Director of Facilities

Florida Division of Emergency Management               School Board of Bay County Florida

2555 Shumard Oak Blvd.                                                1311 Balboa Avenue

Tallahassee Florida, 32399-2100                                   Panama City, Florida 32401

 

Re:  Second Appeal – School Board of Bay County, PA ID: 005-U5PCR-00, FEMA-4399-DR-FL, Grants Manager Project (GMP) 113459/ Project Worksheet (PW) 2156  

       Allowable Costs and Reasonable Costs, Financial Accounting and Reconciliation

 

Dear Kevin Guthrie and Lee Walters:

This is in response to the Florida Division of Emergency Management’s (Recipient) letter dated March 13, 2023, which transmitted the referenced second appeal on behalf of the School Board of Bay County (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of funding in the amount of $121,338.19 for completed repairs to the Lynn Haven Elementary School Gymnasium (Facility).  

As explained in the enclosed analysis, I have determined that the Applicant has demonstrated that the costs claimed are directly tied to the performance of completed eligible work. Accordingly, this appeal is granted in the amount of $121,338.19 in eligible Public Assistance funding. By copy of this letter, I am requesting the Regional Administrator to take appropriate action to implement this determination. 

This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals

 

                                                                                 Sincerely, 

                                                                                    /S/

                                                                                 Robert Grimley

                                                                                 Acting Deputy Division Director for Operations

                                                                                 Public Assistance Division

 

Enclosure

cc:  Robert D. Samaan                                    

Acting Regional Administrator                

FEMA Region 4   

Appeal Analysis

Background

From October 7-19, 2018, Hurricane Michael’s strong winds, torrential rain and tidal surge caused extensive damage throughout Florida.[1]The School Board of Bay County (Applicant) requested Public Assistance (PA) funding for contracted work to permanently repair damage to its Lynn Haven Elementary School Gymnasium (Facility), including the roof, wall panels, insulation, lighting, drywall, windows, overhead doors, electrical system and Heating, Ventilation, and Air Conditioning (HVAC) control. FEMA prepared Grants Manager Project (GMP) 113459 to document the damage and approved scope of work (SOW). The Applicant provided work order cost detail reports, building inspection reports with photographs dated February 19 and August 21, 2019, and cost estimates prepared using RS Means software to assert that the Facility was eligible for total replacement, totaling $1,487,101.85. On June 15, 2021, FEMA obligated the project, approving $923,685.00 to replace the Facility.

During review of the Applicant’s cost estimate, FEMA identified damage and cost discrepancies. On December 8, 2020, FEMA issued a request for information (RFI), requesting confirmation of Facility dimensions and adjustment to the various inconsistencies found in the repair and replacement cost estimates, including soft costs. In its response, the Applicant provided an updated cost estimate spreadsheet that revised its replacement costs to $992,894.74. On 

March 18, 2021, FEMA issued a Determination Memorandum (DM) approving $723,867.91 for Facility replacement costs.[2] FEMA denied $269,026.83 and noted that the percentage factors in the Applicant’s estimates for site access, storage, and staging were unnecessary given the Facility’s location, and further stated that other soft cost factors appeared excessive and lacked justification. 

First Appeal 

On May 18, 2021, the Applicant filed its appeal through the Florida Division of Emergency Management (Recipient), seeking the previously denied costs, to total the full amount of the previously requested replacement costs. The Applicant contended that: (1) it was not required to provide supporting invoices for completed work until project closeout; (2) FEMA policy allowed for funding completed work using estimated costs; and (3) the factors used to calculate soft costs in its estimates were reasonable and compliant with FEMA policy. On July 16, 2021, the Recipient transmitted the Applicant’s appeal to FEMA with a letter recommending approval.

On January 6, 2022, FEMA issued an RFI, stating the DM did not adequately communicate all applicable eligibility issues and noting issues with the Applicant’s cost documentation for contracted and completed work. The Applicant responded, providing approved time extensions, construction contracts, bids and bid tabulations for categories of work, and selected contractor payment applications. Payment Application Number 18 (dated February 8, 2022) shows that the Applicant had contracted for Facility repair, not replacement, for a total scheduled repair value of $397,943.31, with $274,873.04, or about 70 percent of the total, completed by January 31, 2022. Accordingly, the Applicant also reduced its total claimed amount to $397,943.31 to align with the provided payment applications. Based on the Applicant’s response, FEMA inquired whether the Applicant was repairing rather than replacing the Facility. On March 8, 2022, the Applicant confirmed that it was repairing the Facility, not replacing it. On September 9, 2022, FEMA prepared an updated cost estimate (CEF). 

On November 10, 2022, the FEMA Region 4 Regional Administrator denied the appeal finding that the Applicant’s documentation did not demonstrate all the costs requested were tied to work required as a direct result of the disaster. FEMA compared the invoiced costs with the approved SOW and the updated CEF. FEMA also summarized the line-item costs in FEMA’s cost validation in the CEF in accordance with the Applicant’s breakdown of actual costs and found a cost underrun. In total, FEMA found $276,605.12 to be eligible. FEMA determined that federal law did not bar it from deobligating the remaining $647,079.00 previously awarded funds because the Applicant did not draw down all the funds, the Applicant did not complete the approved SOW, and the claimed costs were not reasonable for the work performed.[3] 

Second Appeal

The Applicant submits a second appeal, dated January 13, 2023, seeking an additional $121,338.19 for the remaining costs to repair the Facility.[4] The Applicant provides additional documentation to account for work performed after January 31, 2022, via Pay Application Number 22, outlining work performed until September 30, 2022.  It also shows that items of incomplete work previously included on Pay Application Number 18 were completed. The Applicant contends that Pay Application Number 22, together with the previously provided documentation (including its engineer’s and architect’s assessments and FEMA approved SOW, construction contract, and pay applications) all support the eligibility of the actual costs of the completed work. The Recipient transmitted the Applicant’s second appeal to FEMA with a letter recommending approval.

 

Discussion

FEMA provides PA funding to eligible applicants for the repair, restoration, reconstruction, or replacement of facilities damaged or destroyed by disasters.[5] Final costs for large projects are based on the actual documented cost of the completed, eligible work.[6] To be eligible, costs must be directly tied to the performance of eligible work and be adequately documented.[7] The burden to fully substantiate appeals with documented justification falls exclusively to the applicant and hinges upon the applicant’s ability to produce not only its own records but to clearly explain how those records are relevant to the appeal.[8]

FEMA, in its first appeal decision, approved costs for the Applicant’s completed repair work directly tied to eligible work, but did not approve funding for the costs associated with the uncompleted repair work. On second appeal, the Applicant submitted additional cost documentation that is tied to the completed repair work. Specifically, Pay Application Number 22 shows all repair work was completed within the allowed timeframe and directly tied to the performance of eligible work. This documentation provides a quantitative description of the repairs performed and the costs attributable to those completed eligible repairs. As such, the Applicant has shown that all eligible work has been completed and adequately documented, and therefore, the actual costs for completed work in the amount of $121,338.19 are eligible for PA funding.

 

Conclusion

The Applicant demonstrated that the costs claimed are directly tied to the performance of completed eligible work. Accordingly, this appeal is granted in the amount of $121,338.19 and the Regional Administrator is requested to take appropriate action to implement this determination.


 

[1] The President declared major disaster, (DR-4399- FL), on October 11, 2018.

[2] The Applicant received the Determination Memorandum on March 30, 2021.

[3] See Robert T. Stafford Disaster Relief and Emergency Assistance (Stafford) Act § 705(c), Title 42, United States Code (U.S.C.) § 5205(c) (2018) (prohibiting FEMA from deobligating any payment to a state or local government if: 1) the payment was authorized by an approved agreement specifying the costs; 2) the costs were reasonable; and 3) the purpose of the grant was accomplished).

[4] This amount is the difference between the total actual costs requested, $397,943.31, minus the $276,605.12 found eligible in the first appeal.

[5] Stafford Act § 406(a)(1)(A), 42 U.S.C. § 5172(a)(1)(A).

[6] Title 44 of the Code of Federal Regulations (44 C.F.R.) §206.205(b) (2018); Public Assistance Program and Policy Guide, FP 104-009-2, at 144 (Apr. 1, 2018) [hereinafter PAPPG]. See also FEMA Second Appeal Analysis, Sch. Bd. of Bay Cnty., FEMA-4399-DR-FL, at 2 (Dec.12, 2022).

[7] Title 2 of the Code of Federal Regulations (2 C.F.R.) § 200.403(a), (g) (2018); PAPPG, at 21-22. See also Sch. Bd. of Bay Cnty., FEMA-4399-DR-FL, at 2.

[8] 44 C.F.R. § 206.206(a); PAPPG, at 133; FEMA Second Appeal Analysis, Campbell Cty. Fire Dist. #1, FEMA-4497-DR-KY, at 3 (Dec. 19, 2022).

Last updated