Allowable Costs and Reasonable Costs
Appeal Brief
Disaster | 4658 |
Applicant | Minnesota Valley Cooperative Light and Power Association |
Appeal Type | Second |
PA ID# | 000-U9D3-00 |
PW ID# | GMP 688227 |
Date Signed | 2025-01-06T12:00:00 |
Summary Paragraph
From May 8 through May 13, 2022, severe storms, wind, tornadoes and flooding impacted Minnesota and a major disaster was declared on July 8, 2022. The Applicant, a Private Nonprofit electric cooperative, requested Public Assistance (PA) for repairs to wooden transmission and distribution poles. On April 24, 2023, FEMA issued a Determination Memorandum denying the request, finding that the Applicant had not demonstrated the predisaster condition of the poles or that the damages were directly caused by the declared incident. The Applicant appealed FEMA’s determination on June 21, 2023, and the Minnesota Department of Public Safety (Recipient) forwarded the appeal to FEMA, with its support. FEMA issued a Request for Information on December 20, 2023, requesting, among other information, predisaster maintenance and a detailed scope of work (SOW). The Applicant submitted the requested predisaster records and proposed SOW to straighten 1,168 utility poles. It additionally submitted an estimate from its primary contractor for $539,532.05 to complete the SOW. On appeal, the FEMA Region 5 Regional Administrator found that the work to straighten 1,168 utility poles was required as a result of the disaster, but that the Applicant did not demonstrate that its cost estimate was reasonable, and FEMA partially approved the appeal for $268,172.80, the total costs it deemed to be reasonable. The Applicant submits a second appeal, which includes its request for bids (submitted after the first appeal decision), and documentation showing the 4 responsive bids as well as the lowest responsive bid of $418,058.00 for work associated with straightening 1,168 utility poles. The Recipient forwards the appeal with its support.
Authorities
- 2 C.F.R. §§ 200.403, 200.404.
- PAPPG, at 65-66.
Headnotes
- FEMA generally considers contract costs reasonable when the Applicant adheres to full and open competition under applicable Federal procurement requirements, and the scope of services or work in the contract and level of effort is consistent with respect to the eligible SOW. As part of this evaluation FEMA considers whether the Applicant provided a cost or price analysis as well as whether the Applicant selected the lowest responsible bidder based on the selection criteria.
- Here, the Applicant adhered to full and open competition under applicable Federal procurement requirements, the scope of services are consistent with the eligible SOW, and the Applicant has selected the lowest responsible bidder. Therefore, the additional requested costs are reasonable.
Conclusion
FEMA finds that the Applicant has demonstrated that the additional costs of $149,885.20 are reasonable. Therefore, this appeal is granted.
Appeal Letter
SENT VIA EMAIL
Kristi Rollwagen Patrick Carruth
Director General Manager
Homeland Security and Emergency Management Minnesota Valley COOP
Division of Minnesota Department of Public Safety Power and Light Assn.
445 Minnesota Street, Suite 223 PO Box 248
St. Paul, MN 55105 Montevideo, MN 56265
Re: Second Appeal – Minnesota Valley Cooperative Light and Power Association, PA ID: 000-U9D3-00, FEMA-4658-DR-MN, Grants Manager Project (GMP) 688227, Allowable Costs and Reasonable Costs
Dear Kristi Rollwagen and Patrick Carruth:
This is in response to the Minnesota Department of Public Safety’s (Recipient) letter dated October 7, 2024, which transmitted the referenced second appeal on behalf of Minnesota Valley COOP Light and Power Association (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) prior finding that $268,172.80 constitutes the reasonable costs for work to repair 1,168 utility poles. The Applicant is requesting that FEMA approve additional costs of $149,885.20, which would bring this project’s eligible costs to $418,058.00.
As explained in the enclosed analysis, I have determined the Applicant has demonstrated its additional requested costs are reasonable. Therefore, this appeal is granted. By copy of this letter, I am requesting the Regional Administrator to take appropriate action to implement this determination.
This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.
Sincerely,
/S/
Robert M. Pesapane
Director, Public Assistance
Enclosure
cc: Thomas Sivak
Regional Administrator
FEMA Region 5
Appeal Analysis
Background
From May 8 to 13, 2022, severe storms, straight-line winds, tornadoes and flooding impacted Minnesota, resulting in a major disaster declaration on July 8, 2022. Minnesota Valley Cooperative Light and Power Association (MVCLPA) (Applicant), a private nonprofit entity, requested Public Assistance (PA) funding for repairs to wooden transmission and distribution poles that the disaster caused to lean. The Applicant claimed damage to over 1,000 total poles. FEMA developed Grants Manager Project 688227 to document the Applicant’s costs. The scope of work (SOW) prepared by FEMA stated “The [A]pplicant will utilize contract for repairs to the [MVCLPA] to restore this facility to its predisaster design, function, and capacity (in-kind) within the existing footprint.”[1] On January 30, 2023, FEMA issued a Request for Information (RFI) to the Applicant, requesting predisaster maintenance records and work orders, as well as standard operating procedures (SOP) which explained the need to straighten the poles. The Applicant responded on February 6, 2023, with a letter from its consulting engineer, certifying the predisaster maintenance and status of the poles, and that it did not have a SOP regarding leaning poles. On April 24, 2023, FEMA issued a Determination Memorandum denying $169,312.00, finding that the Applicant had not demonstrated the predisaster condition of the poles, or that the damage was caused by the declared incident. FEMA also found that the Applicant did not provide any documentation demonstrating the work was performed inside the disaster declared areas.
First Appeal
On June 21, 2023, the Applicant appealed. The Applicant provided a map of the pole locations and a map from the National Weather Service showing high wind in the same areas during the disaster. The Applicant argued that its own engineer determined the poles to be in good working order before the disaster, and included predisaster service orders for the poles. The Minnesota Department of Public Safety (Recipient) forwarded the appeal, with its support, on August 17, 2023.
FEMA issued an RFI on December 20, 2023, requesting a SOW and cost estimate for the work, predisaster maintenance and inspection documents, documentation regarding the extent of lean, and the status of the work. The Applicant responded on January 22, 2024, stating that no work had begun, and that FEMA’s previous estimate of $169,312.00 was inaccurate. FEMA followed up to again request a SOW, method of repair information, and a cost estimate. The Applicant responded on May 6, 2024, stating that 1,168 poles needed straightening, and provided the GPS location of each pole. The Applicant provided cost information for this project as well as a similar project under a different disaster, such as a price analysis estimate prepared by its primary contractor and a document explaining the manpower and factors that were considered in developing the estimate. However, the Applicant noted that it would request proposals for the work (i.e., advertise a request for proposals (RFP)). The Applicant claimed that it expected the proposals would quote a total project cost of $539,532.05.
On June 18, 2024, the FEMA Region 5 Regional Administrator partially granted the appeal. Although FEMA found that the work to straighten 1,168 poles was required as a result of the declared incident, it determined that the cost estimate proposed by the Applicant was unreasonable. FEMA conducted a reasonable cost analysis based on historical data from 2019 and validated $268,172.80 as a reasonable cost estimate.
Second Appeal
On August 16, 2024, the Applicant submitted a second appeal seeking an additional $149,885.20 in PA funding to complete the repair work approved by FEMA in the first appeal decision. The additional requested funding is based on a bid amount to repair 1,1168 poles for a total cost of $418,058.00. The Applicant provides documentation demonstrating that it published an RFP after FEMA issued its first appeal decision.[2] The RFP listed technical specifications for the work, and that the poles would be straightened as near as practical to in-place. The RFP also specified that the vendors must comply with all relevant Federal contract provisions. The Applicant sent the RFP to 11 electrical utility repair and construction contractors and received four responsive bids. The Applicant includes an evaluation sheet with its appeal, which shows the per unit and total prices from each of the four contractors that bid. The documentation shows that Michels Power, Inc. (Michels) submitted the lowest cost bid. Michels estimated $400,538.00 to straighten 1,168 poles, with an additional $17,520.00 in material costs for gravel to stabilize the poles, for a total low bid amount of $418,058.00.
Discussion
To be eligible, costs must be directly tied to the performance of eligible work and necessary and reasonable to accomplish the work properly and efficiently.[3] A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person under the circumstances prevailing at the time the Applicant makes the decision to incur the cost.[4] FEMA generally considers contract costs reasonable when the Applicant adheres to full and open competition under applicable Federal procurement requirements, and the scope of services or work in the contract and level of effort is consistent with respect to the eligible SOW.[5] FEMA evaluates reasonableness when price competition is lacking or when the selection was noncompliant with the applicable procurement under grant requirements even though there may have been price competition.[6] As part of this evaluation FEMA considers whether the Applicant provided a cost or price analysis as well as whether the applicant selected the lowest responsible bidder based on the selection criteria.[7]
On second appeal, the Applicant provides documentation to show the results of its competitive bid process for the eligible SOW. The Applicant prepared an RFP, using the assistance of a consulting engineer, and solicited bids from 11 vendors. The Applicant analyzed the competing bids it received, in comparison to the cost estimate, and demonstrated prudence by selecting the lowest bidder that offered to complete the project in accordance with the RFP’s requirements in a timely manner. A review of the RFP requirements and bid results show that the scope of services in the contract and level of effort is consistent with the eligible SOW of straightening 1,168 poles. While FEMA notes that installing gravel to stabilize the poles was not previously approved, this work is eligible because it is necessary to accomplish the work of straightening the poles properly and efficiently. Because the Applicant adhered to full and open competition, consistent with applicable Federal procurement requirements, and the scope of services are consistent with the eligible SOW, FEMA finds the low bid contract costs, totaling $418,058.00 to be reasonable.
Conclusion
The Applicant has demonstrated that additional costs of $149,885.20 are reasonable. Therefore, this appeal is granted.[8]
[1] Grants Manager Project Report GMP 688227, at 100.
[2] Although the Applicant submitted an RFP that included the work for this project and another similar project from a different disaster (totaling a combined 1,721 poles), the bids delineate the price per pole straightening, which allows FEMA to determine the bid amounts associated with just the 1,168 poles associated with this project.
[3] Title 2 of the Code of Federal Regulations (C.F.R.) § 200.403(a) (2022); Public Assistance Program and Policy Guide, FP 104-009-2, at 65 (June 1, 2020) [hereinafter PAPPG].
[4] 2 C.F.R. § 200.404.
[5] PAPPG, at 66.
[6] Id.
[7] Id.
[8] The total low bid amount of $418,058.00 minus the $268,172.80 previously approved by FEMA equals the $149,885.20 of additional costs approved on second appeal.