This page has not been translated into Français. Visit the Français page for resources in that language.
Time Extension
Appeal Brief
Disaster | 1609-DR-FL |
Applicant | City of Southbay |
Appeal Type | Second |
PA ID# | 099-67175 |
PW ID# | PW 5403 |
Date Signed | 2015-06-15T00:00:00 |
Conclusion: The City of Southbay’s (Applicant) first appeal was submitted more than 60 days after the final determination regarding costs of PW 5403. In addition, the Grantee submitted the Applicant’s second appeal after the 60 day regulatory timeframe. As such, the Applicant’s first and second appeals fail to meet the procedural requirements of 44 C.F.R. § 206.206(c). Timeliness aside, the Applicant did not provide adequate documentation to justify an additional $16,300.75 in PA funding.
Summary Paragraph
Hurricane Wilma created significant vegetative debris throughout the City of Southbay. FEMA prepared PW 5403 to reflect debris removal costs. During closeout, FEMA determined that the Applicant’s documentation did not reflect the costs claimed for all of the debris removal work. FEMA de-obligated $5,088.02 due to truck certification discrepancies. In an undated first appeal, the Applicant asserted that it never submitted 24 load tickets related to the debris removal project encompassed in PW 5403 because they were missing at the time of close out. In addition, the State of Florida (Grantee) asserted that the reimbursement for the uncaptured load tickets was originally undertaken through the interim inspection process, however, the process stalled at a certain point. The FEMA Region IV Regional Administrator (RA) determined that the Applicant’s request to include additional costs for the missing load tickets was untimely as it was submitted two and a half years after the closeout version was issued. In the second appeal, the Applicant asserts personnel changes, untrained staff, and internal and external deadlines following Hurricane Wilma led to its failure to submit documentation for unclaimed costs. Due to these unforeseen consequences, the Applicant requests FEMA re-obligate $5,088.02 in PA funding and amend the closeout version of PW 5403 to include $11,212.73 for the 24 load tickets.
Authorities and Second Appeals
- Stafford Act Sections 403 and 407.
- Stafford Act Section 423.
- 44 C.F.R. § 206.206.
- 44 C.F.R. § 206.224.
- OMB Circular A-87, 2 C.F.R. § 225.
Headnotes
- Pursuant to the Stafford Act § 423 and 44 C.F.R. § 206.206(c)(1), the Applicant must submit an appeal of a FEMA determination within 60 days of receipt of such determination.
- FEMA received an undated first appeal for PW 5403 two and a half years after the regulatory timeframe, thus, making the first appeal untimely.
- Pursuant to 44 C.F.R. § 206.206(c)(2), the Grantee must submit appeals from an Applicant, with a written recommendation, to the RA within 60 days of receipt.
- The Grantee submitted the Applicant’s second appeal a year after the regulatory timeframe, thus, making the second appeal untimely.
- OMB Circular A-87 requires procurement costs to be adequately documented.
The Applicant failed to provide adequate documentation demonstrating proper truck certification.
Appeal Letter
06/15/2015
Bryan W. Koon
Director
State of Florida Division of Emergency Management
2555 Shumard Oaks Boulevard
Tallahassee, Florida 32399-2100
Re: Second Appeal – City of Southbay, PA ID 099-67175, FEMA-1609-DR-FL, Project Worksheet (PW) 5403 – Time Extension – Appeal
Dear Mr. Koon:
This is in response to a letter from your office dated August 22, 2014, which transmitted the referenced second appeal on behalf of the City of Southbay (Applicant). The Applicant is appealing the U.S. Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of $16,300.75 in Public Assistance (PA) funding for debris removal work performed following Hurricane Wilma.
As explained in the enclosed analysis, the appeal was not submitted within the regulatory timelines established in 44 C.F.R. § 206.206. Additionally, I have determined that the Applicant has not provided adequate documentation to justify the obligation of $16,300.75 in PA funding. Therefore, I am denying the appeal.
Please inform the Applicant of my decision. This determination is the final decision on this matter pursuant to 44 C.F.R. § 206.206, Appeals.
Sincerely,
/s/
William W. Roche
Director
Public Assistance Division
Enclosure
cc: Garcia Szczech
Regional Administrator
FEMA Region IV
Appeal Analysis
Background
In October 2005, Hurricane Wilma caused heavy rains and powerful winds that generated mixed storm debris throughout the City of Southbay (Applicant). The Applicant utilized a debris removal contract with Phillips and Jordan, Inc. (Contractor) to remove and dispose of storm debris located on its public rights-of-way. The Contractor disposed of 12,576.9 cubic yards (CY) of debris following Hurricane Wilma. FEMA prepared Project Worksheet (PW) 5403 to address the debris-related work. During closeout, FEMA determined that the Applicant’s documentation did not reflect the costs claimed for all of the debris removal work, and de-obligated $5,088.02 due to truck certification discrepancies. On September 2, 2010, PW 5403 was obligated for $145,834.78. The Grantee was notified of FEMA’s final determination in a letter dated September 8, 2010.
First Appeal
In an undated, unaddressed document proffered as an appeal,[1] the Applicant asserted that “24 load tickets were missing and they never have been submitted for reimbursement to your office.” The Applicant further argued, without substantiating documentation, that the missing load tickets were issued by the “same vendor that was contracted to remove debris in the city.”
The Grantee noted that $5,088.02 was deobligated from PW 5304 in its January 4, 2013 letter forwarding the Applicant’s appeal. In addition, the Grantee asserted that the Applicant’s 24 load tickets represented eligible work, totaling $11,212.73, that was not captured in PW 5403. The Grantee contended that the load ticket costs should be added to the closeout version of PW 5403, but did not specify whether the Applicant was appealing FEMA’s determination to de-obligate $5,088.02 from PW 5403. Finally, the Grantee stated, with no further explanation, that the Applicant’s first appeal was received in a timely manner.
In the first appeal response dated May 24, 2013, the FEMA Region IV Regional Administrator (RA) found that the closeout version of PW 5403[2] constituted FEMA’s final determination of costs for the project. As such, the Applicant’s request to include additional costs for the missing load tickets was untimely as it was submitted to FEMA 28 months after the closeout version was issued. In addition, the RA determined that the de-obligation of $5,088.02 for documentation discrepancies was not germane to the issue presented in the first appeal. Accordingly, the appeal was denied.
Second Appeal
The Applicant asserts in its second appeal dated July 10, 2013, that personnel changes following Hurricane Wilma led to delays in submitting documentation to FEMA regarding PW 5403, indicating that its staff’s inadequate training and understanding of the process resulted in the documentation not being provided properly. The Applicant states that internal and external deadlines also led to a rushed process for submitting documentation to FEMA. Finally, the Applicant states it is not seeking reimbursement of $5,088.00 deobligated during the closeout of PW 5403.
In a letter dated August 22, 2014, the Grantee argues that, while FEMA determined that $5,088.02 in PA funding was ineligible due to documentation discrepancies, it failed to indicate which truck certifications were in question. The Grantee asserts that the Applicant checked internal records and found no discrepancies. The Grantee concludes that the Applicant cannot properly respond to FEMA’s determination without additional details regarding the deduction in funding. Additionally, the Grantee requests FEMA draft a new version of PW 5403 to include costs associated with the 24 load tickets.
Discussion
Appeal Timeliness
Pursuant to the Stafford Act § 423 and 44 C.F.R. § 206.206(c)(1), an eligible Applicant may appeal any determination previously made related to an application for PA funding within 60 days of receiving notice of the action that is being appealed. In addition, pursuant to 44 C.F.R. § 206.206(c)(2), the Grantee must submit appeals from an Applicant, with a written recommendation, to the Regional Administrator within 60 days of receipt.[3] Neither the Stafford Act nor its implementing regulations provide FEMA authority to grant time extensions for filing first or second appeals.[4]
The closeout version of PW 5403 was obligated on September 2, 2010. While the Applicant’s first appeal is undated, the Grantee’s letter transmitting the appeal to FEMA is dated January 4, 2013. While the Grantee asserted that the Applicant’s first appeal was received in a timely manner, it did not explain why it failed to forward the first appeal to FEMA within the regulatory timelines. In the first appeal determination, the RA noted that the first appeal was submitted more than two years after the final determination of costs for PW 5403; therefore, the appeal was denied based on timeliness. Although the Applicant’s second appeal provides an explanation regarding the delay of its first appeal, FEMA does not have the authority to waive or extend the 60 day statutory and regulatory timeframes. Accordingly, the RA’s first appeal determination regarding timeliness was appropriate.
Regarding the second appeal, the Applicant submitted it within 60 days of receipt of FEMA’s first appeal determination. However, the Grantee’s letter dated August 22, 2014, seeking clarification of the deobligation, was submitted to FEMA after the regulatory timeframe lapsed. As such, the Applicant’s second appeal failed to meet the procedural requirements of 44 C.F.R. § 206.206(c)(2) and consequently is denied. Timeliness aside, as described below, the second appeal also is not meritorious on the substantive issues and would otherwise be denied.
Allowable Costs
Pursuant to the Stafford Act §§ 403 and 407, FEMA Public Assistance (PA) funding may be available to a state or local government for debris removal if the work is essential to saving lives and protecting property or in the public interest.[5] Costs associated with debris removal work are eligible for PA funding if the costs are reasonable and necessary to accomplish the work and in compliance with federal and state procurement requirements.[6] Pursuant to 44 C.F.R. § 13.22, only allowable costs are eligible for Public Assistance funding. In addition, all allowable procurement costs must be adequately documented.[7]
In PW 5403, FEMA determined that the debris removal work was eligible and the contract used to complete the work followed proper procurement standards. FEMA also determined that the majority of costs claimed in PW 5403 were eligible under the PA Program. However, during closeout, FEMA found discrepancies with three truck certification forms which caused FEMA to deobligate $5,088.02 in PA funding. Neither in their first appeal, nor in their second has the Applicant provided adequate documentation regarding the truck certification discrepancies.[8] Rather, they have only asserted that their process for obtaining reimbursement was stalled due to, among other things, personnel changes. A truck certification list, including size of hauling bed in cubic yards, license plate number, truck identification number assigned by the owner, and a short physical description of each truck constitutes adequate documentation.[9] Additionally, regarding the additional 24 load tickets, such items do not, in and of themselves demonstrate the work performed was compliant with 2 C.F.R. § 225, FEMA 325, and other FEMA policy and guidance.[10] The Applicant has failed to substantiate that the work associated with the 24 load
tickets, totaling $11,212.73, is eligible. In addition, it has not explained why the $5,088.22 should be re-obligated. As such, FEMA cannot reimburse these costs.
Conclusion
The Applicant’s first appeal was submitted more than 60 days after the final determination regarding costs of PW 5403. In addition, regarding the second appeal, the Grantee submitted their request for clarification of the deobligation after the 60 day regulatory timeframe. As such, the Applicant’s first and second appeals failed to meet the procedural requirements of 44 C.F.R. § 206.206(c). Timeliness aside, the Applicant has not provided adequate documentation to justify re-obligating $5,088.02 in PA funding nor substantiated that funding for the 24 load tickets meets all eligibility requirements. The second appeal is denied.
[1] Pursuant to 44 C.F.R. § 206.206(a) , an appeal of a FEMA determination must contain documented justification supporting the appellant's position, specifying the monetary figure in dispute, and citing the provisions in Federal law, regulation, or policy with which the appellant believes the initial action was inconsistent. The statement submitted by the Applicant lacks these three criteria.
[2] Project Worksheet 5403, City of Southbay, Version 6 (Sep. 2, 2010).
[3] 44 C.F.R. § 206.206(c)(2).
[4] But see Public Assistance Guide, FEMA 322 at 86 (Oct. 1999) [hereinafter PA Guide] (stating, “[t]he State will then prepare a written recommendation on the merits of the appeal and forward that recommendation to FEMA within 60 days of its receipt of the appeal letter or receipt of additional information that it had requested.” (Emphasis added). However, it is important to note that this language is not found in the Stafford Act or 44 C.F.R., and it only applies to first level appeals.)
[5] The Robert T. Stafford Disaster Relief and Emergency Assistance Act of 1988, Pub. L. No. 93-288, §§ 403 and 407, 42 U.S.C. §§ 5170b and 5192 (2003); see also 44 C.F.R. § 206.224(a).
[6] See OFFICE OF MGMT. & BUDGET, EXEC. OFFICE OF THE PRESIDENT, OMB CIRCULAR A-87, COST PRINCIPLES FOR STATE, LOCAL, AND INDIAN TRIBAL GOVERNMENTS (2004) (codified at 2 C.F.R. § 225), Basic Guidelines, at 8; see also 44 C.F.R. § 13.36.
[7] See OMB Circular A-87, 2 C.F.R. § 225.
[8] Grantee Second Appeal Letter, City of Southbay, FEMA-1609-DR-FL, at 1 (Aug. 22, 2014) (stating the Applicant is unable to respond to FEMA’s determination regarding truck certification discrepancies because FEMA did not specify which certifications were questioned, and the Applicant found no discrepancies in its records). However, pursuant to 44 C.F.R. § 206.206(c), the Applicant’s request for clarification should have occurred within 60 days of the final determination.
[9] Public Assistance Debris Management Guide, FEMA 325, at 109 (April 1999) [hereinafter FEMA 325].
[10] See OMB Circular A-87, 2 C.F.R. § 225; see also FEMA 325 (stating that applicants must maintain and update notarized lists of trucks involved in debris removal operations); see also FEMA Second Appeal Analysis, City of West Miami, FEMA-1602-DR-FL, at 1 (Feb. 18, 2014) (finding that FEMA requires Applicant to substantiate truck certifications through notarized lists).