Hurricane Fran Debris Removal Contract
Appeal Brief
Disaster | FEMA-1134-DR |
Applicant | Onslow County |
Appeal Type | Second |
PA ID# | 133-00000 |
PW ID# | 76599 |
Date Signed | 1999-10-29T04:00:00 |
Cross Reference: Debris Removal
Summary: Hurricane Fran struck Onslow County on September 5, 1996. Wind and storm surge generated large amounts of sand, vegetative and construction and demolition debris. Onslow County and Grubbs Construction entered into a $4.75 million lump sum contract. Under the contract, Grubbs was responsible for the removal, burning or chipping, and disposal of vegetative debris; demolition of condemned structures, processing and burning or disposal of demolition debris; and the removal, screening, and replacement of sand displaced by disaster 1134-NC. Subsequently, the State of North Carolina Department of Environment, Health, and Natural Resources placed a ban on all burning activities. Because of this change in disposal method, Onslow County entered into a second contract with Grubbs for a total of $14,647,250. FEMA approved DSR 28834 on March 8, 1997 for $6,389,686 based on multiple supplemental requests. This increased the total approved eligible funding to $10,666,994. In June of 1997, FEMA tasked Price Waterhouse (PW) to perform a financial review of the debris removal activities performed by Grubbs Construction. PW concluded that Onslow County and Grubbs Construction could document only $7,802,913. Based on this finding, FEMA wrote DSR 76599 to de-obligate $3,429,102. Onslow County waived its first appeal and submitted a second appeal on December 22, 1998. In the appeal, the County requests that Grubbs estimates for the quantities of both vegetative and C&D debris be used for calculating the eligible funding. It is requesting an additional $7,508,764.
Issues:
- Is the requested volume of C&D debris eligible?
- Is the requested volume of vegetative debris eligible?
- No. The requested volume cannot be supported. However, a revised estimate can be supported as detailed in the analysis.
- Yes. The requested volume of vegetative debris is accepted as detailed in the analysis.
Appeal Letter
Mr. Steven N. Glenn
Deputy Operations Chief
Division of Emergency Management
Disaster Recovery Operations Center
205 West Cabarrus Street
Raleigh, North Carolina, 27601
RE: Second Appeal - Onslow County, Hurricane Fran Debris Removal, FEMA-1134-DR-NC, DSR 76599
Dear Mr. Glenn:
This letter is in response to the referenced second appeal transmitted by your letter dated March 12, 1999. The subgrantee is requesting an additional $7,508,764 for debris removal costs associated with Hurricane Fran.
As explained in the enclosed analysis, the total eligible cost for debris removal activities is $11,218,028. This represents an increase of $3,415,115 over the currently approved amount. Therefore, the appeal has been partially approved. By copy of this letter, I am requesting the Regional Director to prepare a DSR for the amount of $3,415,115.
Please inform the applicant of my determination. In accordance with the appeal procedure governing appeal decisions made on or after May 8, 1998, my decision constitutes the final decision on this matter. The current appeal procedure was published as a final rule in the Federal Register on April 8, 1998. It amends 44 CFR 206.206.
Sincerely,
/S/
Lacy E. Suiter
Executive Associate Director
Response and Recovery Directorate
Enclosure
cc: John B. Copenhaver
Regional Director
FEMA Region IV
Appeal Analysis
BACKGROUNDHurricane Fran struck Onslow County on September 5, 1996. Wind and storm surge battered the County generating large amounts of sand, vegetative and structural debris. As a result, Onslow County hired Grubbs Construction to perform emergency debris clearance and prepare staging sites for the public to deposit debris. On September 11, 1996, Onslow County issued a Request For Proposal (RFP) for the debris removal operations throughout the County. Because of the wide range of bids received, the County issued a second RFP on September 17, 1996. Onslow County and Grubbs Construction entered into a $4.75 million lump sum contract on September 23, 1996. Under the contract, Grubbs was responsible for the removal, burning or chipping, and disposal of vegetative debris; demolishing condemned structures, processing and burning or disposal of debris generated from the demolition; and the removal, screening, and replacement of sand displaced by the storm.
Work progressed through the end of October, at which time, the State of North Carolina Department of Environment, Health, and Natural Resources placed a ban on all burning activities. This presented problems for the disposal of structural (Construction & Demolition) (C&D) debris. The County would now have to dispose of the C&D debris in a permitted subtitle D Landfill. The closest subtitle D Landfill was located approximately 100 miles away in Sampson County. Because of this change in disposal method, Onslow County entered into a second contract with Grubbs for an aggregate total of $14,647,250. The contract was lump sum and included the original $4.75 million with several adjustments for tasks that no longer had to be completed.
On October 29, 1996, FEMA wrote DSRs 32118 and 95846 for the loading and hauling of C&D debris that had accumulated at the NC 24 and NC 210 staging sites. The NC 24 staging site was for private citizens to dispose of various C&D debris while the NC 210 staging site was mainly for C&D debris generated from the demolition efforts, although some private dumping occurred.
FEMA approved DSR 28834 for $6,389,686 on March 8, 1997. The $6,389,686 was derived by starting with $14,647,250. This was the Grubbs' contract amount and was supported by information packages submitted by Onslow County in support of several supplemental requests. From this amount, FEMA made deductions totaling $8,257,564 for three items: $4,277,306 for 26 previously approved DSRs; $318,445 for previously approved work in units of the Coastal Barrier Resource System (CBRS); and $3,661,813 as a twenty-five percent holdback of the contract amount. FEMA withheld the twenty five percent because the debris volume quantities had not yet been documented. The intent was to release a portion of the funds up front and reconcile the debris quantities during closeout procedures. This action brought the total approved funding to $10,666,994. FEMA had approved other DSRs in addition to those accounted for in DSR 28834 that brought the total approved funding to $11,232,015.
To determine the eligible contract cost, FEMA tasked Price Waterhouse (PW) in June of 1997 to perform a financial review of the debris removal activities performed by Grubbs Construction. The PW report concluded that Onslow County and Grubbs Construction could document only $7,802,913. To reduce the approved funding from the $11,232,015, FEMA approved DSR 76599 to de-obligate $3,429,102.
Onslow County waived its first appeal and submitted a second appeal on December 22, 1998. In the appeal, the County requested that Grubbs' estimates for the quantities of both vegetative and C&D debris be used for calculating the eligible funding. The Division of Emergency Management of the State of North Carolina's Department of Crime Control and Public Safety (State) forwarded Onslow County's appeal to FEMA on March 12, 1999.
On August 10, 1999, representatives of Onslow County, the State of North Carolina and FEMA met in Raleigh, North Carolina. The County did not present any new information at the meeting. However, the County and State clarified some of the existing data on file. One item that was clarified was the number of structures demolished after the hurricane.
DISCUSSION
Onslow County addresses multiple issues in its second appeal letter. The two most relevant issues are the quantities of C&D and vegetative debris to be used for funding calculations. For the purposes of this analysis, we will discuss C&D and vegetative debris separately and will summarize the remaining issues raised by Onslow County.
C&D Debris
Onslow County states, "Grubbs' estimates concerning the quantities of C&D debris disposed of should be used for reimbursement calculations." The County asserts that Grubbs' estimate of 485,831 cy of C&D debris should be used. The County is requesting that 485,831 cy be applied to the $18.35 which would yield a total cost of $8,914,998. To support this, the County explains that no documentation of quantities was required, as the contract with Grubbs was lump sum. The 485,831 cy figure was provided to Onslow County by Grubbs just prior to the second contract approval. Documentation to support this quantity has not been provided. Additionally, Onslow County describes apparent flaws in how PW calculated the quantity of debris in the draft November 1997 report that include:
- PW ignored any reduction and recycling efforts by Grubbs and its subcontractors.
- PW ignored the fact that because the Governor had lifted the weight restrictions, substantially more debris could be compacted into the trucks. Grubbs reported that it was able to take a four-to five-cubic yard pile and reduce it to a one and a half-cubic yard pile by compaction. The only way this would have been accounted for was to weigh the trucks as they entered the landfill.
- PW relied upon DSR estimates of debris that did not sufficiently account for mobile homes and furnishings within all structures.
Description | Cost per cubic yard |
Trucking | $6.40 |
Load & Separate | $1.50 |
Site management & Logistics | $0.95 |
Tipping Fee | $6.50 |
Overhead | $1.50 |
Profit | $1.50 |
TotalR"/TABLE>
Lump Sum Contract Onslow County raises multiple issues concerning the appropriateness of the lump sum contract. Onslow County believes that a lump sum contract was acceptable because it had used a lump sum contract in the final stages of Hurricane Bertha cleanup activities and that FEMA did not voice objections to the lump sum contract following Hurricane Fran. Therefore, they believed there was no requirement to keep detailed records related to the contract. Lump Sum contracts are acceptable if the quantities of work are known in sufficient detail to allow a detailed scope of work to be established. In the case of Hurricane Bertha, when the lump sum contract was initiated, the debris removal operations were far along in the process and the quantities were either known or could be physically measured as debris piles. Therefore, a detailed scope of work could be established. In the case of Hurricane Fran, at the time the contract was let, the quantities were not established. Total funding The Regional Director had determined that eligible funding for debris activities was $7,802,913. This appeal has determined that an additional $3,235,823 for C&D debris and $323,981 for CBRS activities are eligible. In addition, a reduction of $144,689 is necessary for vegetative debris. Together, these three changes result in a net increase of $3,415,115 over the currently approved amount. The total eligible amount for debris work is now $11,218,028. CONCLUSION Based on our review of the information submitted with the second appeal, we have determined that Onslow County is eligible for additional funding. Based on documented field measurements detailed above, the eligible volume of C&D debris is 346,000 cy. Based on PW's report and the second appeal information, the eligible volume of vegetative debris is 508,480 cy. Additionally, the debris removal work within CBRS areas is found to be eligible. The appeal is partially approved. The additional eligible amount as a result of this appeal is $3,415,115. The Regional Director will approve a DSR in this amount. Last updated
|