alert - warning

This page has not been translated into 简体中文. Visit the 简体中文 page for resources in that language.

Bank Erosion

Appeal Brief Appeal Letter

Appeal Brief

DisasterFEMA-1734-DR
ApplicantCity of Centralia
Appeal TypeSecond
PA ID#041-11160-00
PW ID#1062
Date Signed2010-03-29T04:00:00

Citation:         FEMA-1734-DR-WA, City of Centralia, China Creek Force Main Bank Erosion, Project Worksheet (PW) 1062

Cross-

Reference:      Emergency Protective Measures, Environmental Compliance

 

Summary:        FEMA obligated PW 1062 for $25,159 for the  restoration of support and cover to a 10-foot length of exposed sewer line along an eroded river bank.  The approved scope of work included the installation of a 14-foot-long sheet pile wall.  The Applicant’s consultant observed significant erosion along a 100-foot section of river bank and recommended stabilizing the entire length to eliminate the threat of additional erosion that could further threaten the sewer line.  The Applicant entered into a contract for the armoring of a 100-foot section of bank and the construction of a rock and log jam groin based on its consultant’s recommendation.  The Applicant submitted a first appeal stating that the emergency bank stabilization was complete and requested FEMA fund its actual costs incurred ($169,778).  The Applicant submitted a memorandum from its consultant, which states that the bank had eroded within less than 5 feet from the sewer pipe, creating a hazard of exposure and failure for the entire 100-foot length of river bank.  The consultant considered a sheet pile alternative recommended by FEMA, but determined it was not feasible due to the high risk of bank collapse.  The Regional Administrator denied the appeal, because the Applicant had not demonstrated an immediate threat of damage to the pipe.

 

The Applicant submitted a second appeal requesting FEMA reimburse its actual costs for the stabilization of the creek bank.  The Applicant states that the work was necessary to eliminate the immediate threat of additional damage to the sewer line and reiterates that FEMA’s recommended method of repair was not feasible.  While the Applicant’s consultant states that the bank eroded to within 5 feet of the pipeline, the Applicant has provided no documentation to support that statement.

 

  Issues:            1.  Was there an immediate threat of additional damage to the pipe?

                          2.  Was the project as completed reviewed for compliance with the National Environmental Policy Act?

 

Findings:        1.  No.  The Applicant provided no documentation to support the claim that there was an immediate threat to the pipe for the entire 100-foot length of bank.

                        2.  No.  The project was not reviewed for compliance.

 

Rational:        Title 44 of the Code of Federal Regulations §206.225; Response and Recovery Policy 9560.1, Environmental Policy Memoranda, Environmental Policy Memo #3

Appeal Letter

March 29, 2010

 

 

 

Gerard Urbas

Deputy State Coordinating Officer

State of Washington Military Department

Emergency Management Division

MS: TA-20, Building 20

Camp Murray, WA  98430-5122

 

Re:   Second Appeal–City of Centralia, PA ID 041-11160-00, Bank Erosion,

FEMA-1734-DR-WA, Project Worksheet (PW) 1062

 

Dear Mr. Urbas:

 

This letter is in response to your letter dated May 26, 2009, which transmitted the referenced second appeal on behalf of the City of Centralia (Applicant).  The Applicant is appealing the Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of its request for funding for the stabilization of an eroded creek bank adjacent to the China Creek force main.

During the declared December 2007 flood event, the Chehalis River flooded and a portion of its bank adjacent to the China Creek sewer main eroded, exposing a 10-foot length of the pipe.  Based on the recommendation of a geotechnical specialist, FEMA obligated PW 1062 on March 21, 2008, for $25,159 for the restoration of support and cover to the exposed length of pipe.  The approved scope of work included the installation of a 14-foot-long sheet pile wall.

The Applicant’s consultant observed significant erosion along a 100-foot-long section of the river bank and recommended stabilizing the entire length of eroded bank to eliminate the threat of additional erosion, which could further threaten the sewer line.  In April 2008, the Applicant entered into a contract for the armoring of a 100-foot section of bank and the construction of a rock and log jam groin based on its consultant’s recommendation.

On May 30, 2008, the Applicant submitted a first appeal stating that it had completed the emergency bank stabilization and requested FEMA fund the actual project cost of $169,778.  The Applicant submitted a memorandum dated May 5, 2008, from its consultant that states that the bank had eroded to within less than five feet from the sewer pipe, creating a hazard of exposure and pipe failure for the entire 100-foot length of riverbank.  The consultant had considered a sheet pile alternative as recommended by FEMA, but determined that it was not feasible due to the high risk of additional bank collapse.  The Regional Administrator denied the appeal because the Applicant had not demonstrated that there was an immediate threat of damage to the pipe.

The Applicant submitted its second appeal on March 28, 2009, requesting FEMA reimburse its actual costs for the stabilization of the 100-foot section of creek bank.  The Applicant states that the work was necessary to eliminate the immediate threat of additional damage to the sewer line and reiterates that FEMA’s recommended method of repair was not feasible.  While the Applicant’s consultant states that the bank eroded to within five feet of the pipeline, the Applicant did not provide any documentation to support that statement.  The appeal references as-built drawings; however, the Applicant did not submit the drawings in support of the appeal.  Further, the Applicant completed the project without performing, or allowing FEMA to perform, an environmental review for compliance with the National Environmental Policy Act (NEPA).

Response and Recovery Policy 9560.1, Environmental Policy Memoranda, includes Environmental Policy Memo #3, which describes how FEMA treats projects that Applicants complete prior to performing an environmental review.  Actions completed without fulfilling the specific documentation and procedural requirements of NEPA may not be considered for funding.  There are exceptions to the policy for those projects that are eligible for funding as emergency work or for those repair projects that restore a facility substantially to its condition prior to the disaster.  As discussed above, the scope of work that the Applicant completed is not eligible as emergency work.  While the work required to restore cover to the exposed 10-foot length of pipe would have been eligible for funding as permanent work, the Applicant restored the cover to the exposed pipe in conjunction with the bank stabilization.  FEMA did not review the final scope of work for compliance with NEPA prior to the Applicant starting the work. Therefore, FEMA can provide no funding for the project.

I have reviewed the information submitted with the appeal and determined that the Regional Administrator’s decision in the first appeal is consistent with Public Assistance regulations and policy.  Therefore, I am denying the second appeal.

Please inform the Applicant of my decision.  This determination is the final decision on this matter pursuant to 44 CFR §206.206, Appeals.

Sincerely,

/s/

Elizabeth A. Zimmerman

Assistant Administrator

Disaster Assistance Directorate

cc:  Dennis A. Hunsinger, PhD

    Acting Regional Administrator

      FEMA Region X