·Record of Environmental Consideration REVISED FOR FEMA ENVIRONMENTAL --LOUISIANA See 44 Code of Federal Regulation Part 10 Project NamelNumber: Hardin Elementary School I PW 15202vsn4 Applicant Name: Recovery School District Project Location: 2401 St. Maurice Ave., New Orleans, LA 70117 Latitude: 29.97275, Longitude: -90.00341 Project Description: Hurricane Katrina caused catastrophic damage on August 29, 2005 to Hardin Elementary School. This project is one among a total of22 contributing (donor) facilities approved by FEMA for replacement. The Recovery School District chooses to use eligible funds for this replacement project (less demolition costs) towards the renovation of another existing RSD school. This project scope of work includes only the demolition and disposal of Hardin Elementary modulars. Natioual Environmental Policy Act (NEPA) Determination D Statutorily excluded from NEPA review (Review Concluded) D Programmatic Categorical Exclusion D Categorical Exclusion -Category D No Extraordinary Circumstances exist. Are project conditions required? D Yes (see section V) D No (Review Concluded) D Extraordinary Circumstances exist (see Section IV). D Extraordinary Circumstances mitigated. (see Section IV comments) Are project conditions required? D Yes (see section V) D No (Review Concluded) D Environmental Assessment D Supplemental Environmental Assessment (Reference EA or PEA in comments) D Environmental Impact Statement [8J Scope of work requires public involvement plan Comments: This project meets the criteria to utilize the Alternative Arrangements process within the National Environmental Policy Act (NEPA) approved by the Council on Environmental Quality, Department of Homeland Security, and FEMA on 3/23/06. Based on documentation provided by the applicant, FEMA has determined that the Recovery School District has conducted a satisfactory process of public involvement and outreach in its project development and is otherwise eligible for consideration under Alternative Arrangements for NEPA compliance. The Recovery School District is responsible for archiving public involvement materials. This material will be available at close-out for authentication and such documentation will be made available for the closeout reviewer. Project is Non-Compliant (see attached documentation justifYing selection). Reviewer and Approvals FEMA Environmental Reviewer: Name: Adam Borden, E ialist, FEMA LA-TRO Signature _--,,F-'~-"--t/-Jd -07 __----L.__-"----""'--____ Date FEMA Environmental Liaison Officer or Delegated Approving Official: Name: Cynthia eeter, De u Environmental Liaison Officer, FEMA LA TRO Signat::_..----:...:s;;;;2:;::f::::::;;k::::~..L..:.....\..>.~.,d.~~___ Date _l\(-'-'.-_d_?l-L-cf)-'---'--__-' Record ofEnvironmental Consideration (Version April 2007) I. Compliance Review for Environmental Laws (other than NEPA) A. National Historic Preservation Act (NHPA) D Not type of activity with potential to affect historic structures or archaeological resources (Review Concluded) D Activity meets Programmatic Agreement, December 3,2004. Appendix A: Allowance No. Are project conditions required? D Yes (see Section V) D No IZI Programmatic Agreement not applicable for historic structures or archeological sites, must conduct standard Section 106 Review (see comments). D Other Programmatic Agreement dated applies HISTORIC BUILDINGS AND STRUCTURES D No historic properties that are listed or 45/50 years or older in project area. (Review Concluded) IZI Building or structure listed or 45/50 years or older in project area and activity not exempt from review. IZI Determination of No Historic Properties Affected (FEMA findinglSHPO/THPO concurrence on file) Are project conditions required? IZI Yes (see Section V) D No (Review Concluded) D Determination ofHistoric Properties Affected (FEMA findinglSHPOITHPO concurrence on file) D Property a National Historic Landmark and National Park Service was provided early notification during the consultation process. If not, explain in comments D No Adverse Effect Determination (FEMA findinglSHPO/THPO concurrence on file) Are project conditions required? D Yes (see Section V) D No (Review Concluded) D Adverse Effect Determination (FEMA findinglSHPO/THPO concurrence on file) D Resolution of Adverse Effect completed (MOA on file) Are project conditions required D Yes (see Section V) D No (Review Concluded) ARCHEOLOGICAL RESOURCES D Project scope of work has no potential to affect archeological resources (Review Concluded) IZI Project affects only previously disturbed ground. (Review Concluded) D Project affects undisturbed ground or grounds associated with a historic structure D Project area has no potential for presence ofarcheological resources D Determination of no historic properties affected (FEMA findinglSHPO/THPO concurrence on file) (Review Concluded) D Project area has potential for presence of archeological resources D Determination of no historic properties affected (FEMA findinglSHPO/THPO concurrence on file) Are project conditions required D Yes (see Section V) D No (Review Concluded) D Determination of historic properties affected D NR eligible resources not present (FEMA findinglSHPOITHPO concurrence on file) Are project conditions required D Yes (see Section V) D No (Review Concluded) D NR eligible resources present in project area (FEMA findinglSHPO/THPO concurrence on file) D No Adverse Effect Determination (FEMA findingl SHPO/THPO concurrence on file) Are project conditions required? D Yes (see Section V) D No (Review Concluded) D Adverse Effect Determination (FEMA findinglSHPO/THPO concurrence on file) D Resolution ofAdverse Effect completed (MOA on file) Are project conditions required? D Yes (see Section V) D No (Review Concluded) Comments: FEMA, in consultation with the State Historic Preservation Officer (SHPO), has determined that the demolition of Joseph Hardin Elementary and removal of foundation will have no effect on historic properties. Correspondence/Consultation/References: -Amber Martinez, Historic Preservation Specialist B. Endangered Species Act IZI No listed species and/or designated critical habitat present in areas affected directly or indirectly by the Federal action. (Review Concluded) D Listed species and/or designated critical habitat present in the areas affected directly or indirectly by the Federal action. D No effect to species or designated critical habitat. (See comments for justification) Are project conditions required? D Yes (see Section V) D No (Review Concluded) Record of Environmental Consideration (Version April 2007) o May affect, but not likely to adversely affect species or designated critical habitat (FEMA determinationlUSFWSINMFS concurrence on file) (Review Concluded) Are project conditions required? 0 Yes (see Section V) 0 No (Review Concluded) o Likely to adversely affect species or designated critical habitat o Formal consultation concluded. (Biological Assessment and Biological Opinion on file) Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: Project is located in an urban or previously developed area. Neither listed species nor their habitat occur in or near this site, thus FEMA finds there will be no effect to threatened or endangered species. Correspondence/Consultation/References: USFWS emergency consultation provisions determined in letters dated September 15,2005 for Katrina. C. Coastal Barrier Resources Act I2J Project is not on or connected to CBRA Unit or Otherwise Protected Area (Review Concluded). o Project is on or connected to CBRA Unit or Otherwise Protected Area. (FEMA determinationlUSFWS consultation on file) o Proposed action an exception under Section 3505.a.6 (Review Concluded) o Proposed action not excepted under Section 3505.a.6. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: Project is not within a CBRA zone. Correspondence/Consultation/References: Louisiana Coastal Barrier Resource System Maps referenced 04/20/09. D. Clean Water Act [gJ Project would not affect any waters of the U.S. (Review Concluded) o Project would affect waters, including wetlands, ofthe U.s. o Project exempted as in kind replacement or other exemption. (Review Concluded) o Project requires Section 404/401 of Clean Water Act or Section 9/10 of Rivers and Harbors Act permit, including qualification under Nationwide Permits. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) o Project would affect waters of the U.S. by discharging to a surface water body. Comments: No jurisdictional waters of the U.S., including wetlands, occur in the project area. Correspondence/Consultation/References: USFWS National Wetlands Inventory map (http://www.fws.gov/nwi/) queried on 04/20/09. E. Coastal Zone Management Act o Project is not located in a coastal zone area and does not affect a coastal zone area (Review concluded) [gJ Project is located in a coastal zone area and/or affects the coastal zone I2J State administering agency does not require consistency review. (Review Concluded). o State administering agency requires consistency review. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: This project is located within the Louisiana Coastal Management Zone. LA DNR has determined that receipt of federal assistance is consistent with the Louisiana Coastal Resource Program. Projects within the coastal zone may stil1 require a coastal use permit or other authorization from DNR. Projects may be coordinated by contacting LA DNR at 1800- 276-4019. Correspondence/Consultation/References: Louisiana Coastal Zone maps queried 04/20/09. F. Fish and Wildlife Coordination Act I2J Project does not affect, control, or modifY a waterwaylbody of water. (Review Concluded) o Project affects, controls or modifies a waterwaylbody ofwater. o Coordination with USFWS conducted o No Recommendations offered by USFWS. (Review Concluded) o Recommendations provided by USFWS. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Record of Environmental Consideration (Version April 2007) Comments: No streams or water bodies are located in or near the project area. Correspondence/Consultation/References: Louisiana Map (http://wwwlamap.doa.louisiana.gov/) queried 04/20109. G. Clean Air Act [gI Project will not result in permanent air emissions. (Review Concluded) o Project is located in an attainment area.