Record of Environmental Consideration REVISED FOR FEMA ENVIRONMENTAL --LOUISIANA See 44 Code of Federal Regulation Part 10 Project NamelNumber: Carver Complex HSIMS-Bldg HI PW 11509vsn4 Applicant Name: Recovery School District Project Location: 3059 Higgins Blvd., New Orleans, LA 70126 Latitude: 29.99483, Longitude: -90.03841 Project Description: Hurricane Katrina caused catastrophic damage on August 29, 2005 to Carver Complex HSIMS-Bldg H. This project is one among a total of22 contributing (donor) facilities approved by FEMA for replacement. The Recovery School District chooses to use eligible funds for this replacement project (less demolition costs) towards the renovation of another existing RSD school. This project scope of work includes only the demolition and disposal of Carver Complex HSIMS-Bldg H. National Environmental Policy Act (NEPA) Determination D Statutorily excluded from NEP A review (Review Concluded) D Programmatic Categorical Exclusion D Categorical Exclusion -Category D No Extraordinary Circumstances exist. Are project conditions required? D Yes (see section V) D No (Review Concluded) D Extraordinary Circumstances exist (see Section IV). D Extraordinary Circumstances mitigated. (see Section IV comments) Are project conditions required? D Yes (see section V) D No (Review Concluded) D Environmental Assessment D Supplemental Environmental Assessment (Reference EA or PEA in comments) D Environmental Impact Statement IS] Scope of work requires public involvement plan Comments: This project meets the criteria to utilize the Alternative Arrangements process within the National Environmental Policy Act (NEPA) approved by the Council on Environmental Quality, Department of Homeland Security, and FEMA on 3/23/06. Based on documentation provided by the applicant, FEMA has detennined that the Recovery School District has conducted a satisfactory process of public involvement and outreach in its project development and is otherwise eligible for consideration under Alternative Arrangements for NEPA compliance. The Recovery School District is responsible for archiving public involvement materials. This material will be available at close-out for authentication and such documentation will be made available for the closeout reviewer. D Project is Non-Compliant (see attached documentation justitying selection). Reviewer and Approvals FEMA Environmental Reviewer: Name: Adam Borden:JAironmental 081, FEMA LA-TRO SIgnature __..~~~==---=-7_;"'_..c.._~"i~--:...:.:::____ Date tt-r2 ?-0 "( FEMA Environmental Liaison Officer or Delegated Approving Official: Name: Cynthia eter, Depu!)' Environmental Liaison Officer, FEMA LA TRO Signa~ M ,. ~ Date <.fL~{1, I{j~ Record of Environmental Consideration (Version April 2007) I. Compliance Review for Environnlental Laws (other than NEP A) A. National Historic Preservation Act (NHPA) o Not type ofactivity with potential to affect historic structures or archaeological resources (Review Concluded) o Activity meets Programmatic Agreement, December 3, 2004. Appendix A: Allowance No. Are project conditions required? 0 Yes (see Section V) 0 No [gI Programmatic Agreement not applicable for historic structures or archeological sites, must conduct standard Section 106 Review (see comments). o Other Programmatic Agreement dated applies HISTORIC BUILDINGS AND STRUCTURES o No historic properties that are listed or 45/50 years or older in project area. (Review Concluded) [gI Building or structure listed or 45/50 years or older in project area and activity not exempt from review. [gI Determination ofNo Historic Properties Affected (FEMA findingiSHPOITHPO concurrence on file) Are project conditions required? [gI Yes (see Section V) 0 No (Review Concluded) o Determination of Historic Properties Affected (FEMA findingiSHPOITHPO concurrence on file) o Property a National Historic Landmark and National Park Service was provided early notification during the consultation process. Ifnot, explain in comments o No Adverse Effect Determination (FEMA finding/SHPOITHPO concurrence on file) Are project conditions required? 0 Yes (see Section V) 0 No (Review Concluded) o Adverse Effect Determination (FEMA finding/SHPOITHPO concurrence on file) o Resolution ofAdverse Effect completed (MOA on file) Are project conditions required 0 Yes (see Section V) 0 No (Review Concluded) ARCHEOLOGICAL RESOURCES o Project scope of work has no potential to affect archeological resources (Review Concluded) [gI Project affects only previously disturbed ground. (Review Concluded) o Project affects undisturbed ground or grounds associated with a historic structure o Project area has no potential for presence of archeological resources o Determination of no historic properties affected (FEMA finding/SHPOITHPO concurrence on file) (Review Concluded) o Project area has potential for presence of archeological resources o Determination of no historic properties affected (FEMA findingiSHPOITHPO concurrence on file) Are project conditions required 0 Yes (see Section V) 0 No (Review Concluded) o Determination of historic properties affected o NR eligible resources not present (FEMA findingiSHPOITHPO concurrence on file) Are project conditions required 0 Yes (see Section V) 0 No (Review Concluded) NR eligible resources present in project area (FEMA findingiSHPOITHPO concurrence on file) o No Adverse Effect Determination (FEMA findingl SHPOITHPO concurrence on file) Are project conditions required? 0 Yes (see Section V) 0 No (Review Concluded) o Adverse Effect Determination (FEMA finding/SHPOITHPO concurrence on file) o Resolution of Adverse Effect completed (MOA on file) Are project conditions required? 0 Yes (see Section V) 0 No (Review Concluded) Comments: FEMA, in consultation with the State Historic Preservation Officer (SHPO), has determined that the demolition of Carver Complex HS/MS-Bldg H and removal offoundation will have no effect on historic properties. Correspondence/Consultation/References: -Amber Martinez, Historic Preservation Specialist B. Endangered Species Act [gI No listed species and/or designated critical habitat present in areas affected directly or indirectly by the Federal action. (Review Concluded) o Listed species and/or designated critical habitat present in the areas affected directly or indirectly by the Federal action. o No effect to species or designated critical habitat. (See comments for justification) Are project conditions required? 0 Yes (see Section V) 0 No (Review Concluded) Record of Environmental Consideration (Version April 2007) o May affect, but not likely to adversely affect species or designated critical habitat (FEMA detennination/USFWSINMFS concurrence on file) (Review Concluded) Are project conditions required? 0 Yes (see Section V) 0 No (Review Concluded) o Likely to adversely affect species or designated critical habitat o Fonnal consultation concluded. (Biological Assessment and Biological Opinion on file) Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: Project is located in an urban or previously developed area. Neither listed species nor their habitat occur in or near this site, thus FEMA finds there will be no effect to threatened or endangered species. Correspondence/Consultation/References: USFWS emergency consultation provisions detennined in letters dated September 15,2005 for Katrina. C. Coastal Barrier Resources Act [8J Project is not on or connected to CBRA Unit or Otherwise Protected Area (Review Concluded). o Project is on or connected to CBRA Unit or Otherwise Protected Area. (FEMA detenninationlUSFWS consultation on file) o Proposed action an exception under Section 3505.a.6 (Review Concluded) o Proposed action not excepted under Section 3505.a.6. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: Project is not within a CBRA zone. Correspondence/Consultation/References: Louisiana Coastal Barrier Resource System Maps referenced 04/20/09. D. Clean Water Act [8J Project would not affect any waters of the U.S. (Review Concluded) o Project would affect waters, including wetlands, of the U.S. o Project exempted as in kind replacement or other exemption. (Review Concluded) o Project requires Section 404/401 of Clean Water Act or Section 9/1 0 of Rivers and Harbors Act penn it, including qualification under Nationwide Pennits. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) o Project would affect waters of the U.S. by discharging to a surface water body. Comments: No jurisdictional waters of the U.S., including wetlands, occur in the project area. Correspondence/Consultation/References: USFWS National Wetlands Inventory map (http://www.fws.gov/nwi/) queried on 04120109. E. Coastal Zone Management Act o Project is not located in a coastal zone area and does not affect a coastal zone area (Review concluded) [8J Project is located in a coastal zone area and/or affects the coastal zone [8J State administering agency does not require consistency review. (Review Concluded). o State administering agency requires consistency review. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: This project is located within the Louisiana Coastal Management Zone. LA DNR has detennined that receipt of i federal assistance is consistent with the Louisiana Coastal Resource Program. Projects within the coastal zone may still require a coastal use penn it or other authorization from DNR. Projects may be coordinated by contacting LA DNR at 1800- 276-4019. Corres ondence/Consultation/Re erences: Louisiana Coastal Zone rna s ueried 04/20/09. F. Fish and Wildlife Coordination Act [8J Project does not affect, control, or modify a waterwaylbody of water. (Review Concluded) o Project affects, controls or modifies a waterwaylbody ofwater. o Coordination with USFWS conducted o No Recommendations offered by USFWS. (Review Concluded) o Recommendations provided by USFWS. Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Record of Environmental Consideration (Version April 2007) Comments: No streams or water bodies are located in or near the project area. Correspondence/Consultation/References: Louisiana Map (http://wwwlamap.doa.louisiana.gov/) queried 04/20109. G. Clean Air Act [8J Project will not result in permanent air emissions. (Review Concluded) D Project is located in an attainment area. (Review Concluded) D Project is located in a non-attainment area. D Coordination required with applicable state administering agency. Are project conditions required? D YES (see section V) D NO (Review Concluded) Comments: This project involves the renovation of a public structure. The proposed project includes activities that would produce a minor, temporary, and localized impact on air quality from fugitive dust particles. No long-term air quality impact is anticipated. Correspondence/Consultation/References: EPA Region 6 Non-attainment Map. H. Farmland Protection Policy Act [8J Project will not affect undisturbed ground. (Review Concluded) D Project has a zoning classification that is other than agricultural or is in an urbanized area. (Review Concluded) D Project does not affect designated prime or unique farmland. (Review Concluded) D Project causes unnecessary or irreversible conversion of designated prime or unique farmland. D Coordination with Natural Resources Conservation Service required. D· Farmland Conversion Impact Rating, Form AD-l 006, completed. Are project conditions required? D YES (see section V) D NO (Review Concluded) Comments: The project site is in a developed urbanized area and Farmland Protection Policy Act (FPPA) is precluded. No prime or unique farmland present. Correspondence/Consultation/References: National Resource Conservation Service, Web Soil Survey (htto:llwebsoilsurvev.nrcs.usda.gov/aop/) referenced 04/20109. I. Migratory Bird Treaty Act D Project not located within a flyway zone (Review Concluded) [8J Project located within a flyway zone. [8J Project does not have potential to take migratory birds (Review Concluded) Are project conditions required? D Yes (see section V) [8J No (Review Concluded) Project has potential to take migratory birds. D Contact made with USFWS Are project conditions required? D YES (see section V) D NO (Review Concluded) Comments: The site is an existing disturbed area with little value to migratory birds and would not be included in the USFWS migratory bird management program. Correspondence/Consultation/References: USFWS guidance letter dated September 27,2005. J. Magnuson-Stevens Fishery Conservation and Management Act [8J Project not located in or near Essential Fish Habitat (Review Concluded) D Project located in or near Essential Fish Habitat. D Project does not adversely affect Essential Fish Habitat (Review Concluded) Are project conditions required? D Yes (see Section V) D No (Review Concluded) D Project adversely affects Essential Fish Habitat (FEMA determinationlUSFWSINMFS concurrence on file) D NOAA Fisheries provided no recommendation(s) (Review Concluded), Are project conditions required? D Yes (see Section V) D No (Review Concluded) D NOAA Fisheries provided recommendation(s) Written reply to NOAA Fisheries recommendations completed. Are project conditions required? D YES (see Section V) D NO (Review Concluded) IComments: Project is not located in any surface waters with the potential to affect EFH species. Record of Environmental Consideration (Version April 2007) ICorrespondence/Consultation/References: Louisiana Map (http://wwwlamap.doa.louisiana.govl) referenced 04/20109. K. Wild and Scenic Rivers Act [8J Project is not along and does not affect Wild or Scenic River (WSR) -(Review Concluded) o Project is along or affects WSR o Project adversely affects WSR as detennined by NPS/uSFS. FEMA cannot fund the action. (NPS/uSFS/uSFWS/BLM consultation on file) (Review Concluded) o Project does not adversely affect WSR. (NPS/uSFS/uSFWS/BLM consultation on file) Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: Project is not along and does not affect Wild or Scenic River (WSR). Corre.fpondence/Consultation/References: National Wild and Scenic Rivers http://www.nps.gov/rivers/wildriverslist.html. L. Resource Conservation and Recovery Act State Hazardous Materials and Solid Waste Laws and Resource Conservation and Recovery Act Comments: The renovation activities associated with this project may result in various types of debris and wastes, some of which may be hazardous. Therefore, all debris and waste must be treated, stored, and disposed of in a proper manner and location. (See Section V) II. Compliance Review for Executive Orders A. E.O. 11988 -Floodplains [8J No Effect on Floodplains/Flood levels and project outside Floodplain -(Review Concluded) o Located in Floodplain or Effects on FloodplainslFlood levels o No adverse effect on floodplain and not adversely affected by the floodplain. (Review Concluded), Are project conditions required? 0 Yes (see Section V) 0 No (Review Concluded) o Beneficial Effect on Floodplain Occupancy/Values (Review Concluded). o Possible adverse effects associated with investment in floodplain, occupancy or modification of floodplain environment o 8 Step Process Complete -documentation on file Are project conditions required? 0 YES (see Section V) 0 NO (Review Concluded) Comments: This version is for the demolition of the facility. The remaining replacement funds will be de-obligated and applied to an alternate project involving another facility. No further floodplain review will be forthcoming for PW listed unless there should be a fe-obligation of funds or changes to the scope of work. Correspondence/Consultation/References: Kimberly R. Rogers, Floodplain Management Specialist B. E.O. 11990 -Wetlands [8J No Effects on Wetland(s) andlor project located outside WetJand(s) -