Timeline for the Hazard Mitigation Grant Program

Timeline from 0 to 48 months.
Step 1: Project scoping, 6 months.
Step 2: Project development, 5 months.
Step 3: Project submission, 1 month.
Step 4: Project review, Average of 90 days.
Step 5: Project award and obligation, 1 to 3 months.
Step 6: Project implementation and monitoring, Up to 36 months.
Step 7: Award closeout, 90 days.

Timeline from 0 to 48 months.

Step 1: Project scoping, 6 months.

Step 2: Project development, 5 months.

Step 3: Project submission, 1 month.

Step 4: Project review, Average of 90 days.

Step 5: Project award and obligation, 1 to 3 months.

Step 6: Project implementation and monitoring, Up to 36 months.

Step 7: Award closeout, 90 days.