alert - warning

This page has not been translated into Kreyòl. Visit the Kreyòl page for resources in that language.

91st Avenue Wastewater Treatment Plant

TOLLESON, AZ - The 91st Avenue Wastewater Treatment Plant (WWTP), located along the Salt River in the City of Phoenix, Arizona, has been at risk from the continued soil erosion of the existing bank. It was determined that flooding greater than a 10-year event could potentially cause a 600-foot lateral migration of the north bank of the Salt River. Under this scenario the out-fall channel, the Tolleson Landfill, a portion of the chlorine contact chambers, and a portion of the south holding ponds would be destroyed.

A mitigation project was undertaken by Maricopa County and the City of Tolleson. The project extended an existing soil-cement bank approximately 2,700 feet along the north bank of the Salt River. The soil-cement bank protects the 91st Avenue WWTP and Tolleson Landfill in the City of Tolleson, Maricopa County, Arizona. Material was imported for the soil-cement mix. Excavating a V-shaped toe fourteen feet below the thalwag, backfilling against the soil-cement stabilization with the excavated material, and placing a maximum of 174 feet of the soil-cement bank stabilization below the plane of the ordinary high water mark all were done to strengthen and extend the north bank.

This project also involves the removal and replacement of all digester gas piping and the retrofit of an existing hot water loop and an existing boiler building. There also is the construction of a new boiler building.

University crews demolished the existing digester gas system, fabricated new 24-inch through 8-inch diameter stainless steel piping, and then re-piped 16 digesters at 91st Avenue. Completing this effort required an extremely intense effort, including two 24-hour shutdowns.

The benefits in avoided future damage are expected to at least equal the cost of this project.

Tags: