Coeur d'Alene Tribe
Appeal Brief
Applicant | Idaho Office of Emergency Management |
Appeal Type | 1st |
Project Number | 5 |
Date Signed | 2018-05-29T00:00:00 |
- Issue
- FEMA Region X terminated and de-obligated funds awarded to a generator project based on the finding that an updated hazard mitigation plan had not been provided to FEMA within one year of the grant award.
- Reason for Approval
- Region X found that the subrecipient reasonably complied with 44 CFR and the Extraordinary Circumstances Exception approval letter by providing a hazard mitigation plan to FEMA and IOEM within 12 months of the award of the project grant and prior to the deadline for mitigation plan approval.
- Reference(s)
- 44 CFR 206.434 (b)(2) - Extraordinary circumstances
- 44 CFR 206.440 (b)(1) - Appeals