After You Apply for Flood Mitigation Assistance Funds

Managing Your Award

After FEMA has completed its review of all FMA subapplications, each of them will be assigned and updated with one of the following three statuses:

Once a status has been assigned, FEMA will make a formal announcement. At that time, FEMA Regions will conduct any additional pre-award review action necessary. Applicants should work with their FEMA Regional points of contact and subapplicants should work with their applicant points of contact.

alert - info

Previously selected subapplications for the Flood Mitigation Assistance Program are available here.

Managing Your Award

The Period of Performance (POP) is 48 months for Community Flood Mitigation Projects and 36 months for all other activities, starting on the date of the recipient’s federal award. Any subsequent amendments to the federal award, including awarding additional subawards, will not extend the POP unless explicitly stated.

Mitigation Project Requirements

Mitigation projects must, at a minimum, be in conformance with the latest published editions (meaning either of the two most recently published editions) of relevant consensus-based codes, specifications and standards that incorporate the latest hazard-resistant designs.

If the mitigation project is within a Special Flood Hazard Area, it must meet both of the following conditions:

  • The project is in a jurisdiction participating in the National Flood Insurance Program that is not on probation, suspended or withdrawn.
  • The property owner obtains and maintains flood insurance for the life of the structure, regardless of transfer of ownership, in an amount at least equal to the project cost or to the maximum limit of coverage made available with respect to the mitigated property, whichever is less.

Long-Term Monitoring Requirements

By accepting an award, all recipients agree to participate in monitoring or an evaluation of the grant, which may include analysis of the impact and providing access to program operating personnel and participants, as specified by the evaluator(s).

Starting Project Construction

Construction activities can begin after approval. Construction activities for which ground disturbance has already been initiated or completed prior to funding award are not eligible for funding. Non-construction activities that have already started may not be considered for funding if not approved as pre-award activities.

alert - info

Subapplicants should contact their appropriate state, tribe or territory (applicant level) Hazard Mitigation Office for further information. State and territory contacts are provided here: State Hazard Mitigation Officers