Support Documentation

Appeal Brief Appeal Letter Appeal Analysis

Appeal Brief

DisasterFEMA-1345
ApplicantMiami-Dade County
Appeal TypeSecond
PA ID#025-99025-00
PW ID#3343
Date Signed2017-10-20T00:00:00

Conclusion: Because Miami-Dade County (Applicant) never received the final request for information (RFI), this appeal is remanded to Region IV to issue another RFI and a new first appeal decision.

Summary Paragraph

From October 3 through 11, 2000, heavy rains impacted the state of Florida, including the Applicant.  Multiple project worksheets (PWs) were written to address damage, including several for Category D, water control facilities.  Nearly six years after these PWs were closed out, FEMA prepared PW 3343 to address overruns in project management, engineering, and design costs.  FEMA subsequently determined that none of these costs were eligible because the record did not justify the overruns or delay in seeking reimbursement.  The Applicant then appealed FEMA’s decision.  FEMA Region IV issued a final RFI, but the Applicant never received it.  The Region IV Regional Administrator denied the first appeal based, in part, on a lack of documentation in the record to support the Applicant’s appeal.  The Applicant then filed a second appeal, arguing that it did not have the opportunity to provide documentation to support its first appeal because it never received the final RFI.
Authorities and Second Appeals

  • Recovery Directorate Manual, Public Assistance Program Appeal Procedures (Appeals Manual), at 14.

Headnotes

  • According to the Appeals Manual, a final RFI must be issued for the administrative record to properly close.
    • Here, the Applicant never received the final RFI, so the administrative record was not properly closed.

       

Appeal Letter


Wes Maul
Interim Director
State of Florida Division of Emergency Management
2555 Shumard Oaks Boulevard
Tallahassee, Florida  32399-2100

Re:  Second Appeal – Miami-Dade County, PA ID: 025-99025-00, FEMA-1345-DR-FL, Project Worksheet (PW) 3343

Dear Mr. Maul:

This is in response to a letter from your office dated September 26, 2017, which transmitted the referenced second appeal on behalf of the Miami-Dade County (Applicant).  The Applicant is appealing the Department of Homeland Security’s Federal Emergency Management Agency’s (FEMA) denial of $399,386.43 pertaining to overruns in project management, engineering, and design costs.

As explained in the enclosed analysis, because I have determined that the Applicant did not receive the final request for information (RFI), I am remanding this appeal to Region IV so that a new final RFI can be issued and a new first appeal determination made, taking into consideration any new documents that the Applicant submits.    

Sincerely,

/s/

Christopher Logan
Director
Public Assistance Division                                                     

Enclosure

cc: Gracia Szczech
     Regional Administrator
     FEMA Region IV

 

Appeal Analysis

Background

From October 3 through 11, 2000, heavy rains impacted the state of Florida, including Miami-Dade County (Applicant).  Multiple project worksheets (PWs) were written to address damage, including several for Category D, water control facilities.  In 2009, nearly six years after these Category D projects were closed out, FEMA prepared PW 3343 to address overruns in project management, engineering, and design costs which the Applicant asserted were eligible for Public Assistance (PA) funding, but had not been reimbursed previously.  The total of these costs was $399,386.43.  In September 2014, FEMA determined that the additional costs were ineligible for funding because the record did not justify the cost overruns or delay in seeking reimbursement.[1] 

First Appeal

The Applicant appealed FEMA’s denial in January 2015, arguing that the cost overruns were eligible for PA funding.[2]  The Applicant inquired with the Florida Division of Emergency Management (Grantee) as to the status of the appeal in emails dated March 5, 2015, May 24, 2016, June 1, 2016, and December 19, 2016.[3]  On December 22, 2016, FEMA Region IV issued a final Request for Information (RFI) for documentation to support the cost overruns and delay in seeking reimbursement.  The final RFI, however, was emailed to the Grantee, and not to the Applicant.[4]  On January 11, 2017, the Grantee contacted FEMA requesting the status of the first appeal.  FEMA responded the same day, advising the Grantee that an RFI had been sent and attaching a copy of the RFI and the December 22 email.  There is no indication in the record that the Grantee ever forwarded the RFI to the Applicant because, on June 6, 2017, the Applicant again contacted the Grantee requesting an update on the status of the first appeal and stating that it had not heard from FEMA or the Grantee regarding the first appeal.  The Grantee replied, explaining that the appeal was under consideration by FEMA, but neglecting to mention the RFI.

The Region IV Regional Administrator issued the first appeal determination on June 28, 2017.  She denied the first appeal because the administrative record did not contain sufficient documentation to justify the cost overruns or the delay in seeking reimbursement.  The first appeal decision specifically mentioned the Applicant’s failure to respond to the RFI.

Second Appeal

The Applicant filed its second appeal in a letter dated August 18, 2017.  It summarized its substantive arguments, and argued that it never received the final RFI, so it never had the opportunity to provide documentation that would have supported its first appeal.  In forwarding the second appeal, the Grantee acknowledges that it has no record of sending the RFI to the Applicant.  Following the submission of the second appeal, the Grantee inquired with FEMA as to whether the RFI had been sent to the Applicant, as stated in the first appeal decision.  FEMA acknowledged in an email dated August 23, 2017, that it had not and that the statement within the first appeal decision was incorrect.

Discussion

When a Regional Administrator (RA) is considering denying a first appeal in whole or in part, the RA must issue to the applicant a final RFI, explaining the basis for the likely denial and requesting that the applicant provide additional information that could support its appeal.[5]  The Applicant must also be advised that, after the RA issues the first appeal decision, the administrative record will close and FEMA will not consider new documentation submitted for the first time on second appeal.  

Here, FEMA is convinced that, despite the fact that Region IV sent the RFI to the Grantee twice, the Applicant never received it.  As FEMA has already acknowledged, the RFI was not sent directly to the Applicant.  The Applicant diligently inquired about the status of the appeal, but was not informed about the RFI.  Moreover, the first appeal decision relied, at least in part, on the lack of documentation in the administrative record, making the RFI particularly important in this case.

Conclusion

In light of the foregoing, this appeal is remanded to Region IV to rescind the first appeal determination so that a new RFI can be issued and the Applicant can submit documentation.  After this, a new first appeal decision must be issued taking the Applicant’s documentation into consideration, at which point the administrative record will close.  In remanding this appeal, FEMA expresses no opinion on the substantive merits of the Applicant’s arguments.

 

[1] Because this second appeal deals exclusively with a procedural issue, this analysis will not discuss the underlying substantive issue.

[2] The first appeal decision noted an extensive delay in the Applicant receiving notification of FEMA’s decision, but found that the Applicant’s first appeal was timely.

[3] These emails were provided with the second appeal, which means that Region IV did not have the benefit of seeing them prior to issuing its decision.  As will be discussed later in this analysis, FEMA typically will not consider new information on second appeal.  Here, however, these emails relate directly to the closing of the administrative record.  Accordingly, as will be discussed later, FEMA will consider them to the extent they are relevant to this purely procedural issue.

[4] According to the email, a hard copy of the RFI was also to be sent to the Applicant, but review of the record does support a conclusion that such delivery occurred.    

[5] Recovery Directorate Manual, Public Assistance Program Appeal Procedures, Version 3, at 14 (Apr. 7, 2014).

Last updated