alert - warning

This page has not been translated into Tiếng Việt. Visit the Tiếng Việt page for resources in that language.

Hillside Drive West Road Repair

Appeal Brief Appeal Letter

Appeal Brief

DisasterFEMA-1577-DR
ApplicantLos Angeles (County)
Appeal TypeSecond
PA ID#037-99037-00
PW ID#3118
Date Signed2007-12-03T05:00:00

Citation:         FEMA-1577-DR-CA, Los Angeles (County), Project Worksheet (PW) #3118, Hillside Drive West Road Repair

Cross             

Reference:      Pre-disaster Condition; Eligible Work; Improved Project; Reasonable Costs

Summary:      As a result of heavy rainfall during the January 2005 Winter Storms, PW #3118 was prepared in September 2005 for $656,222 to stabilize a slope failure in order to restore a portion of the pavement and unpaved shoulder along a section of Hillside Drive West near mile marker (MM) 0.12.  The PW calls for a 155-foot long soldier pile wall, with piles 8 feet on-centers, and pre-cast reinforced concrete panels, along with provision for drainage behind the wall, as well as the restoration of the asphalt pavement.  The County contends that the repair requires a cast-in-place reinforced concrete wall, soldier piles spaced 6 feet on-centers, as well as 232 feet of guardrail and 162 feet of 3-inch PVC pipe for drainage.  The estimated total project cost requested in the second appeal is $1,095,168.

Issues:             1.   Has the Applicant provided the necessary documentation to justify a change to the approved scope of work?

2.   Does the information provided warrant an increase in the approved project costs?

Findings:        1.   No.  The Applicant did not provide information in the second appeal to support a change in the scope of work to repair the damage caused by the declared incident.

                        2.   No, the information provided by the Applicant indicates that this project is an Improved Project, and therefore the total eligible costs are limited to the approved estimate to restore the facility to its pre-disaster design.

Rationale:       44 CFR §206.223(a)(1); 44 CFR §206.203(d)(1)

Appeal Letter

Mr. Paul Jacks

Governor’s Authorized Representative

Governor’s Office of Emergency Services

Response and Recovery Division

3650 Schriever Avenue

Mather, CA  95655

 

Re:       Second Appeal – Los Angeles (County), PA ID 037-99037-00

            Hillside Drive West Road Repair, FEMA-1577-DR-CA, Project Worksheet 3118

Dear Mr. Jacks:

This letter is in response to your letter dated December 21, 2006, transmitting the referenced second appeal on behalf of Los Angeles County (Applicant).  The Applicant is appealing the Department of Homeland Security’s Federal Emergency Management Agency (FEMA) denial to revise the scope of work and increase funding for the repair of damages to this section of Hillside Drive West Road.

As a result of heavy rainfall during the January 2005 Winter Storms, FEMA prepared project worksheet(PW) 3118 for $656,222 in September 2005 to fund the stabilization of a slope failure along Hillside Drive in the Topanga area of Los Angeles County.  The scope of work in this PW included the construction of a 155-foot long soldier pile wall with piles eight feet on-centers, pre-cast reinforced concrete panels, drainage behind the wall, and restoration of the asphalt pavement.  The Applicant submitted a first appeal to the California Governor’s Office of Emergency Services (OES) on March 31, 2006.  OES forwarded the appeal to FEMA on May 26, 2006.  The Applicant requested that FEMA revise the scope of work in order to reflect a soldier pile wall with piles spaced six feet on-centers with a cast-in-place reinforced concrete wall and timber lagging for forming purposes.  Specific revisions included (1) an additional five (5) soldier piles (for a total of 26); (2) a cast-in-place reinforced concrete wall with timber lagging instead of pre-cast reinforced concrete panels; (3) 232 feet of guardrail; (4) 162 feet of 3-inch PVC pipe required for drainage; and (5) reinforced steel for concrete wall.  The Applicant also requested that FEMA revise the cost estimate from $656,222 to $1,042,615.  As part of the appeal the Applicant provided the following: (1) a document(date, preparer, and agency all unidentified) with a rationale for the use of a cast-in-place concrete wall with soldier piles; and (2) a line item estimate for the repair costs identified as Total Contract Estimate for Project RDC0014667 – Hillside Drive @ CM 0.12, Final Pay Quantity Items For 155 Ft Wall, prepared by County of Los Angeles Department of Public Works(LADPW) and dated March 30, 2006.

The Acting Regional Director denied the first appeal on August 14, 2006, because the Applicant did not provide sufficient documentation to support their request for the additional work items.  In this denial the Acting Regional Director noted that construction of a cast-in-place wall instead of the recommended pre-cast wall would not constitute a significant change in the approved scope of work, provided wall dimensions remained the same.

The Applicant submitted a second appeal to OES on October 31, 2006.  OES forwarded the appeal to FEMA on December 21, 2006.  The Applicant reiterated their position regarding the need for a change to the scope of work to comply with the design, along with the associated increase in the total project cost.  In addition to copies of the PW and first appeal response, the Applicant included the following information with the second appeal: (1) a copy of the geotechnical report prepared by the URS Corporation (URS) for the Hillside Drive Slope Failure (URS Job No. 29401960), dated March 25, 2005; (2) seven pages of information prepared by LADPW under a cover sheet titled Hillside Drive at Culvert Marker 0.12, Retaining Wall Calculations, Malibu, CA, signed and sealed by a professional engineer in the state of California; (3) a one-page cost comparison(date, preparer, and agency all unidentified) for two alternate pile spacings of six and eight feet; and (4) a revised line item estimate for the repair costs of the damage on Hillside Drive at CM 0.12 (Project RDC0014667) prepared by LADPW and dated October 24, 2006.  The total revised cost estimate was $1,095,168.  In addition, the Applicant stated that its Road Maintenance staff initially suggested piles on eight-foot centers, however, the design engineers later determined that the wall design with soldier piles spaced at six feet on centers was more cost effective.

We have reviewed all of the information submitted with the appeal and have determined that the Applicant’s request to change the scope of work is adequately supported with one exception.  There is no information in the file stating that the guard rail existed before the disaster or that it was based on an existing code or standard.  Therefore, I partially approve the request to revise the scope of work.  Because the Applicant’s latest cost estimate differs significantly from previous project estimates without explanation, I will not revise the cost estimated at this time.  We will reconcile the cost of the approved scope of work during the closeout.  By copy of this letter, I request the Regional Administrator to take the appropriate actions to implement this determination. 

Please inform the Applicant of my decision.  My determination constitutes the final decision on this matter as set forth in 44 CFR §206.206.

Sincerely,

/s/

Carlos J. Castillo

Assistant Administrator

Disaster Assistance Directorate

cc:          Nancy Ward

Regional Director

FEMA Region IX