Record of Environmental Consideration REVISED FOR FEMA ENVIRONMENTAL·-LOUISIANA See 44 Code of Federal Regulation Part 10 Project NamelNumber: John W. Hoffman ES Bldg G I PW 15291 vsn5 Applicant Name: Recovery School District Project Location: 2622 S. Prieur St. New Orleans, LA 70125 Latitude: 29.94452, Longitude: -90.09535 Project Description: Hurricane Katrina caused catastrophic damage on August 29, 2005 to John W. Hoffman ES Bldg G. This project is one among a total of22 contributing (donor) facilities approved by FEMA for replacement. The Recovery School District chooses to use eligible funds for this replacement project (less demolition costs) towards the renovation of another existing RSD school. This project scope of work includes only the demolition and disposal ofJohn W. Hoffman ES Bldg G. National Environmental Policy Act (NEPA) Determination D Statutorily excluded from NEPA review (Review Concluded) D Programmatic Categorical Exclusion D Categorical Exclusion -Category D No Extraordinary Circumstances exist. Are project conditions required? D Yes (see section V) D No (Review Concluded) D Extraordinary Circumstances exist (see Section IV). D Extraordinary Circumstances mitigated. (see Section IV comments) Are project conditions required? D Yes (see section V) D No (Review Concluded) D Environmental Assessment D Supplemental Environmental Assessment (Reference EA or PEA in comments) D Environmental Impact Statement [gJ Scope of work requires public involvement plan Comments: This project meets the criteria to utilize the Alternative Arrangements process within the National Environmental Policy Act (NEPA) approved by the Council on Environmental Quality, Department of Homeland Security, and FEMA on 3/23/06. Based on documentation provided by the applicant, FEMA has determined that the Recovery School District has conducted a satisfactory process of public involvement and outreach in its project development and is otherwise eligible for consideration under Alternative Arrangements for NEPA compliance. The Recovery School District is responsible for archiving public involvement materials. This material will be available at close-out for authentication and ,such documentation will be made available for the closeout reviewer. D Project is Non-Compliant (see attached documentation justifying selection). Reviewer and Approvals FEMA Environmental Reviewer: Specialist, FEMA LA-TRO Name: Adam BO~~irOnmenta Signature _--!:.,,~J~~:J,~~~::::::-____Date -Lf-+--ILI=-'i-+-----..:;{)~,f-----=. FEMA Environmental Liaison Officer or Delegated Approving Official: Name: Cynthi r, D Environmental Liaison Officer, FEMA LA TRO Sign~re _~~d~~.....Y...!....L--=:::::::::::::::::;;:""::=-___ Date _'l......I--'iY<-\{-'.j('-t'J-l-___-----' Record of Environmental Consideration (Version April 2007) I. Compliance Review for Environmental Laws (other than NEPA) A. National Historic Preservation Act (NHP A) o Not type ofactivity with potential to affect historic structures or archaeological resources (Review Concluded) o Activity meets Programmatic Agreement, December 3,2004. Appendix A: Allowance No. Are project conditions required? 0 Yes (see Section V) 0 No k8J Programmatic Agreement not applicable for historic structures or archeological sites, must conduct standard Section 106 Review (see comments). o Other Programmatic Agreement dated applies HISTORIC BUILDINGS AND STRUCTURES o No historic properties that are listed or 45/50 years or older in project area. (Review Concluded) k8J Building or structure listed or 45/50 years or older in project area and activity not exempt from review. k8J Determination ofNo Historic Properties Affected (FEMA findingiSHPO/THPO concurrence on file) Are project conditions required? k8J Yes (see Section V) 0 No (Review Concluded) o Determination ofHistoric Properties Affected (FEMA findingiSHPOITHPO concurrence on file) o Property a National Historic Landmark and National Park Service was provided early notification during the consultation process. If not, explain in comments o No Adverse Effect Determination (FEMA findingiSHPO/THPO concurrence on file) Are project conditions required? D Yes (see Section V) D No (Review Concluded) o Adverse Effect Determination (FEMA findingiSHPO/THPO concurrence on file) D Resolution ofAdverse Effect completed (MOA on file) Are project conditions required D Yes (see Section V) D No (Review Concluded) ARCHEOLOGICAL RESOURCES D Project scope of work has no potential to affect archeological resources (Review Concluded) k8J Project affects only previously disturbed ground. (Review Concluded) D Project affects undisturbed ground or grounds associated with a historic structure Project area has no potential for presence of archeological resources o Determination of no historic properties affected (FEMA findingiSHPO/THPO concurrence on file)