Reviewer Name: Catherine Jones Applicant: Recovery School District DisasterlEmergencylProgramIProject Title: DR1603LA I Hurricane Katrina I Public Assistance Program I EOR 1926 Barbara Jordan ES-Library (Building F) Record of Environmental Consideration See 44 Code ofFederal Regulation Part 10. Project NamelNumber: EOR 1926 Barbara Jordan ES-Library (Building F) / PW 12948 Project Location: 4348 Reynes Street New Orleans, Louisiana Orleans Parish 70126 (N30.01311 W90.01104) Project Description: Project activities include replacing 14 fluorescent strip lights, 20 recessed fluorescent lights, 3,097 vct flooring, 96 LF wood paneling, 25 LF ceramic tile, 7 SF plexiglass, 2 metal doors, one wood double door, 5 interior wood doors, 6 LF wood cabinets, 2 porcelain toilets, 2 wood toilet cubicles, 2 stainless framed mirrors, dispensers (soap, toilet paper & paper towels), 2 disconnect switch, safety switch, 12 ton condensing compressor unit, and electrical floor receptacles. Hazard mitigation will be achieved by compliance with codes and standards. Documentation Requirements D No Documentation Required (Review Concluded) D (Short version) All consultation and agreements implemented to comply with the National Historic Preservation Act, Endangered Species Act, and Executive Orders 11988, 11990 and 12898 are completed and no other laws apply. (Review Concluded) [gI (Long version) All applicable laws and executive orders were reviewed. Additional information for compliance is attached to this REC. National Environmental Policy Act (NEPAl Determination D Statutorily excluded from NEP A review. (Review Concluded) D Programmatic Categorical Exclusion -Category (Review Concluded) D Categorical Exclusion -Category D No Extraordinary Circumstances exist. Are project conditions required? D Yes (see section V) D No (Review Concluded) D Extraordinary Circumstances exist (See Section IV). D Extraordinary Circumstances mitigated. (See Section IV comments) Are project conditions required? D Yes (see section V) D No (Review Concluded) D Environmental Assessment D Supplemental Environmental Assessment (Reference EA or PEA in comments) [gI Environmental Impact Statement Comments: This project meets the criteria for an alternative arrangement (Permanent Schools) type ofproject. This project has conditions and requires mitigation under the other EHP laws which are listed under the NEPA level ofenvironmental review in the project worksheet. Any changes to this approved scope of work will require submission to, and evaluation and approval by, the state and FEMA prior to initiation ofany work, for compliance with the national environmental policy act. The applicant is required to obtain and comply with all local, state and federal permits and requirements. Non-compliance with the requirements noted above may jeopardize the receipt of federal funding. Reviewer Name: Catherine Jones Applicant: Recovery School District DisuterlEmergentylProgramIProjeet Tide: DRI603LA / Hurricane Katrina/ Public Assistance Program / EOR 1926 Barbara Jordan ES-Library (Building F) Reviewer and Approvals D Project is Non-Compliant (See attached documentation justifying selection). FEMA Environmental Reviewer. Name: Catherine Jone , Environmen"""-_,,,,,cialist Signature_.....Ic:-_--I-,H-"_______---=.. Date _--:::;;8/=2=8/=2;.;:..00=..;6"--____...:. FEMA Regional Environmental Officer or delegated approving official. Name: Howard R. Bush, ELO r,:;) ~ L:::> Signature ~--;;,-~ /;;z.2.----I, . Date __8=1=28=/2=0"""0=6______=_ I. Compliance Review for Environmental Laws (other than NEPAl A. National Historic Preservation Act ~Not type of activity with potential to affect historic properties. D Applicable executed Programmatic Agreement Otherwise, conduct standard Section 106 review. QActivity meets Programmatic Allowance # Are project conditions required? D Yes (see section V) D No . D Project is on or connected to CBRA Unit or Otherwise Protected Area. (FEMA detenninationlUSFWS consultation on file) D Proposed action an exception under Section 3S0S.a.6? (Review Concluded) D Proposed action not excepted under Section 3S0S.a.6. Are project conditions required? D YES (see section V) D NO (Review Concluded) Comments: None Correspondence/Consultation/References: D. Clean Water Act I:8l Project would not affect any waters ofthe U.S. (Review Concluded) D Project would affect waters, including wetlands, ofthe U.S. D Project exempted as in kind replacement or other exemption. (Review Concluded) D Project requires Section 404/40Ilor Section 911 0 (Rivers and Harbors Act) pennit, including qualification under Nationwide Pennits. Are project conditions required? D YES (see section V) D NO (Review Concluded) Comments: Project is not in or adjacent to any waterways ofthe US. Correspondence/Consultation/References: E. Coastal Zone Management Act D Project is not located in a coastal zone area and does not affect a coastal zone area (Review concluded) I:8l Project is located in a coastal zone area and/or affects the coastal zone I:8l State administering agency does not require consistency review. (Review Concluded). D State administering agency requires consistency review. Are project conditions required? D YES (see section V) D NO (Review Concluded Reviewer Name: Catherine Jones Appllcaot: Recovery School District DisuterlEmergeocylProgramiProjec:t Tide: DR1603LA I Hurricane Katrina I Public Assistance Program I EOR 1926 Barbara Jordan ES-Library (Buildin2 F) Comments: This project is located within the Louisiana Coastal Management Zone. La DNR has determined that receipt of federal assistance is consistent with the Louisiana Coastal Resource Program. Projects within the coastal zone may still require a coastal use permit or other authorization from DNR. Projects may be coordinated by contacting LA DNR at 1800- 267-4019.). Correspondence/Consultation/References: F. Fish and Wildlife Coordination Act ~Project does not affect, control, or modify a waterwaylbody ofwater. (Review Concluded) D Project affects controls or modifies a waterwaylbody of water. D Coordination with USFWS conducted D No Recommendations offered by USFWS. (Review Concluded) D Recommendations provided by USFWS. Are project conditions required? D YES (see section V) D NO (Review Concluded) Comments: Project is not in or adjacent to any waterways of the US. Correspondence/Consultation/References: G. Clean Air Act ~Project will not result in permanent air emissions. (Review Concluded) D Project is located in an attainment area. (Review Concluded) D Project is located in a non-attainment area. D Coordination required with applicable state administering agency.. Are project conditions required? D YES (see section V) D NO (Review Concluded) Comments: This project involves the demolition or renovation of a public structure. Regardless ofthe asbestos content, the applicant is responsible for ensuring that renovation or demolition activities are coordinated with the Louisiana Department of Environmental Quality (LDEQ) in accordance with the LDEQ "Sixth Amended Declaration of Emergency and Administrative Order" dated June 30,2006, incorporating the provisions ofEPA's National Emission Standards for Hazardous Air Pollutants (NESHAP) and the Louisiana Administrative Code (LAC) 33.m.S1S1 and Chapter 27. Should Asbestos Containing Materials (ACMS) be present at the project site, the applicant is also responsible for ensuring proper disposal in accordance with the previously referenced administrative order. Correspondence/Consultation/References: H. Farmland Protection Policy Act ~Project does not affect designated prime or unique farmland. (Review Concluded) D Project causes unnecessary or irreversible conversion ofdesignated prime or unique farmland. D Coordination with Natural Resource Conservation Commission required. o Farmland Conversion Impact Rating, Form AD-I 006, completed. Are project conditions required? 0 YES (see section V) D NO (Review Concluded) Comments: None Correspondence/Consultation/References: I. Migratory Bird Treaty Act D Project not located within a flyway zone. (Review Concluded) ~Project located within a flyway zone. ~Project does not have potential to take migratory birds. (Review Concluded) Are project conditions required? 0 Yes (see section V) ~No (Review Concluded) o Project has potential to take migratory birds. D Contact made with USFWS Are project conditions required? 0 YES (see section V) 0 NO (Review Concluded) Reviewer Name: Catherine Jones Applicant: Recovery School District DlsasterlEmergencylProgramIProject Title: DR 1603LA I Hurricane Katrina I Public Assistance Program I EOR 1926 Barbara Jordan ES-Library uildin Comments: See letter from Don Fairley to Mr. Russ Watson with USF&WS, dated 09/14/2005. Specifically, FEMA has detennined that restoration projects funded with federal resources will not have adverse impacts on migratory birds or other fish and wildlife reserves. These detenninations are based on the understanding that the conditions outlined in the Louisiana Endangered Species Summary are met. Corres ondence/Consultation/Re erences: htt :/1 J. Magnuson-Stevens Fishery Conservation and Management Act 181 Project not located in or near Essential Fish Habitat. (Review Concluded) o Project located in or near Essential Fish Habitat. o Project does not adversely affect Essential Fish Habitat.