Revitwer Name: Letha Dawson Applicant: Mount Cannel Academy Di.uterlEmergencylProgramlProject Title: DRI603LA I Hurricane Katrina I Public Assistance Program! EORl149·Louviere Dining CenterPennanent Repairs Record of Environmental Consideration See 44 Code of Federal Regulation Part 10. Project NamelNumber: Louviere Dining Center-Permanent Repairs I PW 11425 Project Location: 7027 Milne Blvd., New Orleans, Louisiana, Orleans Parish, 70124 (N 30.01944, W -90.11055) Project Description: Project activities involve removing and replacing floor tile, ceiling tile, drywall, carpet, doors, frames, windows, electrical equipment, communication equipment, china cabinets, shelves, desk, gondola, self hanging units, bunker unit, slat wall panels, T -stands, roof and skylights. Some mitigation will be achieved by compliance with current codes and standards and by good construction practices. Documentation Requirements o No Documentation Required :-C/3 . Date 0911112006 ----~~~~~------------~ I. Compliance Review for Environmental Laws (other than NEPAl A. National Historic Preservation Act l8J Not type of activity with potential to affect historic properties. (Review Concluded) D Applicable executed Programmatic Agreement (12/0312004) Otherwise, conduct standard Section 106 review. D Activity meets Programmatic Allowance # __ Are project conditions required? D Yes (see section V) D No (Review Concluded) mSTORIC BUILDINGS AND STRUCTURES l8J No historic properties that are listed or 45150 years or older in project area. (Review Concluded) D Building or structure listed or 45150 years or older in project area and activity not exempt from review. D Determination ofNo Historic Properties Affected (FEMA fmdinglSHPOffHPO concurrence on file) Are project conditions required? D Yes (see section V) D No (Review Concluded) D Determination of Historic Properties Affected (FEMA fmdingiSHPOffHPO concurrence on file) D Property a National Historic Landmark and National Park Service was provided early notification during the consultation process. If not, explain in comments D No Adverse Effect Determination (FEMA findinglSHPOffHPO concurrence on file). Are project conditions required? D Yes (see section V) D No (Review Concluded) D Adverse Effect Determination (FEMA fmdinglSHPOffHPO concurrence on file) D Resolution ofAdverse Effect completed. (MOA on file) Are project conditions required DYes (see section V) D No (Review Concluded) ARCHEOLOGICAL RESOURCES l8J Project affects only previously disturbed ground. (Review Concluded) D Project affects undisturbed ground. D Project area has no potential for presence ofarcheological resources D Determination ofno historic properties affected (FEMA findingiSHPOffHPO concurrence or consultation on file). (Review Concluded) D Project area has potential for presence of archeological resources D Determination ofno historic properties affected (FEMA findingiSHPOffHPO concurrence on file) Are project conditions required D Yes (see section V) D No (Review Concluded) D Determination ofhistoric properties affected D NR eligible resources not present (FEMA findinglSHPOffHPO concurrence on file). Are project conditions required DYes (see section V) D No (Review Concluded) D NR eligible resources present in project area (FEMA fmdingl SHPOffHPO concurrence on file) D No Adverse Effect Determination. (FEMA findingl SHPOffHPO concurrence on file) Are project conditions required? D Yes (see section V) D No (Review Concluded) D Adverse Effect Determination. (FEMA fmdingl SHPO/THPO concurrence on file) Revirwer Name: Letha Dawson Appliunt: Mount Cannel Academy DlsasterlEmergenc:ylProgramIProjut Title: DR I603LA I Hurricane Katrina I Public Assistance Program! EOR1149-Louviere Dining CenterPermanent Repairs o Resolution ofAdverse Effect completed. (MOA on file) Are project conditions required? 0 Yes (see section V) 0 No (Review Concluded) Comments: 07/1812006 -This structure does not meet 45-year-criterion or the level ofexceptional importance required by Criterion G of the National Register guidelines to be considered eligible for the National Register ofHistoric Places. Therefore, the proposed work will have no effect on historic structures. -V. Gomez, Historic Preservation Specialist Correspondence/Consultation/References: B. Endangered Species Act 181 No listed species and/or designated critical habitat present in areas affected directly or indirectly by the Federal action. (Review Concluded) o Listed species and/or designated critical habitat present in the areas affected directly or indirectly by the Federal action. o No effect to species or designated critical habitat. (See comments for justification) Are project conditions required? 0 Yes (see section V) 0 No (Review Concluded) o May affect, but not likely to adversely affect species or designated critical habitat (FEMA determinationlUSFWS/NMFS concurrence on file) (Review Concluded) Are project conditions required? 0 Yes (see section V) D No (Review Concluded) o Likely to adversely affect species or designated critical habitat D Formal consultation concluded. (Biological Assessment and Biological Opinion on file) Are project conditions required? D YES (see section V) 0 NO (Review Concluded) Comments: None Correspondence/Consultation/References: C. Coastal Barrier Resources Act 181 Project is not on or connected to CBRA Unit or Otherwise Protected Area (Review Concluded). o Project is on or connected to CBRA Unit or Otherwise Protected Area. (FEMA determinationlUSFWS consultation on file) D Proposed action an exception under Section 3505.a.6? (Review Concluded) o Proposed action not excepted under Section 3505.a.6. Are project conditions required? 0 YES (see section V) D NO (Review Concluded) Comments: None Correspondence/Consultation/References: D. Clean Water Act 181 Project would not affect any waters of the U.S. (Review Concluded) o Project would affect waters, including wetlands, of the U.S. o Project exempted as in kind replacement or other exemption. (Review Concluded) D Project requires Section 404/401l0r Section 9/10 (Rivers and Harbors Act) permit, including qualification under Nationwide Permits. Are project conditions required? 0 YES (see section V) 0 NO (Review Concluded) Comments: None Correspondence/Consultation/References: E. Coastal Zone Management Act D Project is not located in a coastal zone area and does not affect a coastal zone area (Review concluded) [:gJ Project is located in a coastal zone area and/or affects the coastal zone 181 State administering agency does not require consistency review. (Review Concluded). o State administering agency requires consistency review. Are project conditions required? D YES (see section V) D NO (Review Concluded) 09/11/06 Rtviewtr Namt: Letha Dawson Applicant: Mount Carmel Academy DlsuttrlEmtrgtncylProgramlProjtct nalt: DRI603LA I Hurricane Katrina I Public Assistanct Program! EORl149-Louviere Dining Center ~~anemrR~~~la~in~______________________________________________________________________, Comments: This project is located within the Louisiana Coastal Management Zone. LA DNR has determined that receipt offederal assistance is consistent with the Louisiana Coastal Resource Program. Projects within the Coastal Zone may still require a Coastal Use Permit or other authorization from DNR. Projects may be coordinated by contacting LA DNR at 1-800-267-4019. Correspondence/Consultation/References: F. Fish and Wildlife Coordination Act t8J Project does not affect, control, or modify a waterwaylbody of water. (Review Concluded) o Project affects, controls or modifies a waterwaylbody of water. o Coordination with USFWS conducted o No Recommendations offered by USFWS. (Review Concluded) o Recommendations provided by USFWS. Are project conditions required? 0 YES (see section V) 0 NO (Review Concluded) Comments: None Correspondence/Consultation/References: G. Clean Air Act t8J Project will not result in permanent air emissions. (Review Concluded) o Project is located in an attainment area. (Review Concluded) o Project is located in a non-attainment area. o Coordination required with applicable state administering agency.. Are project conditions required? 0 YES (see section V) 0 NO (Review Concluded) Comments: None Correspondence/Consultation/References: H. Farmland Protection Policy Act t8J Project does not affect designated prime or unique farmland. (Review Concluded) o Project causes unnecessary or irreversible conversion of designated prime or unique farmland. o Coordination with Natural Resource Conservation Commission required. o Farmland Conversion Impact Rating, Form AD-1006, completed. Are project conditions required? 0 YES (see section V) 0 NO (Review Concluded) Comments: None Correspondence/Consultation/References: I. Migratory Bird Treaty Act o Project not located within a flyway zone.