U.S. Department of Homeland Security Federal Emergency Management Agency FEMA-1603/1607-DR-LA 415 N 151~ Street Baton Rouge, LA 70802 FEMA August 16, 2006 Johnny Gonzales GOHSEPPAO FEMA-1603-DR-LA 415 N. 15th Street Baton Rouge, Louisiana 70802 RE: Alternative Arrangements, Reconstruction of Critical Infrastructure in the New Orleans Metropolitan Area, John Q. Adams Middle School, Jefferson Parish Public School System, PW#: 11542, DR-1603-LA, PA ID: 051-U415A-00 Dear Mr. Gonzales: The purpose ofthis letter is to notify you that the Public Assistance project for John Q. Adams Middle School, 5525 Henican Place, (30.0262N, 90.2098W), qualifies for the National Environmental Policy Act (NEPA) Alternative Arrangements for the Reconstruction ofCritical Infrastructure in the New Orleans Metropolitan Area. Under the regular Federal Emergency Management Agency (FEMA) NEPA review process; this project would have qualified for categorical exclusion in accordance with 44 CFR Part 10.8(d)(2)(xv). However, due to the unprecedented number of grants requested that need to be processed in a short time, the potential cumulative effects, and potential environmentally-related socio-economic effects ofFEMA's funding in the New Orleans Metropolitan Area, FEMA has determined that this type ofaction may have significant impacts that cannot be reviewed under the normal Environmental Impact Statement (EIS) process. FEMA, the Department of Homeland Security (DHS), and the Council on Environmental Quality (CEQ) have adopted the Alternative Arrangements to address the basic elements ofNEPA under these circumstances. For more information visit www.fema.gov/planlehp/nomalindex.shtm. While the use of Alternative Arrangements meets NEPA compliance requirements, there are requirements of other Environmental and Historic Preservation (EHP) laws and executive orders that must be individually complied with. For the work described in this Project Worksheet (PW) the following conditions relating to those requirements apply: • Unusable equipment, debris and material shall be disposed of in an approved manner and location. In the event significant items (or evidence thereof) are discovered during implementation ofthe project applicant shall handle, manage, and dispose ofpetroleum products, hazardous materials and/or toxic waste in accordance to the requirements and to the satisfaction ofthe governing local, state and federal agencies. • In accordance with the Formosan Termite Initiative Act, (LA R.S. 3:3391.1 thru 3391.13) the Louisiana parish ofJefferson is under quarantine. The movement ofwood or cellulose material, temporary housing or architectural components (e.g. beams, doors and other wood salvaged from a structure) may not leave the quarantined parish without written authorization from the commissioner ofthe Louisiana Department of Agriculture and Forestry or his designee(s) Johnny Gonzales August 16, 2006 Page 2 • This project is located within the Louisiana Coastal Management Zone. Louisiana Department of Natural Resources (LDNR) has determined that receipt of federal assistance is consistent with the Louisiana Coastal Resource Program. Projects within the coastal zone may still require a Coastal Use Permit (CUP) or other authorization from LDNR. Projects may be coordinated by contacting LDNR at 1-800-267-4019. • This project involves the demolition or renovation ofa public structure. Regardless of the asbestos content, the applicant is responsible for ensuring that renovation or demolition activities are coordinated with the Louisiana Department of Environmental Quality (LDEQ) in accordance with the LDEQ "Sixth Amended Declaration of Emergency and Administrative Order" dated June 30, 2006, incorporating the provisions of the Environmental Protection Agency's (EPA's) National Emission Standards for Hazardous Air Pollutants (NESHAP) and the Louisiana Administrative Code (LAC) 33.iii.5151 and chapter 27. Should Asbestos Containing Materials (ACMs) be present at the project site, the applicant is also responsible for ensuring proper disposal in accordance with the previously referenced administrative order. Please note that this transmittal is a notification that this project has been cleared under NEPA only. This is not a notice of final approval or eligibility. Any change beyond the approved scope of work for this project will require additional environmental review by FEMA. . /~~ vr_':'7_t- Howard ~tu:r4(j.,.,,.v;;II : Environmental Liaison Officer FEMA-1603/1607-DR-LA Enclosures: Project Worksheet (PW) #11542 Cc: Oliver Mack, FEMA DPAO for Grants