Reviewer Name: Catherine Jones Applicant: Jefferson Parish Disaster/Emergency/Program/Project Title: DR1603LA / Hurricane Katrina / Public Assistance Program / Belle Terre Library Record of Environmental Consideration See44CodeofFederalRegulation Part 10. Project Name/Number; BelleTerreLibrary / PW 10146 Project Location: 5500BelleTerreRoad, CityofMarrero, LouisianaJefferson Parish70072 (N29.8791 W-90.10996) Project Description: Project activities include replacing the roof(1200 SF), canopy (28 SF), window panes (63 SF), carpet (161 SY), ceiling tile (1456 SF), insulation (1452 SF), sheetrock (1388 SF), and covebasemolding(109 LF). Hazardmitigationwillbeachievedwithcurrentcodesandstandards. Documentation Requirements • No Documentation Required (Review Concluded) • (Short version) All consultation and agreements implemented to comply with the National Historic PreservationAct,Endangered SpeciesAct,andExecutiveOrders11988,11990and 12898 are completed and no other laws apply. (Review Concluded) ^ (Long version) All applicable laws and executive orders were reviewed. Additional information for compliance is attached to this REC. National Environmental Policy Act (NEPA) Determination • Statutorily excluded from NEPA review. (Review Concluded) • Programmatic Categorical Exclusion -Category (Review Concluded) l~~1 Categorical Exclusion -Category 0 No Extraordinary Circumstances exist. Are project conditions required? • Yes (see section V) • No (Review Concluded) • Extraordinary Circumstances exist (See Section IV). • Extraordinary Circumstances mitigated. (See Section IV comments) Are project conditions required? • Yes (see section V) • No (Review Concluded) l~~l Environmental Assessment O Supplemental Environmental Assessment (Reference EA or PEA in comments) £3 Environmental Impact Statement Comments: This project meets the criteria for an alternative arrangement (Permanent Schools) type ofproject. This project has conditions and requires mitigation under the other EHP laws. Record ofEnvironmental Consideration 1 07/22/06 Reviewer Name: Catherine Jones Applicant: Jefferson Parish Dbaster/Emergency/Program/Project Title: DR1603LA / Hurricane Katrina / Public Assistance Program / Belle Terre Library Reviewer and Approvals d Project is Non-Compliant (See attached documentation justifying selection). FEMA Environmental Reviewer. Name: Catherine Jones, Environmental Specialist Signature ^f^f\^f 19^^ . Date 7/22/2006 , FEMARegional Environmental Officer or delegated approving official. Name: Don Fairley, ELO Signature CR^g—^^ 7/22/2006 /^=S— /*> , Date I. Compliance Review for Environmental Laws (other than NEPA) A. National Historic Preservation Act ^ Not type ofactivity with potential to affect historic properties. (Review Concluded) • Applicable executed Programmatic Agreement Otherwise, conduct standard Section 106 review. [U Activity meets Programmatic Allowance # Are project conditions required? • Yes (see section V) • No(Review Concluded) HISTORIC BUILDINGS AND STRUCTURES ^ No historic properties that are listed or45/50 years orolder inproject area. (Review Concluded) • Building or structure listed or 45/50 years or older in project area and activity not exempt from review. • Determination ofNo Historic Properties Affected (FEMA finding/SHPO/THPO concurrence on file) Are project conditions required? • Yes (see section V) • No (Review Concluded) • Determination ofHistoric Properties Affected (FEMA finding/SHPO/THPO concurrence on file) • Property aNational Historic Landmark and National Park Service was provided early notification during the consultation process. If not, explain in comments • No Adverse Effect Determination (FEMA finding/SHPO/THPO concurrence on file). Are project conditions required? • Yes (see section V) • No (Review Concluded) • Adverse Effect Determination (FEMA finding/SHPO/THPO concurrence on file) • Resolution ofAdverse Effect completed. (MOA onfile) Are project conditions required • Yes (see section V) • No (Review Concluded) ARCHEOLOGICAL RESOURCES £3 Project affects only previously disturbed ground. (Review Concluded) O Project affects undisturbed ground. 1~1 Project area has no potential for presence ofarcheological resources • Determination ofno historic properties affected (FEMA finding/SHPO/THPO concurrence or consultation on file). (Review Concluded) E] Project area has potential for presence ofarcheological resources • Determination ofno historic properties affected (FEMA finding/SHPO/THPO concurrence on file) [ Are project conditions required • Yes (see section V) • No (Review Concluded) j I I Determination ofhistoric properties affected { • NR eligible resources not present (FEMA finding/SHPO/THPO concurrence on file). | Are project conditions required [^Yes (see section V) • No (Review Concluded) f • NR eligible resources present in project area. (FEMA finding/ SHPO/THPO concurrence on I file) | • No Adverse Effect Determination. (FEMA finding/ SHPO/THPO concurrence on file) \ Are project conditions required? • Yes (see section V) • No (Review Concluded) j • Adverse Effect Determination. (FEMA finding/ SHPO/THPO concurrence on file) I EH Resolution ofAdverse Effect completed. (MOA on file) j Record ofEnvironmental Consideration 2 07/22/06 j | I Reviewer Name: Catherine Jones Applicant: Jefferson Parish Disaster/Emergency/Program/Project Title: DR1603LA / Hurricane Katrina / Public Assistance Program / Belle Terre Library Are project conditions required? • Yes (see section V) • No (Review Concluded) Comments: 07/22/2006-Facility is less than 45 years old. Catherine Jones, Environmental Specialist. I Correspondence/Consultation/References: I B. Endangered Species Act I 13 No listed species and/or designated critical habitat present in areas affected directly or indirectly by the Federal action. j (Review Concluded) | • Listed species and/or designated critical habitat present in the areas affected directly or indirectly by the Federal action. | • No effect to species or designated critical habitat (See comments for justification) | Are project conditions required? • Yes (see section V) f~l No(Review Concluded) I • May affect, but not likely to adversely affect species or designated critical habitat (FEMA I determination/USFWS/NMFSconcurrence on file) (Review Concluded) i Are project conditions required? • Yes (see section V) |~1 No (Review Concluded) { • Likely toadversely affect species ordesignated critical habitat I • Formal consultation concluded. (Biological Assessment and Biological Opinion on file) t Are project conditions required? • YES (seesection V) f~1 NO(ReviewConcluded) I Comments: None C. Coastal Barrier Resources Act I 13Project is not on or connected to CBRA Unit orOtherwise Protected Area (Review Concluded). j • Project is on or connected to CBRA Unit or Otherwise Protected Area. (FEMA determination/USFWS consultation on j file) j • Proposed action an exception under Section 3505.a.6? (Review Concluded) { • Proposed action notexcepted under Section 3505.a.6. I Are project conditions required? • YES (see section V) • NO (Review Concluded) I Comments: None Correspondence/Consultation/References: D. Clean Water Act ^ Project would not affect any waters ofthe U.S. (Review Concluded) Q Project would affect waters, including wetlands, ofthe U.S. O Project exempted as inkind replacement orother exemption. (Review Concluded) • Project requires Section 404/401/or Section 9/10 (Rivers and Harbors Act) permit, including qualification under Nationwide Permits. Are project conditions required? • YES (see section V) • NO (Review Concluded) Comments: Project isnot inoradjacentto anywaterways ofthe US. Correspondence/Consultation/References: E. Coastal Zone Management Act CD Projectisnotlocatedina coastalzoneareaanddoesnotaffectacoastalzonearea(Reviewconcluded) ^ Projectislocatedina coastalzoneareaand/oraffectsthecoastalzone £<] State administering agency does not require consistency review. (Review Concluded). O State administering agency requires consistency review. Are project conditions required? • YES (see section V) • NO(Review Concluded Comments: FEMAhasdetermined thatthisprojectisconsistent withtheCoastalZoneManagement ActandtheLouisiana Coastal Management Plan (LCMP). Correspondence/Consultation/References: Record of Environmental Consideration 3 07/22/06 Reviewer Name: Catherine Jones Applicant: Jefferson Parish Disaster/Emergency/Program/Project Title: DR1603LA / Hurricane Katrina / Public Assistance Program / Belle Terre Library F. Fish and Wildlife Coordination Act 13Projectdoes not affect, control, ormodifyawaterway/bodyofwater. (Review Concluded) O Project affects controls ormodifies awaterway/body ofwater. • Coordination with USFWS conducted • No Recommendations offered by USFWS. (Review Concluded) n Recommendations provided by USFWS. Are project conditions required? • YES (see section V) • NO (Review Concluded) Comments: Project is not in or adjacent to any waterways of the US. Correspondence/Consultation/References: G. Clean Air Act E>3 Project will not result in permanent air emissions. (Review Concluded) Q Projectislocatedinanattainmentarea. (Review Concluded) O Projectislocatedina non-attainmentarea. O Coordination required with applicable state administering agency.. Are project conditions required? • YES (see section V) D NO (Review Concluded) Comments: Projectwillnot resultinpermanentair emissions. Correspondence/Consultation/References: H. Farmland Protection Policy Act £3 Project does not affect designated prime orunique farmland. (Review Concluded) C]Project causes unnecessary or irreversible conversion ofdesignated prime or unique farmland. I~[ Coordination with Natural Resource Conservation Commission required. • Farmland Conversion Impact Rating, Form AD-1006, completed. Are project conditions required? • YES (see section V) • NO(Review Concluded) Comments: None Correspondence/Consultation/References: I. Migratory Bird Treaty Act • Project not located within a flyway zone. (Review Concluded) G3 Project located within a flyway zone. [3 Project does not have potential totake migratory birds. (Review Concluded) Are project conditions required? Q Yes (see section V) [3 No(Review Concluded) CH Project has potential totake migratory birds. • ContactmadewithUSFWS Are project conditions required? • YES (see section V) • NO (Review Concluded) Comments: See letter from Don Fairley to Mr. Russ Watson with USF&WS, dated 09/14/2005. Specifically, FEMA has determinedthat restoration projects funded with federal resources will nothave adverse impactsonmigratory birdsorother fishand wildlifereserves. Thesedeterminationsarebasedonthe understandingthatthe conditionsoutlinedinthe Louisiana Endangered Species Summaryare met. Correspondence/Consultation/References: http://pacificflvway.gov/Documents/Mississippi map.pdf, J. Magnuson-Stevens Fishery Conservation and Management Act ^ Project notlocated inornear Essential Fish Habitat. (Review Concluded) • Project located inornear Essential Fish Habitat. • Project does not adversely affect Essential Fish Habitat. (Review Concluded) Are project conditions required? • Yes (see section V) • No(Review Concluded) • Project adversely affects Essential Fish Habitat (FEMA determination/USFWS/NMFS concurrence on file) Record of Environmental Consideration 07/22/06 Reviewer Name: Catherine Jones Applicant: Jefferson Parish Disaster/Emergency/Program/Project Title: DR1603LA / Hurricane Katrina / Public Assistance Program / Belle Terre Library • NOAA Fisheries provided norecommendation(s) (Review Concluded). Are project conditions required? Q Yes (see section V) • No(Review Concluded) • NOAA Fisheries provided recommendation(s) d Written reply toNOAA Fisheries recommendations completed. Are project conditions required? • YES (see section V) • NO (Review Concluded) Comments: None Correspondence/Consultation/References: K. Wild and Scenic Rivers Act ^ ProjectisnotalonganddoesnotaffectWildorScenicRiver(WSR)-(Review Concluded) O Project isalong oraffects WSR • Project adversely affects WSR asdetermined byNPS/USFS. FEMA cannot fund theaction. (NPS/USFS/USFWS/BLM consultation on file) (Review Concluded) • Project does not adversely affect WSR. (NPS/USFS/USFWS/BLM consultation onfile) Are project conditions required? • YES (see section V) • NO (Review Concluded) Comments: None Correspondence/Consultation/References: L. Other Relevant Laws and Environmental Regulations II. Compliance Review for Executive Orders A. E.0.11988 -Floodplains O No Effect onFloodplains/Flood levels and project outside Floodplain -(Review Concluded) ^ Located inFloodplain orEffects onFloodplains/Flood levels ^ No adverse effect onfloodplain and notadversely affected bythe floodplain. (Review Concluded). Areprojectconditionsrequired? ^ Yes(seesectionV)O No (Review Concluded) Q Beneficial Effect onFloodplain Occupancy/Values (Review Concluded). [~l Possibleadverseeffectsassociatedwithinvestmentinfloodplain, occupancyormodificationoffloodplain environment O 8 StepProcessComplete-documentationonfile Are project conditions required? O YES (see section V) O NO (Review Concluded) Comments: 07/18/2006-Jefferson Parish enrolled in the National Flood Insurance Program (NFIP) 10/1/1971. Per Flood Insurance Rate Map (FIRM) 22051C0135E, dated 03/23/1995, project is located within Zone X, area protected from the 100-year flood by levee, dyke, or other structure subject to failure or overtopping during larger floods. Project is repair building to pre-disaster conditions which is not likely to impact floodplains. Per FEMA flood recovery guidance, dated 04/12/2006, where possible, all equipment and contents should be elevated to either the base flood elevation (BFE) shown on the current effective firm or at least 3 feet above the highest existing adjacent grade (HEAG) at the building site, whichever is higher. Jahn Kallis, Environmental Specialist. Correspondence/Consultation/References: B. E.0.11990-Wetlands E3 NoEffectsonWetland(s) and project located outside Wetland(s) -(Review Concluded) O Located in Wetland or effects Wetland(s) • BeneficialEffectonWetland-(ReviewConcluded) C] Possible adverse effect associated with constructing inornear wetland l~lReview completedaspartoffloodplain review l~l 8Step Process Complete -documentation onfile Are project conditions required? CD YES (see section V) fZ] NO (Review Concluded) Comments: None Record of Environmental Consideration 07/22/06 Reviewer Name: Catherine Jones Applicant: Jefferson Parish Disaster/Emergency/Program/Project Title: DR1603LA / Hurricane Katrina / Public Assistance Program / Belle Terre Library Correspondence/Consultation/References: C. E.0.12898 -Environmental Justice For Low Income and Minority Populations [3 No Low income orminority population in, near oraffected by the project -(Review Concluded) Q Low income orminority population in ornear project area n No disproportionately high and adverse impact on low income or minority population-(Review Concluded) • Disproportionately high or adverse effects on low income or minority population Are project conditions required? • YES (see section V) • NO (Review Concluded) Comments: None Correspondence/Consultation/References: III. Other Environmental Issues Identify other potential environmental concerns in the comment box not clearly falling under a law or executive order (see environmental concerns scoping checklist for guidance). Comments: None Correspondence/Consultation/References: IV. Extraordinary Circumstances Based on the review of compliance with other environmental laws and Executive Orders, and in consideration of other environmental factors, review the project for extraordinary circumstances. *A"Yes" underanycircumstancemayrequireanEnvironmentalAssessment(EA)withthe exceptionof(ii) which I should beapplied inconjunction with controversy onan environmental issue. Ifthe circumstance canbe mitigated, i please explain in comments. Ifno, leave blank. j i Yes_ | CD (i) Greater scope orsize than normally experienced for aparticular category ofaction S l~l (ii) Actions with ahigh level ofpublic controversy | O (iii) Potential for degradation, even though slight, ofalready existing poor environmental { conditions; { CH (iv) Employment ofunproven technology with potential adverse effects oractions involving J unique or unknown environmental risks; f • (v) Presence ofendangered or threatened species or their critical habitat, or archaeological, \ cultural, historical or other protected resources; ! Q (vi) PresenceofhazardousortoxicsubstancesatlevelswhichexceedFederal,stateorlocal \ regulations or standards requiring action or attention; t [H (vii) Actions with the potential to affect special status areas adversely orother critical resources { such aswetlands, coastal zones, wildlife refuge and wilderness areas, wild and scenic rivers, | soleorprincipaldrinkingwateraquifers; v j • (viii) Potential for adverse effects on health or safety; and J EH (ix) Potential to violate a federal, state, local ortribal law orrequirement imposed for the I protection of the environment. f CD (x) Potential for significant cumulative impact when the proposed action is combined with f other past, present and reasonably foreseeable future actions, even though theimpacts ofthe t proposedactionmaynot be significantby themselves. \ Comments: None V. Environmental Review Project Conditions Record of Environmental Consideration 6 07/22/06 Reviewer Name: Catherine Jones Applicant: Jefferson Parish Disaster/Emergency/Program/Project Title: DR1603LA / Hurricane Katrina / Public Assistance Program / Belle Terre Library Project Conditions: • Per FEMA flood recovery guidance, dated 04/12/2006, where possible, all equipment and contents shouldbeelevatedtoeitherthebase flood elevation (BFE) shownonthecurrent effective firmoratleast3feet above the highest existingadjacentgrade (HEAG)atthe building site, whichever is higher. Monitoring Requirements: None I | i RecordofEnvironmental Consideration 7 07/22/06